20.01.2026 Court No.7 Swd WPA 26507 of 2025
Rubaitul Islam Vs.
WBSEDCL & Ors.
Mr. Indranil Halder, Mr. Neha Singh. … for the Petitioner. Mr. Asif Dewan. … for the WBSEDCL.
1. The grievance of the petitioner is directed against the failure of the respondent WBSEDCL to provide an electricity connection for the submersible pump belonging to the petitioner.
2. On behalf of the WBSEDCL it is submitted that the necessary formalities of boring and providing a separate electric metre room have not complied with. In response, the petitioner submits that all such formalities have since been complied with.
3. In view of the above submissions made on behalf of the parties, WPA 26507 of 2025 stands disposed of by directing the WBSEDCL to provide an electricity connection at the subject submersible pump on the condition that the petitioner has complied with all statutory prescribed formalities.
4. It is clarified that the above exercise be completed within four weeks from the date of communication of this order.
(RAVI KRISHAN KAPUR, J.)