$~56 * IN THE HIGH COURT OF DELHI AT NEW DELHI + O.M.P.(MISC.)(COMM.) 375/2026
SLIPCO CONSTRUCTIONS PVT LTD
.....Petitioner Through: Mr. Rohit Rattu & Mr. Gaurav Singh, Advs.
versus
BHARAT HEAVY ELECTRICALS LTD .....Respondent Through: Mr. Surjendu Sankar Das & Ms. Annie Mittal, Advs.
CORAM:
HON'BLE MR. JUSTICE AVNEESH JHINGAN
O R D E R %
07.05.2026
1. This petition is filed under Section 29A of the Arbitration & Conciliation Act, 1996 seeking extension of period for concluding the arbitration proceedings.
2.
Learned counsel for the respondent has no serious objection to the prayer made.
3. In view of the above, the time period for conclusion of the proceedings is extended by three months w.e.f. 11.04.2026 as prayed for.
4. This petition is disposed of in the aforesaid terms.
AVNEESH JHINGAN, J MAY 7, 2026 Ch