IN THE HIGH COURT OF JUDICATURE AT PATNA Civil Writ Jurisdiction Case No.2064 of 2026 ====================================================== Mohan Paswan S/o Late Deo Narayan Paswan, resident of Village-Bourani, P.S.-Dandkhora, District-Katihar. ... ... Petitioner/s Versus
1. The State of Bihar through the Addl. Chief Secretary, Revenue and Land Reforms, Bihar, Patna. 2. The Addl. Chief Secretary Road Construction Department, Govt. of Bihar, Patna. 3. The Divisional Commissioner, Purnea Division, Purnea. 4. The Collector cum District Magistrate, Katihar. 5. The District Land Acquisition Officer, Katihar. 6. The Circle Officer, Dandkhore, Katihar. 7. The General Manager, Bihar State Road Development Corporation Ltd., Patna. 8. The Deputy General Manager (Technical), Bihar State Road Development Corporation Ltd., Purnea. ... ... Respondent/s ====================================================== Appearance : For the Petitioner/s : Mr.Bhola Prasad, Advocate Mr. Ashish Bhaskar, Advocate For the Respondent/s : Mr.Standing Counsel (16) For respondent no.7&8 : Mr. P.K. Shahi, Sr. Advocate Mr. Manish Dhari Singh, Advocate ====================================================== CORAM: HONOURABLE MR. JUSTICE RAJIV ROY ORAL ORDER 4 21-07-2026 Heard Mr. Bhola Prasad, learned counsel for the petitioner and Mr. Manish Dhari Singh, learned counsel for Bihar State Road Development Corporation as also the State. 2. The present application has been preferred for the following relief(s): (i) For quashing the notice dated 30.12.2025 issued by the District Land Acquisition Officer whereby the petitioner
Patna High Court CWJC No.2064 of 2026(4) dt.21-07-2026 2/5 has been remove directed to revenue structure from Plot No. 470, 469 477. (ii) For direction to the respondent concern to consider the claim of the petitioner and after local inspection and measurement fixed the valuation and pay the compensation to the petitioner for acquisition of his land bearing Plot No. 470, 469, 477. (iii) Further till the disposal of the claim of the petitioner respondent concern may be restrained from removing the structure and construction road on the aforesaid plot. And for any other relief (s) for which the petitioner is found to be entitled in the facts and circumstances of the case. 3. The details of land stand incorporated in para-4 and read as under: (i) khata no. 255 and 256; (ii) plot nos. 475 (40 decimal), 476 (70 decimal), 477 (76 decimal) and 471 (1 acre); (iii) area- 2 acre 86 decimal, situated at mouza-Bouriya Gogama, Anchal- Dandhora, Katihar. 4.
Learned counsel for the petitioner submits that
Patna High Court CWJC No.2064 of 2026(4) dt.21-07-2026 3/5 though for preparing the Award for the land, the structure that is existing there, no payment is being made and the stand has been taken that it has come after the intention of respondent to acquire the land. However, submission is that it will suffice if the respondent no.04, the Collector, Katihar looks into the matter and take appropriate steps. 5. Learned counsel representing the respondents have no objection to it. 6. Having heard the parties, this Court allows the petitioner to approach the Collector, Katihar to agitate the matter who shall be passing a reasoned order in accordance with law after noticing all the relevant parties. However, this Court has taken note of the letter dated 11.02.2021 issued by the Additional Chief Secretary, Revenue and Land Reforms Department (Land Acquisition Directorate, Bihar, Patna) (henceforth for short ‘the Revenue Department’) which has taken note of the fact that repeatedly, it has come to the knowledge that Six Men Committee recommendation are always set aside and as such taking into account the aforesaid fact, no further Six Men Committee should make recommendation and Clause-9 to this effect be deemed deleted. 7.
7. The letter dated 11.02.2021 read as follows:
Patna High Court CWJC No.2064 of 2026(4) dt.21-07-2026 4/5 i=kad&14@Mh0,y0,0 ,y0,0,DV ¼fu/kkZj.k lfefr½&19@2017 162@jk0 fcgkj ljdkj jktLo ,oa Hkwfe lq/kkj foHkkx ¼Hkw&vtZu funs'kky;½ izs"kd] foosd dqekj flag] vij eq[; lfpoA lsok esa] lHkh lekgrkZ] fcgkjA iVuk] fnukad%& 11-02-2021 fo"k;%& fofHkUu dsUnzh; ,oa jktdh; ifj;kstuk gsrq vftZr@vf/kxzfgr Hkwfe dk nj fu/kkZj.k ds fy, legrkZ dh v/;{krk esa mfpr izfrdj] iquokZlu vkSj iquO;ZoLFkkiu lfefr dk xBuA izlax%& jktLo ,oa Hkwfe lq/kkj foHkkx dk i=kad&450] fnukad&12-04- 2017 egk'k;] mi;qZDr fo"k;d izklafxd i= ds laca/k esa dguk gS fd RFCTIARR Act- 2013 dh /kkjk&26 esa lekgrkZ ds }kjk Hkwfe ds cktkj ewY; (Market Value) dk vfHkfu/kkZj.k djus dk izko/kku gSA mDr vkyksd esa izklafxd i= ds }kjk fofHkUu dsUnzh; ,oa jktdh; ifj;kstuk gsrq vftZr@vf/kxzfgr Hkwfe dk nj fu/kkZj.k ds fy, lekgrkZ dh v/;{krk esa mfpr izfrdj] iquokZlu vkSj iquO;ZoLFkkiu lfefr dk xBu djrs gq, izklafxd i= ds dafMdk&9 ds }kjk ,u0,p0 vf/kfu;e&1956 ,oa jsyos fo'ks"k vf/kfu;e 2008 ds rgr~ vtZuk/khu@vf/kxzfgr Hkwfe ds izd`fr ,oa fdLe fu/kkZj.k fd;s tkus dk funs'k Hkstk x;k FkkA izklafxd i= ds mijksDr of.kZr dafMdk&9 dh leh{kk dh x;hA leh{kk ds dze esa ik;k x;k fd dfri; ekeyksa esa ,u0,p0,DV dh /kkjk&3G(3) ds rgr competent authority ds }kjk iapkV ?kks"k.kk ds le; lekgrkZ dh v/;{krk esa xfBr N% lnL;h; lfefr dh vuq'kalk ugha ekuh tkrh gS vkSj fcuk fdlh oS/kkfud vkSfpR; ds legkRrkZ dks vuko';d :i ls U;kf;d ekeyksa esa i{kdkj cuk;k tkrk gSA iz'kklfud n`f"Vdks.k ls Hkh lekgrkZ dh v/;{krk esa xfBr lefr dh vuq'kalk ij Hkwfe lq/kkj mi lekgrkZ Lrj ds inkf/kdkjh (CALA) }kjk vafre fu.kZ; fy;k tkuk iz'kklfud inlksiku ds izfrdwy gSA vr,o mijksDr ifjis{; esa leh{kksijkar izklafxd i= dh dafMdk&9 dks foyksfir fd;k tkrk gSA bl laca/k esa izklafxd i= dks
Patna High Court CWJC No.2064 of 2026(4) dt.21-07-2026 5/5 bl gn rd la'kksf/kr le>k tk;A vuqjks/k gS fd rnuqlkj dkjZokbZ djus dh d`ik dh tk;A fo'oklHkktu g0@& ¼foosd dqekj flag½ vij eq[; lfpoA (emphasis added)
8. The Collector, Katihar while taking up the matter of the petitioner shall also look into the aforesaid aspect and is duty bound to deal with it before a reasoned order is passed in the matter. 9. The writ petition is disposed of with the aforesaid observation. 10. This Court expect that the entire exercise must be completed by 31.12.2026. Ravi/- (Rajiv Roy, J) U