2026 DAILYLAW 8732 (RAJ)

JCL INFRA PRIVATE LIMITED v. JAIPUR DEVELOPMENT AUTHORITY

CW/17571/2024 · 2026-06-02

Sameer Jain

body2026

Judgment text

Extracted from the PDF above. The PDF is authoritative.

[2026:RJ-JP:20730] HIGH COURT OF JUDICATURE FOR RAJASTHAN BENCH AT JAIPUR S.B. Civil Writ Petition No. 8120/2025 JCL Infra Private Limited, Having Its Registered Office At Industrial Estate, Delhi Road, Partapur, Meerut - 250103 Through Its Managing Director Mr. Ajai Kumar Gupta. ----Petitioner Versus 1. Jaipur Development Authority, Through Its Secretary, Ram Kishor Vyas Bhawan, Indira Circle, Jawahar Lal Nehru Marg, Jaipur-302004. 2. Commissioner, Jaipur Development Authority, Ram Kishor Vyas Bhawan, Indira Circle, Jawahar Lal Nehru Marg, Jaipur Rajasthan, 302005. 3. Executive Engineer - ROB/RUB-V, Jaipur Development Au- thority, Ram Kishor Vyas Bhawan, Indira Circle, Jawahar Lal Nehru Marg, Jaipur-302004 ----Respondents Connected With S.B. Civil Writ Petition No. 17571/2024 JCL Infra Private Limited, Having Its Registered Office At Indus- trial Estate, Delhi Road, Partapur, Meerut - 250103 Through Its Authorized Signatory Mr. Ajai Kumar Gupta. ----Petitioner Versus 1. Jaipur Development Authority, Through Its Commissioner, Ram Kishor Vyas Bhawan, Indira Circle, Jawahar Lal Nehru Marg, Jaipur - 302004. 2. Jaipur Development Authority, Through Its Executive En- gineer - Traffic - Ii, Room No. 110, Ff, Main Building, Ram Kishor Vyas Bhawan, Indira Circle, Jawahar Lal Nehru Marg, Jaipur - 302004. 3. Sincere Architects Engineers Pvt. Ltd., 42, Lal Singh Judo Colony, Near Jaipuria Hospital, Tonk Road, Jaipur, Ra- jasthan - 302018. Through Its Authorized Signatory. ----Respondents [2026:RJ-JP:20730] (2 of 106) [CW-8120/2025] For Petitioner(s) : Mr. S. S. Hora with Mr. Adesh Arora Mr. OP Singh Tanwar For Respondent(s) : Mr. Amit Kuri with Mr. Ayush Sharma Mr. Devendra Gupta, Director Engineer JDA-1 HON'BLE MR. JUSTICE SAMEER JAIN JUDGMENT REPORTABLE : 1. Arguments Concluded on: 23.04.2026 2. Judgment Reserved on: 23.04.2026 3. Full Judgment/Operative Part Pronounced: Full Judgment 4. Pronounced on: 02.06.2026 1. In the present batch of writ petitions, the scope of the controversy involved, albeit not limited to but is broadly and predominantly defined as enumerated ad infra: SBCWP No. 8120/2025: Is filed assailing the arbitrary and illegal actions of the respondents whereby the respondents have re-invited tender including the component of OTS Flyover in respect of preparation of detailed project report (hereinafter referred to as ‘DPR’) for proposed elevated road from Transport Nagar to Balagi Tri Junction, Jagatpura and from Jothwara at OTS junction, JLN Marg, JDA Jaipur, to extent of flyover at OTS Junction vide NIB No. EE-ROB/RUB-B/01/2025-26 dated 03.04.2025; primarily being governed by the Public Works Financial and Accounts Rules, Part-II. SBCWP No. 17571/2024: Is filed assailing the letter dated 24.04.2024 issued by the Jaipur Development Authority [2026:RJ-JP:20730] (3 of 106) [CW-8120/2025] (hereinafter referred to as ‘JDA’), thereby withdrawing the work allotted to the petitioner vide the Letter of Acceptance No. JDA/EE/TR WORKS-II/LOA/2022-2023/DEC/01 (hereinafter referred to as ‘LoA’) dated 14.12.2022, without affording any rationale of such withdrawal. Consequently, considering the fact that the writ petitions warrant adjudication on common questions of law and fact; with the consent of learned counsel appearing on behalf of all the parties, S.B. Civil Writ Petition No. 8120/2025 titled as JCL Infra Private Limited V. Jaipur Development Authority and Ors. is being taken up as the lead case. It is cautiously clarified that any discrepancies in the present batch of writ petitions, pertain purely to the factual narratives contained therein and not vis-a-vis the questions of law to be determined by this Court; the instant judgment shall be applicable on both the petitions connected herein/henceforth on mutatis mutandis basis. SUBMISSIONS ADVANCED AND CONTENTIONS PROFFERED BY THE LEARNED COUNSEL APPEARING FOR AND ON BEHALF OF THE PETITIONER HEREIN ARE AD-SERIATIM: 2. At the threshold, and before adverting to the substantive arguments, the chronological particulars giving rise to the instant controversy, as submitted by the learned counsel appearing for and on behalf of the petitioner are set forth hereinbelow: 2.1 At the very outset, learned counsel appearing on behalf of the petitioner submitted that the petitioner is a company duly [2026:RJ-JP:20730] (4 of 106) [CW-8120/2025] incorporated under the provisions of the Companies Act, 2013, bearing CIN U24231UP1980PTC005098, and having its registered office in Meerut. It was submitted that the petitioner has been constrained to approach this Court on account of the manifestly arbitrary, capricious, and unlawful actions of the respondent authorities in re-inviting consultancy services for the preparation of a DPR in respect of the OTS Flyover, notwithstanding the undisputed position that the DPR for the said project had already been prepared and the work stood duly awarded to the petitioner, pursuant to a valid and concluded tender process, and that the petitioner has, in furtherance thereof, incurred substantial financial expenditure and mobilised significant resources of men and machinery. 2.2 It was submitted that the respondents issued a Notice Inviting Bid bearing NIB No. EE-ROB/RUB-B/01/2025-26 dated 03.04.2025 for “Consultancy Services for Preparation of DPR for proposed elevated road from Transport Nagar to Balagiri Tri Junction, Jagatpura and from Jhotwara ROB to Khatipura ROB and flyover at OTS Junction, JLN Marg, JDA Jaipur.” Learned counsel had clarified that the petitioner has confined its challenge only to that segment of the impugned NIB which pertains to the OTS Flyover, inasmuch as the said project had already been awarded to the petitioner through a lawful tendering process and was already under active execution. 2.3 Elaborating further, it was submitted that the petitioner had been awarded the EPC contract vide LoA dated 14.12.2022 [2026:RJ-JP:20730] (5 of 106) [CW-8120/2025] bearing No. JDA/EE TR Works-II/LOA/2022-2023/Dec/01 for the work of “Traffic improvement and beautification work at OTS Crossing, JLN Marg, JDA Jaipur,” which was predicated upon a DPR earlier prepared by the respondents’ appointed consultants, namely, Sincere Architects Engineers Pvt. Ltd. Pursuant thereto, a valid and binding Contract Agreement bearing No. 01/2022-23 came to be executed between the parties on 27.12.2022, and that the said DPR itself was the culmination of a prior tender process wherein Sincere Architects Engineers Pvt. Ltd. had been duly selected, and on the strength of which the petitioner emerged as the successful bidder for execution of the EPC contract. Learned counsel submitted that in pursuance of the said contract, the petitioner duly mobilised its men, machinery, and financial resources, and commenced execution of the work strictly in accordance with contractual stipulations. The petitioner submitted various survey reports, investigations, and detailed design documents through communications dated 23.02.2023, 24.02.2023, 27.02.2023, 02.03.2023, and 13.03.2023, and further sought requisite approvals, including vide letter dated 17.03.2023, for execution of the flyover and allied works at the OTS crossing. It was vehemently contended that despite scrupulous adherence by the petitioner to all contractual obligations, inter alia, submission of disposal plans, traffic movement plans, and detailed engineering drawings through letters dated 22.03.2023, 27.03.2023, 11.04.2023, and 26.04.2023, the respondents failed to accord the necessary site approvals, thereby stultifying the progress of the project. It was [2026:RJ-JP:20730] (6 of 106) [CW-8120/2025] submitted that the petitioner made repeated representations on 28.03.2023, 25.05.2023, 01.09.2023, 20.02.2024, and 05.01.2024 seeking approvals; however, the respondents remained supine and failed to discharge their corresponding contractual obligations. 2.4 As a consequence of such inaction, the petitioner has suffered grave financial prejudice, with men and machinery lying idle and investments aggregating approximately Rs. 40 Crores already having been made, out of which work to the extent of Rs. 20.41 Crores stood completed and duly communicated to the respondents. it was further submitted that despite repeated requests, including communications dated 01.11.2023, 26.12.2023, and 20.02.2024, no payments were released by the respondents, nor was any communication forthcoming. Subsequently, to the utter astonishment of the petitioner, that the respondents issued a letter dated 03.01.2024 alleging that no drawings had been submitted, in complete disregard of the extensive documentation furnished by the petitioner between 27.02.2023 and 03.01.2024. It was further contended that paradoxically, thereafter, the respondents issued a project extension letter dated 04.01.2024 extending the completion timeline till 30.04.2024, thereby unequivocally acknowledging both the subsistence of the contract and the satisfactory progress of the petitioner’s work. 2.5 In response, to the said time extension the petitioner furnished a comprehensive representation dated 05.01.2024 [2026:RJ-JP:20730] (7 of 106) [CW-8120/2025] detailing the progress achieved and sought payment on account of price variation arising from the extended contractual period beyond twelve months, vide letter dated 08.01.2024; however, the same elicited no response from the respondents. It was further contended that during a meeting held on 01.03.2024, certain concerns were raised regarding the technical feasibility of the project at Jhalana Rotary and MNIT Gate opening; however, the said concerns stood conclusively addressed by the respondents’ own consultant, Sincere Architects Engineers Pvt. Ltd., vide letter dated 26.03.2024, affirming the technical feasibility of the project. Despite this, the petitioner’s subsequent request for site instructions vide letter dated 27.03.2024 remained unanswered. 2.6 Learned counsel submitted that in a gross violation of the principles of natural justice and in complete arbitrariness, the respondents, without affording any opportunity of hearing or assigning cogent reasons, invoked Clause 32 of the contract and withdrew the awarded work vide letter dated 24.04.2024. The petitioner, aggrieved thereby, furnished a legal notice dated 10.05.2024 seeking revocation of the said withdrawal, which too went unheeded. Thereafter, Sincere Architects Engineers Pvt. Ltd. submitted a further communication dated 05.07.2024 enclosing final drawings and reaffirming the feasibility of the project, thereby dispelling any residual doubts. It was submitted that the petitioner was constrained to furnish second legal notice dated 26.08.2024, which was similarly disregarded. Aggrieved by such arbitrary withdrawal, the petitioner instituted S.B. Civil Writ [2026:RJ-JP:20730] (8 of 106) [CW-8120/2025] Petition No. 17571/2024, wherein notices were issued on 18.12.2024 and duly served on 20.12.2024. However, during the pendency of the said proceedings, the respondents proceeded to re-invite consultancy bids for the very same project vide NIB dated 03.04.2025, which, inter alia, includes the OTS Flyover, despite the matter being sub judice and despite the petitioner’s prior execution and substantial investment. 2.7 Learned counsel submitted that the impugned action of re-inviting a DPR consultancy tender for the OTS Flyover is nothing short of an attempt to restart the project de novo, in brazen disregard of the DPR already prepared by Sincere Architects Engineers Pvt. Ltd. and the petitioner’s execution of work amounting to Rs. 20.41 Crores and investment of approximately Rs. 40 Crores. Such conduct, is ex facie arbitrary and violative of the doctrine of promissory estoppel, inasmuch as the petitioner acted to its detriment on the basis of the respondents’ unequivocal representations and contractual assurances, and now stands placed in a position of severe financial jeopardy. Learned counsel submitted that Clause 32 of the contract contemplates only partial withdrawal of work and does not sanction unilateral termination of the entire contract. The respondents’ action in withdrawing the whole of the work under the guise of Clause 32 is therefore wholly illegal, unsustainable, and contrary to the express terms of the contract. It was further submitted that the EPC contract provided for stage-wise payments, which were liable to be sub-categorised in terms of the [2026:RJ-JP:20730] (9 of 106) [CW-8120/2025] corrigendum dated 20.10.2022, and the petitioner had duly complied with the same vide its letter dated 31.01.2023. 3. Learned counsel appearing on behalf of the petitioner further submitted that the petitioner is engaged, inter alia, in the execution of large-scale infrastructure development projects, possessing the requisite technical expertise, financial wherewithal, and professional acumen for undertaking complex urban mobility works. It was contended that the OTS Crossing situated on JLN Marg, Jaipur, constitutes one of the most critically congested traffic bottlenecks within the city, plagued by incessant vehicular load and chronic traffic snarls. In order to ameliorate the said congestion and to ensure a signal-free corridor facilitating uninterrupted and seamless vehicular movement, coupled with the augmentation of the aesthetic character of JLN Marg, the respondents conceived a project for traffic improvement and beautification of the said crossing, including the construction of a flyover and allied infrastructural components. Thus, in furtherance of the aforesaid objective, the respondents issued a tender inviting bids for the execution of the said project, thereby initiating a formal procurement process in accordance with law. The said bid was invited under the following title: "Traffic Improvement and beautification work at OTS crossing JLN Marg, JDA Jaipur (Construction of suspended bridge, Traffic Island, Roatries, Underground art gallery, Pedestrian pathway, Sculpture, fountain, improvement of existing drainage system and road surface etc.) on [2026:RJ-JP:20730] (10 of 106) [CW-8120/2025] Engineering Procurement and Construction (EPC) basis." 4. Learned counsel appearing on behalf of the petitioner further submitted that the total EPC contract value, as delineated in the LoA dated 14.12.2022, stood at Rs. 184.30 Crores. It was submitted that the Special Conditions incorporating RPWR-100 were expressly made applicable and formed an integral part of the contract (entered inter-se the parties) in terms of Annexure-19 i.e. the contract agreement, having been mutually agreed upon between the parties. Learned counsel submitted that the stipulated period for commencement and completion of the project was from 06.01.2023 to 05.01.2024. However, the said period was extended vide communication dated 04.01.2024 (Annexure-13) till 30.04.2024, thereby acknowledging the subsistence of the contract and the continuing obligations of the parties. Notwithstanding the same, in a wholly unilateral and ex parte manner, the respondents invoked Clause 32 of the Contract Agreement and withdrew the entire scope of work vide letter dated 24.04.2024, which action has been impugned by the petitioner in S.B. Civil Writ Petition No. 17571/2024. 5. Learned counsel, in order to demonstrate the sequence of events and the manifest arbitrariness of the respondents’ conduct, invited the attention of this Court to the following chronology of material facts: 5.1 That initially, on 02.02.2021 and 03.02.2021, a Letter of Acceptance was issued to consultants for preparation of the DPR, followed by a work order amounting to Rs. 4.58 Crores [2026:RJ-JP:20730] (11 of 106) [CW-8120/2025] (Annexure-4). The said consultants prepared the DPR, which subsequently formed the very foundation for the EPC tender floated by the respondents and ultimately awarded to the petitioner. 5.2 That on 14.12.2022, the respondents issued a LoA in favour of the petitioner awarding the EPC contract for the OTS flyover, based on the DPR prepared by the respondents’ consultants (Annexure-2). This culminated in the execution of a formal Contract Agreement on 27.12.2022 between the petitioner and the respondents, wherein RPWR-100 was incorporated as part of the Special Conditions of Contract. 5.3 That on 31.01.2023, the petitioner addressed a communication to the respondents proposing bifurcation of work and stage-wise payments, as permissible under the corrigendum, thereby demonstrating its readiness to proceed in a structured and compliant manner (Annexure-24). 5.4 That on the same date, the respondents responded to an earlier communication of the petitioner dated 30.01.2023, raising certain queries and requirements with respect to site office arrangements, GAD drawings, traffic diversion plans, and tree- cutting permissions. 5.5 That in compliance thereof, the petitioner, vide letter dated 23.02.2023, sought in-principle approval inter alia, general Arrangement of Bridge Over Nallah on Gopalpur side [Drawing No. OTS/JAIPUR/Nallah Bridge/01 (Conceptual Drawing)]; General Arrangement of Flyover at OTS X-ing [Drawing No. OTS/JAIPUR/Flyover/01 R-3]; Project Plan at OTS Crossing [2026:RJ-JP:20730] (12 of 106) [CW-8120/2025] [Drawing No.OTS/JAIPUR/OVERALL GAD Sheet 01 REV R-1]; Traffic Diversion Plan (Drg. No. OTS/JAIPUR/Traffic Diversion- Sheet 01 REV 1); Land Acquisition Plan (Drg. No. OTS/JAIPUR/Land Acquisition 01 Rev 1) thereby evidencing due diligence and adherence to procedural requirements. 5.6 That despite continuous engagement, the petitioner, vide letter dated 26.12.2023, once again apprised the respondents of the mounting financial losses and requested payment for the work already executed to the tune of Rs. 20.41 Crores. However, in a stark departure from the factual record, the respondents issued a communication dated 03.01.2024 alleging that no drawings had been submitted by the petitioner, in complete disregard of the extensive documentation furnished throughout the year 2023. 5.7 That inconsistently, on the very next day i.e., 04.01.2024, the respondents extended the project deadline till 30.04.2024 without any request from the petitioner, thereby tacitly admitting that the delay was not attributable to the petitioner. 5.8 That the petitioner, vide letter dated 05.01.2024, referred to as many as eighteen prior communications and reiterated that despite submission of all requisite drawings, plans, and reports, no approvals or permissions had been granted, resulting in substantial financial losses (Annexure-8). A comprehensive list evidencing sixty-four communications sent by the petitioner to the respondents was also placed on record (Annexure-10). [2026:RJ-JP:20730] (13 of 106) [CW-8120/2025] 5.8 That the petitioner, vide representation dated 08.01.2024, sought payment on account of price variation occasioned by the extension of the contract beyond twelve months. Thereafter, in a meeting culminating on 26.03.2024, the respondents’ own consultants categorically clarified the technical feasibility of the project, inter alia, stating that the proposed structure would not interfere with the MNIT entrance and that the rotary could be suitably shifted, thereby obviating the need for additional land at OTS (Annexure-16, Pg. 489–491). 5.9 That in light of the aforesaid clarification, the petitioner, vide letter dated 27.03.2024, requested directions to resume and proceed with the pending work. However, instead of facilitating execution, the respondents, in a wholly arbitrary and high-handed manner, invoked Clause 32 of the Contract Agreement and withdrew the entire project vide letter dated 24.04.2024, without issuing any show cause notice or affording an opportunity of hearing (Annexure-18). 5.10 That the petitioner promptly served a legal notice dated 10.05.2024 challenging the illegal withdrawal and seeking revival of the project along with payment of outstanding dues amounting to Rs. 20.41 Crores (Annexure-20). Thereafter, even the respondents’ own consultants, vide communication dated 05.07.2024, furnished detailed drawings, including traffic movement plans, land acquisition requirements, and general arrangement drawings, thereby reaffirming the feasibility and viability of the original DPR (Annexure-21). [2026:RJ-JP:20730] (14 of 106) [CW-8120/2025] 5.11 That the petitioner issued a second legal notice dated 26.08.2024 reiterating its grievances, which also remained not responded. In the interregnum, the respondents, vide letter dated 29.08.2024, called upon the petitioner to collect its bank guarantees amounting to Rs. 5.52 Crores (Annexure P-4), which were thereafter dispatched by post on 16.12.2024 (Annexure P- 5). 5.12 That the petitioner, vide letter dated 24.12.2024, accepted the same under protest (Annexure P-6). 5.13 That in a most arbitrary and untenable development, the respondents issued a fresh Notice Inviting Bid dated 03.04.2025 for preparation of a DPR for the same OTS flyover project, valued at Rs. 6.67 Crores (Annexure-1, Pg. 34), thereby effectively nullifying the earlier DPR, the concluded EPC contract, and the petitioner’s substantial financial investment. Such action, it was submitted, is ex facie illegal, arbitrary, and wholly unsustainable in the eyes of law. 6. Learned counsel appearing on behalf of the petitioner has assailed the impugned withdrawal notice dated 24.04.2024, purportedly issued under Clause 32 of the Contract Agreement, as being ex facie illegal, arbitrary, and vitiated by manifest non- application of mind, qua which it was contended that the said notice is liable to be set aside on, inter alia, the following grounds: 6.1 That the impugned notice is conspicuously vague, bereft of reasons, and wholly non-speaking in nature, thereby failing to disclose any intelligible basis for the drastic action undertaken. Thus, such an unreasoned order stands in stark [2026:RJ-JP:20730] (15 of 106) [CW-8120/2025] contravention of the mandate of Clause 32 of the Contract Agreement, which necessitates a reasoned determination founded upon objective material and due consideration of relevant facts. 6.2 That the impugned notice itself contains a categorical admission to the effect that the work under the contract could not be completed within the stipulated or even the extended period on account of prevailing site conditions and other attendant circumstances. This, unequivocally establishes that the delay was occasioned by factors beyond the control of the petitioner and, therefore, cannot, by any stretch of reasoning, be attributed to any default or lapse on the part of the petitioner. 6.3 That the impugned action is in flagrant violation of the settled principles of natural justice. Clause 32 mandatorily envisages that prior to invoking such a drastic measure, the contractor ought to be afforded a reasonable opportunity of being heard. 7. However, in the present case, no such opportunity was granted to the petitioner, thereby rendering the action wholly arbitrary and unsustainable in law. It was vehemently contended that the doctrine of audi alteram partem has been palpably breached, resulting in grave prejudice to the petitioner and infringing the fundamental rights guaranteed under Articles 14, 19(1)(g), and 21 of the Constitution of India. In support of the said contention, reliance was placed upon the ratio encapsulated in State of Uttar Pradesh vs. Sudhir Kumar Singh & Ors., (2021) 19 SCC 706. [2026:RJ-JP:20730] (16 of 106) [CW-8120/2025] 8. It was further submitted that a plain reading of Clause 32 would reveal that the power of withdrawal cannot be exercised in respect of the entire contract on a wholesale basis. Rather, the said clause contemplates invocation on a “risk and cost” basis, confined to such portion of the work where failure is demonstrably attributable to the contractor. In the present case, however, the respondents have proceeded to withdraw the entire contract without any such attribution or bifurcation, thereby acting in patent excess of their contractual authority. Moreover, the question as to whether the delay is attributable to the petitioner or is a consequence of the respondents’ own lapses, as such failure to hand over the site and non-approval of drawings, stands conclusively answered in favour of the petitioner. It was submitted that repeated delays on account of non-approval by the JDA despite persistent follow-ups by the petitioner, are duly evidenced from communications placed on record. 9. It was further contended that the conduct of the respondents is wholly inconsistent with their present stance. The grant of extension of time without imposition of any liquidated damages, the unilateral release of the bank guarantee, and the subsequent issuance of a fresh tender without invoking the “risk and cost” mechanism or making any reference to Clause 2 of the contract, collectively and unmistakably demonstrate that the delay was neither attributable to the petitioner nor treated as such by the respondents themselves. Learned counsel at this juncture had drawn attention of the Court to the fact that the impugned withdrawal notice itself acknowledges site-related impediments [2026:RJ-JP:20730] (17 of 106) [CW-8120/2025] and other extraneous factors, which, in essence, substantiates the petitioner’s consistent stand. It was further submitted that objections raised by MNIT/OTS in relation to site conditions and execution constraints constituted the principal impediment in carrying out the work, and these factors, being entirely beyond the petitioner’s control, cannot be fastened upon it. 10. Further, it was contended that under the terms of the Contract Agreement, the obligation to hand over the site in a timely and workable condition squarely rested upon the respondents, which obligation they have conspicuously failed to discharge. In this regard, reliance was placed upon relevant Clause in Annexure 3 I.e. contract dated 27.12.2022, which is reproduced as under: “Summary of Work ... Lank is available. If additional land is required, then it shall be made available by JDA." 11. Learned counsel further submitted that the petitioner had duly invoked its contractual entitlement towards price variation on account of delays attributable to the respondents, by way of a detailed communication dated 08.01.2024 (Annexure– 15). It was contended that once such a claim has been raised in consonance with the contractual stipulations, the respondents are estopped from adopting a diametrically opposite stand so as to attribute delay or non-performance upon the petitioner. Learned counsel further submitted that the cumulative circumstances, namely, persistent non-approval of drawings, failure to hand over the site within time, grant of extension without levy of any penalty [2026:RJ-JP:20730] (18 of 106) [CW-8120/2025] or liquidated damages, and the unilateral return of the bank guarantee, unequivocally establish the absence of any default on the part of the petitioner. 12. It was further urged that it is a settled principle of administrative law that an order must stand or fall on the reasons contained therein, and the same cannot be supplemented by subsequent affidavits or justifications sought to be introduced at the stage of reply to the writ petition. Thus, any attempt on the part of the respondents to improve upon or validate the impugned action by introducing fresh grounds dehors the original record is impermissible in law. In support of this proposition, reliance was placed upon the dictum enunciated in Mohinder Singh Gill vs. Chief Election Commissioner, (1978) 1 SCC 405. 13. Learned counsel had next contended that the present case squarely attracts the doctrines of promissory estoppel and legitimate expectation. It was submitted that acting upon the unequivocal assurances and contractual obligations undertaken by the respondents, the petitioner had mobilized extensive resources, conducted surveys, prepared detailed drawings and designs, procured requisite materials, and incurred substantial financial expenditure. In such circumstances, it is impermissible for the respondents to resile from their promise and arbitrarily withdraw the project, particularly on account of extraneous considerations such as a change in government or administrative stance; nonetheless, such conduct, is antithetical to the principles of fairness, reasonableness, and the well-established Wednesbury doctrine governing administrative discretion. It was also [2026:RJ-JP:20730] (19 of 106) [CW-8120/2025] contended that the State, being an instrumentality under Article 12 of the Constitution of India, is under a constitutional and legal obligation to act in a transparent, fair, non-discriminatory, and reasonable manner. The impugned action, whereby the respondents have unilaterally withdrawn the work order for reasons attributable to their own lapses, constitutes a clear abdication of such obligations. 14. In support of the submissions made insofar, learned counsel had placed reliance upon, inter alia, IFGL Refractories Ltd. vs. Orissa State Financial Corporation & Ors., 2020 SCC OnLine SC 208; U.P. Power Corporation Ltd. vs. Sant Steels & Alloys (P) Ltd., (2008) 2 SCC 777; and Sivanandan C.T. vs. High Court of Kerala, (2024) 3 SCC 799. 15. It was further contended that the stand taken by the respondents in their reply reveals that the issuance of a fresh DPR was motivated by a change in governmental policy consequent upon a change in political leadership; however, governance is a continuous process, and the State, as a legal entity, remains bound by its contractual commitments irrespective of political transitions. Thus, the contractual obligations cannot be jettisoned on account of shifting political considerations, as the same would erode the sanctity of contracts and undermine public confidence in governmental dealings. In the conspectus of the aforesaid facts, learned counsel submitted that the project pertaining to the OTS crossing was not conceived as an ad hoc or casual initiative, but rather as a meticulously planned infrastructure undertaking of considerable magnitude, aimed at alleviating traffic congestion [2026:RJ-JP:20730] (20 of 106) [CW-8120/2025] and ensuring seamless vehicular movement along the arterial JLN Road, Jaipur. It was submitted that the petitioner has already invested an amount approximating Rs. 40 Crores in furtherance of the said project and has executed substantial portions of the work. Thence, in such circumstances, the arbitrary withdrawal of the contract, for reasons not attributable to the petitioner, amounts to a gross breach of contractual and constitutional obligations. Sequentially, whilst placing reliance upon the judgment passed in Muhammed Nizar vs. State of Kerala, 2021 Supreme (Ker.) 636, and Vice-Chairman & Managing Director, City and Industrial Development Corporation of Maharashtra Ltd. vs. Shishir Realty Pvt. Ltd., (2022) 16 SCC 527, it was submitted that the respondents cannot be permitted to take a volte-face without cogent and legally sustainable justification, particularly when such action undermines the sanctity of contractual relations and adversely impacts public interest. 16. Learned counsel had also assailed the proposal of a newly conceived flyover, contending that the same reflects a regressive and restrictive approach towards traffic management on JLN Road, allegedly undertaken to accommodate certain influential institutions such as MNIT/OTS. In this regard, reliance was placed upon the dictum encapsulated in State of Tamil Nadu & Ors. vs. K. Shyam Sunder, (2011) 8 SCC 737. It was next contended that the contractual framework governing the petitioner permitted stage-wise payments and sub-categorization of works, as envisaged under the EPC contract and specifically delineated under the head “Payment” (Annexure–3). Learned [2026:RJ-JP:20730] (21 of 106) [CW-8120/2025] counsel submitteds that further clarification in this regard was provided under Note–1 of the corrigendum dated 20.10.2022 (Annexure–23), and the petitioner had duly proposed bifurcation and sub-categorization of works vide letter dated 31.01.2023, thereby permitting rationalization or narrowing of scope along with corresponding financial adjustments. 17. It was further submitted that the State is bound to act fairly even in contractual matters, and the jurisdiction under Article 226 of the Constitution of India is clearly maintainable where the action of the State is arbitrary, illegal, or shocks the conscience of the Court. In support of this proposition, reliance was placed upon the dictum enunciated in Subodh Kumar Singh Rathore vs. Chief Executive Officer & Ors., (2024) 15 SCC 461; ABL International Ltd. & Anr. vs. Export Credit Guarantee Corporation of India Ltd., (2004) 3 SCC 553; and Gujarat State Financial Corporation vs. Lotus Hotels (P) Ltd., (1983) 3 SCC 379. 18. Additionally, it was submitted that the petitioner is entitled to price variation strictly in terms of the contractual provisions, for which a formal requisition had already been submitted upon extension of the contract period. Reliance has been placed upon Clause 45 of the RPWA-100 (Annexure–19), which expressly governs the consideration and applicability of price variation under stipulated conditions; and that the objection raised by the respondents with regard to the locus standi of the petitioner-company is wholly misconceived and untenable. It was submitted that under Order XXIX Rule 1 of the Code of Civil [2026:RJ-JP:20730] (22 of 106) [CW-8120/2025] Procedure, the Managing Director is duly authorized to sign and verify pleadings on behalf of the company. In the present case, a valid Board Resolution dated 09.09.2024 (Annexure P–9) is placed on record, authorizing the institution of the present proceedings. Nevertheless, a company, being a distinct juristic entity, is fully competent to authorize its directors or shareholders to act on its behalf, and such authorization is, at best, a procedural requirement. In support of this contention, reliance was placed upon the authoritative pronouncement of the Hon’ble Supreme Court in United Bank of India vs. Naresh Kumar, (1996) 6 SCC 660. Thus, it was stoutly pleaded that in view of the aforementioned, the objection raised by the respondents deserves to be rejected outright as being devoid of merit, and the instant petitions deserve to be allowed. SUBMISSIONS ADVANCED AND CONTENTIONS PROFFERED BY THE LEARNED COUNSEL APPEARING FOR AND ON BEHALF OF THE RESPONDENTS HEREIN ARE AD-SERIATIM: 19. Per contra, learned counsel appearing for the respondents had, with considerable vehemence, opposed the maintainability as well as the merits of the present writ petitions, advancing the following submissions in a structured and multifold manner: 20. At the very threshold, it was contended that the writ petitions suffer from a foundational defect of maintainability, inasmuch as they are not instituted by a duly authorized and competent person on behalf of the petitioner-company. It was submitted that no valid power of attorney or contemporaneous [2026:RJ-JP:20730] (23 of 106) [CW-8120/2025] authorization in favour of Shri Ajai Kumar Gupta was placed on record, at the time of institution of the proceedings. Therefore, in absence of such specific authorization, the petitions, filed ostensibly on behalf of a juristic entity, are rendered non est in the eyes of law, as per the ratio encapsulated in State of Travancore v. Kingston Computers (P) Ltd., (2011) 11 SCC 524,; thus, the proceedings initiated without proper authorization are liable to be dismissed at the very inception, and so is the instant petition(s). 21. It was further urged that the petitioner had approached this Court with unclean hands and is guilty of gross suppression of material facts; in this regard learned counsel submitted that several communications issued by the JDA spanning a period of approximately fifteen months, highlighting persistent deficiencies in design, structural inadequacies, and non-compliance with contractual obligations, have been deliberately withheld from the Court, by the learned counsel representing the petitioner. Nevertheless, such concealment, strikes at the very root of equitable jurisdiction under Article 226 of the Constitution of India, as also held in the ratio encapsulated in Prestige Lights Ltd. v. State Bank of India, (2007) 8 SCC 449, whereby it was held that suppression of material facts disentitles a petitioner from any discretionary relief. Further, on the substantive plane, it was contended that the lis in question emanates purely from a contractual relationship and is replete with seriously disputed questions of fact. These include, inter alia, attribution of delay, quantification of alleged pre-execution expenditure to the tune of [2026:RJ-JP:20730] (24 of 106) [CW-8120/2025] Rs. 20.41 Crores, interpretation and applicability of contractual clauses, and the propriety of administrative decisions. It was submitted that such issues cannot be adjudicated in writ jurisdiction, which is ill-suited for evidentiary evaluation, and the appropriate remedy lies before competent civil or commercial courts for adjudication and award of damages; in support of the said contention reliance was placed upon the dictum passed in Radhakrishna Agarwal v. State of Bihar, (1977) 3 SCC 457. 22. Justifying the impugned action, learned counsel further submitted that the withdrawal of the work order was squarely in consonance with Clause 32 of the Contract Agreement, which vests wide and unqualified discretion in the Engineer-in-Charge. Elaborating the said contention, it was submitted: 22.1 That the Engineer-in-Charge constitutes a competent authority under the contractual framework; 22.2 That Clause 32, by its very nature, permits withdrawal of the work “for any reason whatsoever,” thereby conferring a broad, non-restrictive power upon the respondents; 22.3 That multiple notices, correspondences, and review meetings addressing delays, non-performance, and deficiencies effectively constituted continuous notice to the petitioner, thereby satisfying the requirements of natural justice, including the princi- ple of audi alteram partem. 23. It was further contended that the EPC contract, being a comprehensive and indivisible framework, does not admit of unilateral modification, reduction, or re-categorization of work in the manner suggested by the petitioner. Learned counsel had [2026:RJ-JP:20730] (25 of 106) [CW-8120/2025] additionally submitted that the respondents invoked the doctrine of public trust and fiscal prudence, qua which it was submitted that the decision to withdraw the contract was guided by paramount public interest, particularly in light of the petitioner’s failure to demonstrate any tangible progress over an extended period of more than one year. It was argued that judicial review in such policy-driven contractual decisions is exceedingly limited. To support the said contention, learned counsel had placed reliance upon the ratio enunciated in Jagdish Mandal v. State of Orissa, (2007) 14 SCC 517, and it was further submitted that where public interest outweighs private commercial considerations, the Court ought to exercise restraint. Auxiliary, amplifying the allegations against the petitioner, it was contended that the petitioner has acted in a manner tantamount to fraud by suppressing critical facts pertaining to the submission and approval of General Arrangement Drawings (GAD), which constituted a sine qua non for commencement of substantive work. Reference was made to the meeting dated 08.02.2023 and document D-22 (letter dated 31.01.2023), evidencing that the drawings submitted were grossly inadequate and fell short of contractual requirements. It was further contended that the petitioner lacks locus standi to assail the subsequent Notice Inviting Bid (NIB) dated 03.04.2025 for DPR consultancy services, on the following grounds: 23.1 That the earlier contract stood validly withdrawn under Clause 32 of the GCC, thereby severing any subsisting legal relationship; [2026:RJ-JP:20730] (26 of 106) [CW-8120/2025] 23.2 That the fresh NIB pertains to an entirely distinct project conceived under the Chief Minister’s Budget 2025–26, involving construction of a flyover at the OTS junction with a significantly altered financial outlay (Rs. 80 crores as against the earlier Rs. 184 crores), rendering both projects mutually exclusive and legally unconnected. 24. It was subsequently submitted that entertaining the present petitions would set a deleterious precedent, enabling unsuccessful or disgruntled contractors to stall or derail public infrastructure projects through protracted litigation, particularly on tenuous grounds of geographical or conceptual overlap. It is also contended that any interim orders passed in the earlier proceedings cannot enure to the benefit of the petitioner in the context of the present, independent tender process. Learned counsel reiterated that the appropriate forum for adjudication of such disputes lies in a full-fledged civil or commercial trial, where evidentiary appreciation can be undertaken, especially in light of Sections 14 and 73 of the Indian Contract Act, 1872. 25. It was further emphatically contended that time was the essence of the contract, which commenced on 06.01.2023 and was to be completed by 05.01.2024. Despite repeated extensions and opportunities, the petitioner failed to adhere to the stipulated timelines and did not achieve even pro-rata progress. Apart from delays, fundamental breaches of essential contractual conditions are alleged, including failure to establish the JDA supervision office, non-submission of comprehensive and approved drawings, absence of a detailed traffic diversion plan in consultation with [2026:RJ-JP:20730] (27 of 106) [CW-8120/2025] traffic authorities, and failure to furnish periodic progress reports and measurement records. Thus, the decision to withdraw the contract was not arbitrary but was preceded by due application of mind, taking into account multiple external factors such as objections raised by MNIT Jaipur (letter dated 29.02.2024), communications from OTS authorities (dated 19.02.2024), concerns relating to the Bisalpur water tank, impediments in piling operations, traffic management constraints, and the necessity to reduce lane configurations from eight to six. These considerations necessitated a fresh DPR and issuance of a new NIB aimed at optimal utilization of public funds with reduced financial burden. Learned counsel had placed reliance upon the ratio enunciated in Air India Ltd. v. Cochin International Airport Ltd., (2000) 2 SCC 617, to submit that in matters of contractual and policy decisions, the State enjoys considerable latitude, and a shift in policy in furtherance of public good must prevail over private commercial interests. Thus, the doctrines of promissory estoppel and legitimate expectation are wholly inapplicable in the present factual matrix, particularly in view of the petitioner’s own defaults, negligible progress, and non-compliance with contractual milestones. The extension of time and release of bank guarantees, demonstrate the bona fide conduct of the respondents and cannot be construed as admission of fault. 26. In culmination, it was submitted that the JDA has acted as a prudent and model public authority, guided by considerations of public interest, financial discipline, and contractual propriety. The impugned action, being lawful, justified, and non-arbitrary, [2026:RJ-JP:20730] (28 of 106) [CW-8120/2025] warrants no interference under writ jurisdiction. Accordingly, it is prayed that the writ petitions be dismissed with exemplary costs. DELIBERATION OF RIVAL CONTENTIONS AND THE ADJUDICATORY FINDINGS: 27. Upon according solicitous consideration to the rival contentions advanced by the learned counsel qua the substantive particulars delineated supra, and upon a meticulous scrutiny of the documentary evidence in conjunction with the governing legal tenets, the judgments cited at the Bar, and the records made available for perusal by the respondent-JDA this court proceedeth to record its opinion, noteworthy record and adjudicatory determinations on the issues framed, ad-seriatim: 28. This Court has carefully perused the pleadings on record, including the writ petitions, replies, rejoinders, and additional documents placed before it. The original records produced pursuant to the directions of this Court by the respondent-JDA have also been minutely examined. Particular attention has been accorded to the Contract Agreement dated 27.12.2022, the General and Special Conditions governing the field, as well as the various communications exchanged between the parties. Upon such comprehensive consideration, this Court is of the opinion that certain aspects emerging from the record assume material significance for adjudication of the controversy at hand. A perusal of the original records produced by JDA, more particularly File No. 5, which pertains to the financial bid and allied decision-making process, reveals certain note sheets that throw considerable light on the manner in which the impugned decision [2026:RJ-JP:20730] (29 of 106) [CW-8120/2025] came to be taken. These note sheets, forming part of the official record, are relevant for examining the decision-making process and the contemporaneous reasoning, if any, which guided the respondents. The said note sheets, as extracted and reproduced from the official records, are set out hereunder for ready reference and consideration: [2026:RJ-JP:20730] (30 of 106) [CW-8120/2025] [2026:RJ-JP:20730] (31 of 106) [CW-8120/2025] [2026:RJ-JP:20730] (32 of 106) [CW-8120/2025] [2026:RJ-JP:20730] (33 of 106) [CW-8120/2025] [2026:RJ-JP:20730] (34 of 106) [CW-8120/2025] [2026:RJ-JP:20730] (35 of 106) [CW-8120/2025] [2026:RJ-JP:20730] (36 of 106) [CW-8120/2025] [2026:RJ-JP:20730] (37 of 106) [CW-8120/2025] [2026:RJ-JP:20730] (38 of 106) [CW-8120/2025] [2026:RJ-JP:20730] (39 of 106) [CW-8120/2025] [2026:RJ-JP:20730] (40 of 106) [CW-8120/2025] [2026:RJ-JP:20730] (41 of 106) [CW-8120/2025] [2026:RJ-JP:20730] (42 of 106) [CW-8120/2025] [2026:RJ-JP:20730] (43 of 106) [CW-8120/2025] [2026:RJ-JP:20730] (44 of 106) [CW-8120/2025] [2026:RJ-JP:20730] (45 of 106) [CW-8120/2025] [2026:RJ-JP:20730] (46 of 106) [CW-8120/2025] [2026:RJ-JP:20730] (47 of 106) [CW-8120/2025] [2026:RJ-JP:20730] (48 of 106) [CW-8120/2025] [2026:RJ-JP:20730] (49 of 106) [CW-8120/2025] Relevant correspondence and note-sheets as on record of JDA, are reproduced as under:- [2026:RJ-JP:20730] (50 of 106) [CW-8120/2025] [2026:RJ-JP:20730] (51 of 106) [CW-8120/2025] [2026:RJ-JP:20730] (52 of 106) [CW-8120/2025] [2026:RJ-JP:20730] (53 of 106) [CW-8120/2025] [2026:RJ-JP:20730] (54 of 106) [CW-8120/2025] [2026:RJ-JP:20730] (55 of 106) [CW-8120/2025] [2026:RJ-JP:20730] (56 of 106) [CW-8120/2025] [2026:RJ-JP:20730] (57 of 106) [CW-8120/2025] [2026:RJ-JP:20730] (58 of 106) [CW-8120/2025] [2026:RJ-JP:20730] (59 of 106) [CW-8120/2025] [2026:RJ-JP:20730] (60 of 106) [CW-8120/2025] [2026:RJ-JP:20730] (61 of 106) [CW-8120/2025] 29. Further, this Court also examined the Contract Agreement along with the Special Conditions governing the execution of the work. The relevant clauses of the Special Conditions of Contract, as forming part of the record produced by the respondent–JDA and applicable to the contractual relationship inter se the petitioner and the respondents, are reproduced hereinbelow for ready reference and proper appreciation of the controversy: Contract For Works General Rules And Directions For the Guidance of Contractors Conditions of contract:- Clause 1: Security Deposit xxxxx Clause 2: Compensation for Delay xxx Note: xxxxxx The contractor shall, further be hornind to carry out the work in accordance with the date and quantity entered. In case the delay inched to the tenderk is attributable to the contractor, the spanwise compensation, as lag down in this clause shall be mandatory. However in case the slow progess in on etime span is covered up within original stipulated period then the amount of such compensation levied earlier shall be refunded. The price escalatiói, if any, admissible under clause 45 of Conditions of Contract would be admissible only on such rates and cost of work, as would be admissible if work would have been carrid out in that particular time span. The Engineer-in. charge shall review the progress achieved in every time span, and grant stagewise extension in čase of slow progress with compensation, if the delay is attributable to contractor, otherwise without compensation. However, if for any special job, a time schedule has been submitted by the contractor before execution of the agreement, and it is entered in agreement as [2026:RJ-JP:20730] (62 of 106) [CW-8120/2025] well as samé has been accepted by the Engineer- in-charge, the contractor shall complete the work within the said time schedule. In the event of the contractor failing to comply with this condition, he shall be liable to pay compensation as this clause shall not exceed 10% of the value of the contract. While granting extension in time attributable to the Government, reasons shall be recorded för each delay. Clause 3 : Risk & Cost Clause The Engineer-in-charge or the Competent Authority defmd under rules may, without prejudice to his rights against the Contractor, in respect of any delay or inferior workmanship or otherwise, or any claims för damages in respect of any breaches of contract and without prejudice to any rights or remedies under any of provisions of this contract or otherwise, and whether the dáte för completion has or has not clapsed by notice in writing, absortek determine the contract in any of the following cases. (i) If Contractor having been given by the Engineer-in-charge, a notice in writing to rectify, reconstruct or replace any defective work or that the work is being performed in any inefficient or otherwise improper or unworkmanlike manner, shall omit to comply with the requirements of such notice för a periód of seven days, thereafter, or if the contractor shall delay or suspend the execution of the work so that either in the judgement of the Engineer-in-charge (which shall be final-and binding) he will be unable to secure completion of the work by the dáte för completion of he already, failed to complete ihe work by that date. (ii) If the Contractor, being company, shall pass a resolution or the Court shall make an order that the company shall be wound up or if a receiver or a manager, on behalf of a creditor, shall be appointed or if circumstances shall arise, which entitle the Court or Creditor to appoint a receiver or a manager or which entitle the Court to make a winding up order. [2026:RJ-JP:20730] (63 of 106) [CW-8120/2025] (iii) If the contractor commits breach of any of the terms and conditions of this contract. (iv) If the Contractor commits any acts mentioned in Clause 19 hereof. when the Contractor has made himself liable for action under any of the cases aforesaid, the Engineer-in-charge on behalf of the Governor of Rajasthan shall have powers ... a)To determine or rescind the contract, as aforesaid (of which determination or rescission notice in Contractor under the hand of the Engineer-in-charge shall be conclusive evidence) upon such determination or notice in writing to the rescission, the earnest money, full security deposit of the contract shall be liable to be forfeited and shall be absolutely at the disposal of the Government. b) To employ labour paid by the Department and to supply materials to debiting the Contractor with the cost of the labour and the price of the materials (of the amount of which cost and price materials to carry out the work or any part of the work, certified by the Engineer-in-charge shall be final and conclusive against the Contractor) and crediting him with the value of the work done in all respects in the same manner and at the same rates, as if it had been carried out by the Contractor under the terms of this contract. The certificate of the Divisional Officer, as to the value of the work done, shall be final and conclusive evidence against the Contractor provided always that action under the sub- clause shall only be taken after giving notice in writing to the Contractor. Frivided also that if the expenses incurred by the department are less than amount payable to the Contractor at his agreement rates, the difference shall not be paid to the Contractor. c) After giving notice to the Contractor to measure up the work of the contractor and to take fuch part thereof, as shall be unexecuted out of his hands and to give it to another contractor to complete, in which čase any expenses which may be "incurred in excess of the sum which would have been paid to the original contractor, if the whole work had been executed by him [of the amount of which excess, the certificate in writing of the Engineer-in-charge [2026:RJ-JP:20730] (64 of 106) [CW-8120/2025] shall be final and conclusivej shall be borne and paid by the originál contractor and may be deducted From any money due to him by Government under this contractor on any other account. Whatsoever, or from his Earnest money. Security Deposit, Enlistment security or the proceeds or sales therof, or a'ufficient part thereof as the ease may be. In the event of any one or more of the above courese being adopted by the Engineer-in-charge, the contractor shall have no claim to compensation tor any loss sustained by him by reason of his having purchased or procured any materials or entered into any engagements or made any advances on account or with a view to the performance of contract. And, in čase action is taken under any of privisions aforesaid, the Contractor shall not be exaction of the work or the entitled to recover or be paid, any work thereof or actually performed under this contract unless and the Engineer-in-charge has certified, in writing, the performance of such work and the value payable in respect thereof, and he shall only be entitled to be paid the value so certified. Clause 4: Contractor remains liable to pay compensation, if action not taken under Clause 3: i) XXXXX ii) In the event of the Engineer-in-charge putting in force, powers vested in hins under the precedin.' Hause 3 he may, if he so desires, také possession of all or any tools, plants, maierials and stores, in or upon the works or the sue, thereof, or belonging to the contractor or procured by him and inteded to be used for the excction of the work or any part thereof, paying or allowing for the same in account, at the contract rates or, in čase of these not being applicable, at current market rates, to b artified by the Chief Engineer or duly authorised Engineer [whose certificate, thereof, shall be final and conclusive]. therwise the Engineer-in chargé may, bè notice in writing to the contractor or his clerk of the works, foreman, or other authorised agent, require him to remove such tools plánt, materials or stores form the [2026:RJ-JP:20730] (65 of 106) [CW-8120/2025] premises [within a time to be specified such notice), and in the event of the Contractor failing to comply with any requisition, the Chief Engineer or other duly athorised Engineer may remove them at the contractors expenses seTl them by auction or priváte såle on.ccount of the contractor and at his risk in all respects, and the certificat; of the Chief Engineer or other duly authorised Engineer is to the expense of any such removai, and the amount of the proceeds and expense of any such Såle shall be final and conclusive against the Contractor. Clause 13: No compensation fór alteration in or restraction of work to be carried out: If, any time after the commencement of the work, the Government, shall för any reason, whatsoever, not require the whole work thereof, as specified in the tender, to bé carried out, the Engineer-in-charge shall give notice in writing, of the fact to the Contractor, who shall have no claim to any paymentys or compensation, whatsoever, on account of any profit or advantage which he might have derived from the execution of the work in full but which he did not derive in consequence of the full amount of the work not having been carried out, Neither, shall he have any claim för compensation by reasons of alterations having made in the originál specifications, drawings and design and instructions, which shall involve any cutrilment of the work, as originally contemplated. Provided, that the contractor shall be paid the charges for the cartage only, of materials, actually brought to theb site of the work by him för bonafide use and rendered surplus as a result of the adandonment or curtailment of the work any portion thereof, and taken them back by the Contractor provided, however that the Engineer-in-charge shall have, in all such cases, the option of taking over all or any such materials at their purchase price or at local market rates whichever may be less. In the čase of such stores, having been issued from Government stores, charges recovered, including storage charges shall be refunded after lacking into [2026:RJ-JP:20730] (66 of 106) [CW-8120/2025] consideration any deduction fór claim on account of any deterioration or damage while in the custody of the contractor, and in this respect the decision of e Engineer-in-charge shall be final. Clause 21: Standing Comniittee for Settlement of disputes: If any question, difference of objection, whatsoever shall arise in any way, in connection with of arising out of this decision of any such matter, as herein before provided has been otherwise provided for and whether it has been finally decided Instrument of the meaning of operation of any part thereof, of the right duties or liabilites of either part then, save in so far, as the accordingly, or whether the contract should be terminated, or has been rightly terminated and as regards the rights or obligations of the parties as the result of such termination, shall be referrred for decision to the empowered Standing Committe, which would consist of the followings. (i) Addutinistrative Secretary concerned. (ii) Finance Secretary or his nominee, not below the rank of Deputy Secretary and/or Chief Accounts officer (iii) Law Secretary or his nominee, not below the rank of Joint Legal Remembrancer. (iv) Chief Engineer-cum-Addi, Secretary of the concerned department. (v) Chief Engineer concerned (Member-Secretary) The Enginner-in-chargem on receipt of application alon with non refufndable prescribed fee, (the fee would be two percent of the amount in dišpute, not exceeding Rs. One lac) from the contractor shall refer the disputes to the committee within a periód of oné month from dnte of receipt of application. Procedure and Application för referring cases för settlement by the Standing Committee shall be as given in Form RPWA90 Clause 32: Withdrawal of work from the Contractor: If the Engineer-in-charge shall at any time and för any reasons, whatever, including inability to maintain prorata progress think [2026:RJ-JP:20730] (67 of 106) [CW-8120/2025] any portion of the work should not be executed or should be withdrawn from the contractor, he may by notice in writing to that effect require the Contractor not to execute the portion of the work specified in the notice, or may withdeaw from the Cotractory the portion of work, so specified, and the Contractor shall nột bé entitled to any compensation, by reason of soul portion of work having been withdrawn from him. The Enginee-in-chagre may supplement the work by engaging another agerevare d portion of the work at the cost of the originalo contractory without prejudice to his rights under clause 2 clause 2. He allo be competent to levy compensation för delay in progress. The recovery of excess cost shall be made from next availar 3 running bili or any other claim and shall nôt bé deferred. Clause 37: Refund of Security Deposit: Security will be refunded after the expiry of the periód as prescribed below :- (a) In case of contract relating to hiring of trucks and other T &P trasnporation including the loading unloading of materials, the amount of Security Deposit is refundable alon with the final bill (b) Suppliers of material: As per privisions of the G.F. & A.R. (c) Ordinary repairs: 3 months after completion of the work provided the final bili has been paid. (d) Originál works/special repairs works: Security deposit will be refunded six months after completion, or expiry of oné full rámy season, or after expiry of defect liability periód as defined in the special condition of agreement, whichever is later provided the final bili has been paid.] (e) In čase of PWD originál works/special repairs works costing more than Rs. 10.00 lacs, partial amount of Security Deposit will be refunded during the defect liability periód @ 10% of ŠD amount after lapse of one year of completion and there after 10% of originál amount of ŠD at the end of each subsequent year. The remaining amount of ŠD bé refunded after the expiry of defect liability periód. [2026:RJ-JP:20730] (68 of 106) [CW-8120/2025] Clause 45: Price Variation Clause: If, during the progress of the contract of value exceeding Rs. 50 lackh (accepted tendered amount minus cost of im supplied 'by the department), and where stipulated completion period'is more than 3 months (both the conditions shoi fulfilled), the price, of any materials/bitumen/diesel/petrol/cement arid steel incorporated'in the works (nôt being materials supplied by the department) and/or wages of labour- increases or decreases, as compared to the price and/or wages prevail; the last dáte of submission of bids the amounts payable to contractors for the work shall be adjusted for increase or decrease in the rates of materials (excepting those materials supplied y the department)/labour/bitumen/diesel and petrol/cement/steel. '[Increase or decrease in the cost of labour /material/bitcemen/diesel/petrol and cement steel shall be calculated quarter accordance with the following formula:] Clause 46: Force Majeure: Neither party shall be liable to each other, för any loss or damage, occasioned by or arising out of acts or God such-as unprecedented floods, volcanic eruptions, earthquake of other invasion of nature and other acts. Clause 48: Post payment Audit & Technical Examination: The Government shall have right to cause an audit and technical examination of the works, and the final bills of the contractor, including all supporting vouchers, abstracts etc., to be made witha-years after payment of the final bili, and if, as a result of Such audit and technical examination, any súm is found to have been over paid in respect of any work done by the Contractor under the contract/or any work claimed by him to have been done by him under the contract and found not to have been executed below specification, the [2026:RJ-JP:20730] (69 of 106) [CW-8120/2025] Contractor shall be liable to refund the amount of over payment,, and it shall be lawful för department to recover the same from him in the manner prescribed in Clause 50 or in any other manner legally permissible and if it is found that the contractor was paid less than what was due to him under the contract in respect of any work executed by him under it, the amount of such under payment shall be duly paid by the Government to the Contractor. Clause 50: Recovery from Contractors: Whenever any claim against the Contractor for the payment of a sum of money arises out of or under the contract, the Department shall be entitled to recover šuch súm bé appropiating in part or whole of the Performance Guarantiee and/or Sceruity Deposit. Security Deposit at the time of enlistment of the Contractor. In the event of the security being insufficinet, or if no security has been taken, therealfirt,, may become due to the Contractor, under this or any other contract with the Governor of Rajasthan. Should this súm bé nôt sufficient to cover the full amount recoverable the Contractor shall pay to he Department on demand the balance remaining dues. The department shall, further, háve the right to effect such recoveries under Public Demands Recovery Act." 30. On the basis of the material available on record, the terms and conditions of the Contract Agreement, as well as the original files produced by the respondent–JDA, the following factual and legal aspects emerge for consideration: 30.1 It is borne out from the record that pursuant to the Budget Declaration for the financial year 2021–2022, the Hon’ble Chief Minister of the State, under the then existing Government, envisaged development of the OTS Crossing, situated on the [2026:RJ-JP:20730] (70 of 106) [CW-8120/2025] prominent Jawahar Lal Nehru Marg (JLN Marg), Jaipur. The said location, being one of the most congested traffic bottlenecks in the city, was identified for comprehensive infrastructural intervention with the avowed objective of ensuring signal-free movement of traffic, easing congestion, and enhancing the aesthetic value of the corridor. 30.2 In furtherance thereof, a tender came to be floated by the Jaipur Development Authority (JDA) with an extensive and composite scope of work, which, inter alia, included “Traffic Improvement and beautification work at OTS Crossing, JLN Marg, JDA Jaipur (Construction of suspended bridge, traffic island, rotaries, underground art gallery, pedestrian pathways, sculptures, fountains, improvement of existing drainage system and road surface, etc.) on Engineering, Procurement and Construction (EPC) basis.” 30.3 The nature of the project thus reflects that it was not merely a construction contract but a holistic urban infrastructure project conceived with both functional and aesthetic objectives. 30.4 The record further reveals that the total contract value under the EPC mode was quantified at Rs. 184.30 Crores. The Letter of Acceptance (LOA) was issued in favour of the petitioner on 14.12.2022, followed by execution of the formal Contract Agreement on 27.12.2022, governed by the General Conditions (RPWR-100) and the Special Conditions forming part thereof. 30.5 As per the contractual stipulations, the date of commencement of the work was fixed as 06.01.2023, with a stipulated period of completion of 12 months, i.e., by 05.01.2024. [2026:RJ-JP:20730] (71 of 106) [CW-8120/2025] It is an admitted position that during the subsistence of the contract, the respondent–JDA granted suo motu extension of time up to 30.04.2024, without levy of any penalty. 30.6 However, prior to the expiry of the extended period, the respondents issued a communication dated 24.04.2024, purporting to withdraw the contract by invoking Clause 32 of the Special Conditions of Contract, which constitutes the primary cause of action for the present proceedings. 30.7 It is further noteworthy that subsequent to such withdrawal, the respondents proceeded to release the petitioner’s bank guarantees on 16.12.2024, unconditionally. The petitioner, however, accepted the same under protest, thereby preserving its right to challenge the underlying action. 31. The petitioner has, thus, approached this Court by way of the present petitions, assailing the legality and validity of the withdrawal of the work order dated 24.04.2024 as being arbitrary and unsustainable; and challenging the subsequent issuance of a fresh Notice Inviting Bid (NIB) dated 03.04.2025, to the extent it pertains to preparation of a DPR for the OTS flyover project, during the pendency of the earlier writ petition. In light of the above factual matrix, it is evident that the first cause of action arose upon issuance of the withdrawal letter dated 24.04.2024, whereby the respondents unilaterally rescinded the contract. The legality, justification, and sustainability of the said communication thus assume central importance in the adjudication of the present dispute. The contents of the said withdrawal letter dated 24.04.2024, being material for examining the decision-making [2026:RJ-JP:20730] (72 of 106) [CW-8120/2025] process and the reasons recorded therein, are reproduced verbatim hereunder: "The aforesaid work was awarded to you vide this office Work Order No JDA/EE TR Works-II/WO/2022-2023/Dec/01 dated 27.12.2022 amounting Rs. 1,84,30,00,000.00 with stipulated dates of commencement and completion as 06.01.2023 and 05.01.2024 respectively. The work was not started during the stipulated period and also cannot be taken-up as per EPC stipulation due to site conditions and various to reasons. Therefore, the competent authority of JDA has taken action as per the relevant clause of agreement (R.P.W.R. 100) and decided to withdraw the whole work of "Traffic improvement and beautification work at OTS crossing JLN Marg, JDA, Jaipur (Construction of suspended bridge, Traffic island, Rotaries, Underground art gallery, Pedestrian pathway, Sculpture, fountain, improvement of existing drainage system and road surface, etc.) on Engineering, Procurement and Construction (EPC) basis" amounting to Rs. 18430.00 lakhs under Clause-32 of the Contract Agreement (R.P.W.R. 100)." 32. The subsequent cause of action arose during the pendency of the earlier writ proceedings, upon issuance of a fresh Notice Inviting Bids (NIB) dated 03.04.2025 (Annexure–1), whereby the respondents initiated a new tendering process for preparation of a Detailed Project Report (DPR), inter alia, covering the development of the OTS flyover. The issuance of the said NIB assumes significance for multiple reasons. Firstly, it pertains, at least in part, to the very subject matter and geographical location forming the basis of the earlier contract awarded to the petitioner. Secondly, the initiation of a fresh tender process, without resolving or lawfully terminating the existing contractual relationship, raises [2026:RJ-JP:20730] (73 of 106) [CW-8120/2025] serious concerns regarding the continuity, fairness, and transparency of State action. It is the case of the petitioner that the fresh NIB is not an independent or distinct project, but is intrinsically connected with, and substantially overlaps the scope of, the original contract, thereby rendering the same arbitrary and legally unsustainable. The respondents, on the other hand, have sought to justify the same as a policy decision based on a revised DPR and altered project configuration. In these circumstances, the issuance of the NIB dated 03.04.2025 constitutes a distinct and recurring cause of action, giving rise to an independent challenge in Writ Petition No. 8120/2025, while also having a direct bearing on the legality of the earlier withdrawal of the petitioner’s contract. 33. Consequently, for the purposes of clarity and procedural convenience, this court proceed to frame the following issues for its determination: Issue No. 1: Whether the present petitions are maintain- able, as the same revolve around a dispute which is con- tractual in nature, and allegedly improper authorization of the deponent? 34. The respondents have raised a preliminary objection assailing the maintainability of the present writ petitions on two counts: firstly, that the petition has not been instituted by a duly authorized person on behalf of the petitioner-company; and secondly, that the dispute arises out of a contractual relationship and is, therefore, not amenable to writ jurisdiction. [2026:RJ-JP:20730] (74 of 106) [CW-8120/2025] (A) Objection regarding authorization of the deponent 35. Insofar as the first limb of objection is concerned, it was contended that the writ petition has been filed by Mr. Ajai Kumar Gupta, Managing Director of the petitioner–company, without proper authorization. Upon consideration of the record, this Court finds that the petitioner is a company, which is a juristic person distinct from its shareholders and directors, and necessarily acts through natural persons. It is not in dispute that Mr. Ajai Kumar Gupta is not only a shareholder but also the Managing Director of the petitioner-company and has executed the contract in question on behalf of the company. A resolution authorizing him in this regard has also been placed on record. Thus, the legal position in this regard is no longer res integra, as in the ratio encapsulated in United Bank of India vs. Naresh Kumar, (1996) 6 SCC 660, it has been categorically held that since a company is a juristic entity, pleadings on its behalf have to be signed and verified by a competent person, and even in the absence of initial authorization, such defect is curable and can be ratified subsequently. Further, under Order XXIX Rule 1 of the Code of Civil Procedure, a company is competent to authorize any person to sign and verify pleadings on its behalf, and such authorization need not necessarily be contemporaneous, but can be established on record at any stage. Thence, in view of the aforesaid settled legal position and the material available on record, this Court is satisfied that the objection raised by the respondents is purely technical in nature and stands duly cured. Accordingly, the same is rejected. [2026:RJ-JP:20730] (75 of 106) [CW-8120/2025] (B) Objection regarding maintainability of writ petition in contractual matters 36. The second limb of objection pertains to the maintainability of the writ petition on the ground that the dispute arises out of a contract. Albeit it is true that ordinarily disputes arising out of contractual obligations are not entertained in writ jurisdiction, the said rule is subject to well-established exceptions; as where the action of the State or its instrumentalities is arbitrary, violative of principles of natural justice, or involves a public law element, the writ court would be justified in exercising jurisdiction under Article 226 of the Constitution. In the present case, it is not disputed that a validly executed EPC contract existed between the parties. The grievance of the petitioner, however, is not confined to mere enforcement of contractual terms. Rather, the challenge is directed against the manner in which the contract has been withdrawn. 37. The record reveals that the contract was withdrawn vide order dated 24.04.2024, which is alleged to have been passed ex parte, without affording any opportunity of hearing to the petitioner. It was further contended that the invocation of Clause 32 of the Special Conditions of Contract is misconceived and dehors the contractual framework. Additionally, it has been brought on record that extensions of time were granted by the respondents, and bank guarantees were dealt with unilaterally, indicating subsistence of the contractual relationship; the delay, if any, was attributable to the respondents themselves; and thereafter, a fresh tender was floated by altering and reducing the [2026:RJ-JP:20730] (76 of 106) [CW-8120/2025] scope of work, allegedly without safeguarding the petitioner’s interests and without resorting to “risk and cost” provisions. The petitioner has also invoked the doctrines of promissory estoppel and legitimate expectation, asserting that the respondents, having induced the petitioner to act upon the contract and having permitted continuation of work through extensions, could not have abruptly withdrawn the contract in an arbitrary manner. The aforesaid facts, taken cumulatively, demonstrate that the controversy involves allegations of arbitrariness, lack of fairness, and violation of natural justice by a State instrumentality, thereby introducing a clear public law element into the dispute; and in such circumstances, this Court is of the considered view that the present case falls within the recognized exceptions where judicial review in contractual matters is permissible. Accordingly, the writ petitions are held to be maintainable. To extract more strength, this Court deems it appropriate to assert reliance upon the ratio encapsulated in Tata cellular v. Union of India: (1994) 6 SCC 651, Sudhir Kumar Singh (supra) and ABL International Ltd. (Supra). The relevant portion of the Sudhir Kumar Singh (supra) is reproduced as under: "21. Dr Singhvi's preliminary objection as to Re- spondent 1 having to approach a civil court, and not a writ court, for actions that pertain to breach of contract, need not detain us. In ABL International Ltd. v. Export Credit Guarantee Corpn. of India Ltd. [ABL International Ltd. v. Export Credit Guarantee Corpn. of In- dia Ltd., (2004) 3 SCC 553], this Court held [2026:RJ-JP:20730] (77 of 106) [CW-8120/2025] that it was no longer res integra that a writ petition under Article 226 of the Constitution is maintainable at the instance of an ag- grieved party to enforce a contractual oblig- ation of the State or its instrumentality when the State acts in an arbitrary manner, as follows : (SCC pp. 564-67, paras 8-14)…. 11. In Gujarat State Financial Corpn. v. Lotus Hotels (P) Ltd. [Gujarat State Financial Corpn. v. Lotus Hotels (P) Ltd., (1983) 3 SCC 379] this Court following an earlier judgment in Ramana Dayaram Shetty v. International Airport Authority of India [Ramana Dayaram Shetty v. International Airport Authority of India, (1979) 3 SCC 489] held : (Gujarat State Financial Corpn. case [Gujarat State Financial Corpn. v. Lotus Hotels (P) Ltd., (1983) 3 SCC 379], SCC p. 380) ‘The instrumentality of the State which would be “other authority” under Article 12 cannot commit breach of a solemn undertaking to the prejudice of the other party which acted on that undertaking or promise and put itself in a disadvantageous position. The appellant Corporation, created under the State Financial Corporations Act, falls within the expression of “other authority” in Article 12 and if it backs out from such a promise, it cannot be said that the only remedy for the aggrieved party would be suing for damages for breach and that it could not compel the Corporation for specific performance of the contract under Article 226.’ 22. This principle in ABL International Ltd. [ABL International Ltd. v. Export Credit Guarantee Corpn. of India Ltd., (2004) 3 SCC 553] has been consistently upheld by this [2026:RJ-JP:20730] (78 of 106) [CW-8120/2025] Court in Noble Resources Ltd. v. State of Orissa [Noble Resources Ltd. v. State of Orissa, (2006) 10 SCC 236], para 15; Food Corpn. of India v. SEIL Ltd. [Food Corpn. of India v. SEIL Ltd., (2008) 3 SCC 440], para 16; Central Bank of India v. Devi Ispat Ltd. [Central Bank of India v. Devi Ispat Ltd., (2010) 11 SCC 186: (2010) 4 SCC (Civ) 401], para 28; and Surya Constructions v. State of U.P. [Surya Constructions v. State of U.P., (2019) 16 SCC 794], para 3. 43. Judged by the touchstone of these tests, it is clear that Respondent 1 has been completely in the dark so far as the cancellation of the award of tender in his favour is concerned, the audi alteram partem rule having been breached in its entirety. As has been correctly argued by Shri Rakesh Dwivedi, prejudice has indeed been caused to his client, not only from the fact that one year of the contract period has been taken away, but also that, if the impugned High Court judgment [Sudhir Kumar Singh v. State of U.P., 2019 SCC OnLine All 5798] is to be set aside today, his client will be debarred from bidding for any of the Corporation's tenders for a period of three years. 45. We, therefore, uphold the impugned judg- ment [Sudhir Kumar Singh v. State of U.P., 2019 SCC OnLine All 5798] of the High Court on the ground that natural justice has indeed been breached in the facts of the present case, not being a case of admitted facts leading to the grant of a futile writ, and that prejudice has in- deed been caused to Respondent 1. In view of this finding, there is no need to examine the [2026:RJ-JP:20730] (79 of 106) [CW-8120/2025] other contentions raised by the parties before us." Issue No. 2 – Whether the invocation of Clause 32 of the Special Conditions of Contract and consequent withdrawal of the contract is legally sustainable in the facts of the present case? 38. This Court has carefully perused the impugned order of withdrawal as well as Clause 32 of the Special Conditions of Contract. A conjoint reading of the same indicates that invocation of Clause 32 is not unfettered, but is conditioned upon the existence of certain foundational requirements. The following ingredients must necessarily be satisfied before resorting to such drastic action: (i) existence of a justifiable and valid reason; (ii) failure on the part of the contractor to maintain the stipulated progress of work; (iii) lapse or default attributable to the contractor in execution of any part of the work; (iv) issuance of a specific notice in writing calling upon the contractor to remedy such default and failure to comply therewith; (v) consequent engagement of another agency for execution of the work; (vi) continuation of the work in public interest through such alternate agency; and (vii) invocation of “risk and cost” provisions, including recovery of losses occasioned due to such default from the contractor. [2026:RJ-JP:20730] (80 of 106) [CW-8120/2025] 39. Upon a meticulous examination of the record, particularly the note-sheets spanning from the year 2023 till 20.04.2024, it emerges that although reasons were recorded for withdrawal of the contract, the same were not attributable to any default on the part of the petitioner. On the contrary, the material on record demonstrates that the impediments in execution arose on account of factors beyond the control of the petitioner, inter alia, including operation of the Model Code of Conduct, which restrained decision-making by the authorities; objections and protests raised by MNIT, OTS; difficulties in shifting of the Bisalpur pipeline; requirement of felling of a substantial number of trees; and proposed alteration in the scope of work, which, as per the respondents themselves, was not permissible under the EPC framework. These circumstances clearly indicate that the delay, if any, was institutional and administrative in nature, and cannot be fastened upon the petitioner. 40. It is further noteworthy that the petitioner was granted extension of time suo motu by the respondents, without imposition of any liquidated damages or penalty, as contemplated under the relevant contractual clauses. Even more significantly, after withdrawal of the contract, the bank guarantees furnished by the petitioner were released without any deduction or adjustment towards alleged losses. Such conduct on the part of the respondents unequivocally establishes that the petitioner was not treated as being in default; no loss was attributed to the petitioner; and thus the essential preconditions for invoking Clause 32, particularly those relating to default and risk-and-cost [2026:RJ-JP:20730] (81 of 106) [CW-8120/2025] consequences, were conspicuously absent. Withal, in the absence of these foundational requirements, the invocation of Clause 32 stands vitiated and unsustainable in law. 41. This Court likewise finds substance in the contention of the petitioner that the stand now sought to be advanced by the respondents is contrary to their own record; as the note-sheets and contemporaneous correspondence, including letters dated 25.03.2023, 12.06.2024 addressed to the Chief Secretary, communications from MNIT, the extension granted on 04.01.2024, extending the contract till 30.04.2024, and the release of bank guarantees on 29.07.2024, collectively demonstrate that the delay was not attributable to the petitioner. It is a settled principle of law that the validity of an administrative order must be judged on the basis of the reasons contained therein and cannot be supplemented by fresh reasons at a later stage. In this regard, reliance is appositely placed on the principle laid down in Mohinder Singh Gill (supra), wherein it has been held that an order must stand or fall on the reasons contained in it, and cannot be improved upon subsequently, for orders “are not like old wine becoming better as they grow older.” The relevant extract therefrom is reiterated hereinbelow: “8. The second equally relevant matter is that when a statutory functionary makes an order based on certain grounds, its validity must be judged by the reasons so mentioned and cannot be supplemented by fresh reasons in the shape of affidavit or otherwise. Otherwise, an order bad in the beginning may, by the time it comes to court on account of a challenge, get validated by additional grounds later [2026:RJ-JP:20730] (82 of 106) [CW-8120/2025] brought out. We may here draw attention to the observations of Bose, J. in Gordhandas Bhanji [Commr. of Police, Bombay v. Gordhandas Bhanji, 1951 SCC 1088 : AIR 1952 SC 16]: “Public orders, publicly made, in exercise of a statutory authority cannot be construed in the light of explanations subsequently given by the officer making the order of what he meant, or of what was in his mind, or what he intended to do. Public orders made by public authorities are meant to have public effect and are intended to affect the actings and conduct of those to whom they are addressed and must be construed objectively with reference to the language used in the order itself.” Orders are not like old wine becoming better as they grow older.” (Emphasis supplied) 42. In view of the aforesaid analysis, this Court holds that the invocation of Clause 32 and the consequent withdrawal of the contract is arbitrary, dehors the contractual framework, and unsustainable in law, the essential preconditions for its invocation having not been satisfied. 43. However, the pleadings in the reply affidavit and the submissions advanced on behalf of the respondents by the Officer In-charge Shri Sanjeevan Jain, and learned counsel representing for and on behalf of JDA, qua the above-discussed appear to be an afterthought and a misrepresentation of the factual position as borne out from the official record. This Court cannot remain oblivious to the conduct of the officers of the respondent–authority and the submissions advanced on their behalf, which are found to be contrary to the contemporaneous record and the contractual [2026:RJ-JP:20730] (83 of 106) [CW-8120/2025] framework governing the parties. Such conduct, particularly on the part of a State instrumentality, deserves to be viewed seriously and is accordingly taken note of adversely. Issue No. 3 – Whether the Doctrines of Promissory Estoppel and Legitimate Expectation be applicable in the prevailing circumstances? 44. From the material placed on record, it stands established that the petitioner, acting upon the assurances flowing from a duly executed and legally enforceable EPC contract, had altered its position to its detriment. The petitioner had mobilized substantial resources, undertaken surveys, prepared drawings and designs, procured materials to the extent of approximately Rs. 20 crores and incurred overall financial expenditure of nearly Rs. 40 crores in furtherance of the project. In such circumstances, the principles of promissory estoppel and the doctrine of legitimate expectation are clearly attracted. The respondents, having induced the petitioner to act upon the contract and having permitted continuation of the project over a considerable period, cannot be permitted to resile from their promise in an arbitrary and unilateral manner. The justification sought to be advanced by the respondents, including change in Government or administrative difficulties in execution of the project, cannot absolve them of their obligations under a concluded and binding contract, as it is well settled that State action must be informed by fairness, reasonableness and non-arbitrariness, and the State cannot be [2026:RJ-JP:20730] (84 of 106) [CW-8120/2025] permitted to wriggle out of its contractual commitments on extraneous or political considerations. 45. Thence, the impugned action of withdrawal of the contract, coupled with the issuance of a fresh tender for preparation of DPR, clearly indicates that the decision is not founded on any contractual default attributable to the petitioner, but is rather a consequence of a change in policy coinciding with change in Government. Such action, in the considered opinion of this Court, is arbitrary, capricious and violative of Article 14 of the Constitution of India, and falls foul of the mandate governing “State” under Article 12. In this regard, reliance placed by the petitioner on the judgments in IFGL Refractories Ltd. (supra), U.P. Power Corporation Ltd. (supra), and Sivanandan C.T. (supra), is well-founded, as the said authorities reiterate that the State and its instrumentalities are bound by the doctrines of fairness, promissory estoppel and legitimate expectation, and cannot act to the prejudice of a party who has altered its position based on a representation or promise. Accordingly, the present issue is answered in favor of the petitioner. Relevant portion of the above said judgments can be summarized by reproducing the relevant extract of the judgment IFGL Refractories Ltd. (supra), which is as under: “115. According to this Court, the true principle of promissory estoppel seemed to be that where one party has, by his words or conduct, made to the other a clear and unequivocal promise which is intended to create legal relations or effect [2026:RJ-JP:20730] (85 of 106) [CW-8120/2025] a legal relationship to arise in the future, knowing or intending that it would be acted upon by the other party to whom the promise is made. Where it is in fact so acted upon by the other party, the promise would be binding on the party making it, and he would not be entitled to go back upon it, if it would be inequitable to allow him to do so, having regard to the dealings which have taken place between the parties. This would be so irrespective of whether there is any pre- existing relationship between the parties or not. 116. It was further observed that it is not necessary, in order to attract the applicability of the doctrine of promissory estoppel, that the promisee, acting on the promise, should suffer any detriment. What is necessary is only that the promisee should have altered his position in reliance on the promise. This Court was of the view that the doctrine of promissory estoppel is also applicable against the government, where the government makes a promise knowing or intending that it would be acted upon by the promisee. Where, in fact, the promisee, acting on it, alters his position, the government would be held bound by the promise. The promise would be enforceable against the government at the instance of the promisee, notwithstanding that there is no consideration for the promise and the promise is not recorded in the form of a formal contract. …….. [2026:RJ-JP:20730] (86 of 106) [CW-8120/2025] 133. This litigation is a fine specimen of the bureaucratic lethargy. It is this bureaucratic lethargy which gave rise to this long drawn litigation. This Court in many of its decisions has reminded various State Governments that if the object of formulating the industrial policy is to encourage investment, employment and growth, the bureaucratic lethargy of the State apparatus is clearly a factor which will discourage entrepreneurship.” (Emphasis supplied) Issue No. 4 - Nature, Scope, and Validity of the power exercised under Clause 32 of the Contract by the respondents: 47. In the present case, this Court finds that the delay in execution of the project is not attributable to the petitioner, but is squarely traceable to the respondents themselves. A bare perusal of the impugned order dated 24.04.2024, purportedly issued under Clause 32 of the Special Conditions of Contract, reveals that no specific fault or breach has been imputed to the petitioner. The impugned order employs vague and non-specific expressions such as “site conditions” and “various reasons”, without delineating any concrete default on the part of the petitioner. Such generalized observations, in the absence of any specific finding of breach, fall short of the requirements necessary for invoking a penal contractual clause like Clause 32. On the contrary, the contemporaneous record, including the note-sheets and official correspondence placed before this Court (inter alia, [2026:RJ-JP:20730] (87 of 106) [CW-8120/2025] communications addressed by the respondent–JDA to the Chief Secretary; objections and correspondence emanating from MNIT, OTS; difficulties in acquisition and handing over of clear and encumbrance-free site; and other infrastructural and administrative constraints affecting execution), unequivocally establishes that the impediments in execution existed from the very inception of the contract till its withdrawal, and were entirely beyond the control of the petitioner. The cumulative effect of these documents clearly attributes the delay to systemic and administrative shortcomings on the part of the respondent-JDA, rather than any lapse on the part of the petitioner. 47. It is a settled principle that where delay is attributable to the employer, the contractor cannot be penalized for non- performance within the stipulated time. The absence of any allegation of default, coupled with the existence of documented impediments attributable to the respondents, renders the invocation of Clause 32 wholly untenable. In this backdrop, it becomes apposite to refer to the relevant provisions of the bid document, particularly those contained in Schedule ‘C’ (Annexure– 3), which govern the obligations of the employer in providing requisite site conditions and facilitating execution of the work. The said clauses, which have a direct bearing on the issue at hand, are reproduced hereunder: “SCHEDULE C. – LIST OF DRAWINGS TO BE SUPPLIED BY THE BIDDER A.The successful bidder has to submit at least three conceptual plans for the project before the JDA committee and the committee reserves the right for approval of plan. [2026:RJ-JP:20730] (88 of 106) [CW-8120/2025] B.The successful bidder has to submit the planning and working drawings of approved plan and finally to be vetted from MNIT/IIT at his own cost. The structural design should be prepared using latest software. The same will need approval by JDA before execution. C.The successful bidder must note that all activities related to project must be completed within 12 months of speculated period” A condition for approval under the heading '"Scope of work & specification" sub heading "Super-Structure" (Annexure-3) of the Contract Agreement, which is reproduced as under:- “SUPER STRUCTURE 1. The super structure shall be steel based plate or composite girder of grade E350 BR steel, preferably precast and/or with sacrificial shuttering. The make of steel plates can only be SAIL/JINDAL/TATA STEEL. The contractor shall be responsible for preparation of QAP/WPSS and preliminary fabrication drawings. After the preparation of these documents, they shall be duly checked and approved or get proof checked from IIT/reputed institutions empanelled consultant as approved by EIC at his own cost and got approved by JDA prior to use. Any direction by JDA shall be incorporated as regards the same. ….. 21. All fabrication of structural steel work should be carried out by Research Designs and Standards Organization (RDSO) approved vendors.” 48. The contractual framework, particularly the aforementioned clauses as contained in Schedule ‘C’ (Annexure– 3), casts an obligation upon the employer to provide requisite site conditions and facilitate unhindered execution of the work. Failure [2026:RJ-JP:20730] (89 of 106) [CW-8120/2025] on the part of the employer to discharge these foundational obligations cannot be used as a ground to penalize the contractor. Thus, in the present case, the material on record unmistakably establishes that the respondents themselves failed to provide the necessary conditions for execution of the project. Consequently, the petitioner cannot be held responsible for non-achievement of progress within the stipulated timeline. 49. In view of the aforesaid analysis, this Court holds that the delay in execution of the contract is squarely attributable to the respondents, and not to the petitioner. The essential precondition for invoking Clause 32, namely default or failure on the part of the contractor, being absent, the action of the respondents in withdrawing the contract is rendered arbitrary, unjustified, and contrary to the contractual provisions. 50. It is further noteworthy, that the contractual matrix governing the parties unequivocally establishes that the obligation to provide a clear, encumbrance-free site vested solely with the respondent–JDA. The “Summary of Work” and the relevant clauses of the Special Conditions of Contract make it abundantly clear that the petitioner’s obligations were contingent upon the respondents first fulfilling their foundational duties, namely: (i) making available the land, (ii) ensuring a clean and obstruction-free site, and (iii) facilitating approvals of drawings and designs within a reasonable time frame. 51. The record further demonstrates that the petitioner had, in fact, diligently performed its reciprocal obligations. The [2026:RJ-JP:20730] (90 of 106) [CW-8120/2025] drawings and designs were prepared and submitted for approval; procurement of steel was undertaken strictly from approved manufacturers; and substantial mobilization of resources was effected. However, the corresponding approvals and site facilitation, which were prerequisites for meaningful execution, remained pending due to administrative and institutional constraints attributable to the respondents. The contemporaneous correspondence forming part of the note-sheet assumes critical importance. The letters exchanged between the parties, including Annexure–13 i.e. letter dated 04.01.2024, whereby extension of time was granted unilaterally without imposition of liquidated damages, constitute a clear and unequivocal acknowledgment by the respondents that the delay was not attributable to the petitioner. This Court is of a stern view that in contractual jurisprudence, such conduct amounts to a waiver of alleged breach and operates as an admission against the employer. Further, the petitioner’s representation/letter (Annexure–15) seeking price variation upon extension of time reinforces the position that the contract was treated as subsisting by both parties. The respondents neither rejected the continuation of the contract on grounds of default nor invoked any penal provisions contemporaneously. Therefore, the fact of considerable significance is that the respondents returned the bank guarantees furnished by the petitioner without invoking Clauses 2, 3, and/or 37 of the Special Conditions of Contract, which otherwise provide for consequences in the event of contractor default. This omission is not merely procedural but substantive in nature, it thus, [2026:RJ-JP:20730] (91 of 106) [CW-8120/2025] unequivocally establishes that no breach or default was ever crystallized against the petitioner. 52. In such circumstances, the subsequent invocation of Clause 32 for withdrawal of work is ex facie inconsistent with the prior conduct of the respondents and is legally untenable. A contracting authority cannot approbate and reprobate, having treated the contract as valid and subsisting, it cannot later attribute delay to the contractor without any intervening material change. This Court also finds substance in the petitioner’s contention that the issuance of a fresh Notice Inviting Bid (NIB) for preparation of a new DPR for the very same project is manifestly arbitrary. The record does not disclose any rational or technical basis necessitating a fresh DPR. On the contrary, the material indicates that the core objectives of the project i.e. decongestion of traffic, seamless flow, and enhancement of aesthetic value of JLN Marg-remained unchanged across the relevant period. In consequence, the attempt of the respondents to draw a distinction between the projects of the years 2021–22 and 2024–25 is not borne out from any contemporaneous record. Such a plea appears to be an afterthought devised to justify an otherwise arbitrary decision, particularly when no substantive alteration in scope, alignment, or purpose has been demonstrated. 53. Consecutively, it is equally germane to jot down that the abrupt abandonment of the ongoing contractual process, despite the petitioner having invested an amount exceeding Rs. 40 crores and the contract itself having been extended for a period of two years, is not only inequitable but also violative of the [2026:RJ-JP:20730] (92 of 106) [CW-8120/2025] principles of fairness and reasonableness which govern State action under Article 14 of the Constitution. The legal position in this regard stands settled by the judgment of the Hon’ble Supreme Court in K. Shyam Sunder (supra), wherein it has been held that a change in government or policy cannot, by itself, be a ground to annul or disturb a concluded and legally enforceable contract, unless it is demonstrated that the earlier decision was contrary to statutory provisions or against public interest. The relevant extract from the ratio encapsulated in K. Shyam Sunder (supra), is reproduced hereinbelow: "35. Thus, it is clear from the above, that unless it is found that act done by the authority earlier in existence is either contrary to statutory provisions, is unreasonable, or is against public interest, the State should not change its stand merely because the other political party has come into power. Political agenda of an individual or a political party should not be subversive of rule of law.” (Emphasis laid) 54. The same has also been held in the dictum enunciated in Shishir Realty Pvt. Ltd. (supra). The relevant portion of the same is reproduced as under:- "61. When a contract is being evaluated, the mere possibility of more money in the public coffers, does not in itself serve public interest. A blanket claim by the State claiming loss of public money cannot be used to forego contractual obligations, especially when it is not based on any evidence or examination. The larger public interest of upholding contracts and the fairness of public authorities is also in play. The courts need to [2026:RJ-JP:20730] (93 of 106) [CW-8120/2025] have a broader understanding of public interest, while reviewing such contracts. … 63. Similarly, this Court in A.P. Dairy Development Corpn. Federation v. B. Narasimha Reddy [A.P. Dairy Development Corpn. Federation v. B. Narasimha Reddy, (2011) 9 SCC 286] held as under : (SCC p. 306, para 40) “40. In the matter of the Government of a State, the succeeding Government is duty-bound to continue and carry on the unfinished job of the previous Government, for the reason that the action is that of the “State”, within the meaning of Article 12 of the Constitution, which continues to subsist and therefore, it is not required that the new Government can plead contrary to the State action taken by the previous Government in respect of a particular subject. The State, being a continuing body can be stopped from changing its stand in a given case, but where after holding enquiry it came to the conclusion that action was not in conformity with law, the doctrine of estoppel would not apply. Thus, unless the act done by the previous Government is found to be contrary to the statutory provisions, unreasonable or against policy, the State should not change its stand merely because the other political party has come into power. ‘Political agenda of an individual or a political party should not be subversive of rule of law.’ The Government has to rise above the nexus of vested interest and nepotism, etc. as the principles of governance have to be tested on the touchstone of justice, equity and fair play.” (emphasis supplied) 55. Further, upon a comprehensive perusal of the contractual stipulations, this Court is of the considered view that [2026:RJ-JP:20730] (94 of 106) [CW-8120/2025] the existing contract itself provided sufficient flexibility to accommodate necessary modifications. It is evident that justifiable and material alterations in the scope of work could have been undertaken, particularly if such changes were effected in a timely manner and upon due consideration of expert opinion. Notably, the appointed consultant under the contract continued to remain engaged and available for such evaluative inputs. The contractual framework, in fact, envisaged stage-wise execution and corresponding payments, coupled with sub-categorization of work components. In such a scenario, it was well within the domain of the respondents to restructure, reduce, or expand the scope of work, and to proceed with execution in a phased manner, rather than abandoning the contract in its entirety. Moreover, a specific clause under the Special Conditions of Contract expressly contemplates variation, alteration, or modification of the contractual scope, even stipulating that no additional compensation would be payable on such account. This clearly indicates that the contract was designed to be adaptable to evolving project requirements. Consequently, any required adjustments could have been mutually deliberated and resolved between the parties, without resorting to termination or withdrawal. 56. This position finds support from the judgment in enunciated in Yash Construction Company v. The Secretary, Ministry of Road Transport and Highways (MoRT & H), Writ Petition No. 9620/2022, decided on 16.12.2022, wherein it has been recognized that modifications in contractual scope, where [2026:RJ-JP:20730] (95 of 106) [CW-8120/2025] contractually permissible, ought to be addressed within the framework of the existing agreement rather than leading to its abrupt discontinuation. The relevant extract from the said ratio is reiterated hereinbelow: “23. To sum up, the decision of the respondents to abort the process of tender wherein the Petitioners were the successful L1 bidders on the sole ground that the notice inviting tender stipulated 24 months as the period for completion of the work instead of 18 months and even when the petitioners expressed their readiness and willingness to complete the work at the same cost offered by them which does not suffer from the sin of post tender negotiations, the decisions of the respondents is clearly arbitrary and would lead to a loss of public money. The cases are fit to be interfered with.” (emphasis supplied) 57. It is also opined that when a contract is entered into between the State or its instrumentalities and a private party upon a duly concluded tender process, any dispute arising out of such contractual relationship does not entirely oust the jurisdiction of this Court under judicial review. It is well-settled that the actions of the State, even in contractual matters, must withstand the test of fairness, reasonableness, and non-arbitrariness, as enshrined under Article 14 of the Constitution of India. Thus, the State cannot be permitted to cloak arbitrary or unreasonable conduct behind the mere existence of a contract, nor can it evade judicial scrutiny on the specious plea of availability of alternate remedies. The doctrine of fairness permeates all State actions, and contractual dealings are no exception, particularly where such [2026:RJ-JP:20730] (96 of 106) [CW-8120/2025] actions bear a public law element. In exercising the power of judicial review, this Court is therefore required to examine whether the decision-making process adopted by the State is just, transparent, and free from arbitrariness, and not merely whether the action is in strict conformity with the terms of the contract. The presence of contractual stipulations or dispute resolution mechanisms does not denude this Court of its constitutional obligation to ensure adherence to the mandate of Article 14. 58. In this regard, reliance is placed upon the celebrated judgment of Subodh Kumar Singh (supra), wherein it has been held that State action in contractual matters remains amenable to judicial review, particularly when it is demonstrated that such action is arbitrary, unfair, or actuated by extraneous considerations, notwithstanding the existence of contractual remedies. The relevant extract of the said judgment is reproduced hereinbelow: "126. The sanctity of public tenders lies in their role in upholding the principles of equal opportunity and fairness. Once a contract has come into existence through a valid tendering process, its termination must adhere strictly to the terms of the contract, with the executive powers to be exercised only in exceptional cases by the public authorities and that too in loathe. The courts are duty bound to zealously protect the sanctity of any tender that has been duly conducted and concluded by ensuring that the larger public interest of upholding bindingness of contracts are [2026:RJ-JP:20730] (97 of 106) [CW-8120/2025] not sidelined by a capricious or arbitrary exercise of power by the State. It is the duty of the courts to interfere in contractual matters that have fallen prey to an arbitrary action of the authorities in the guise of technical faults, policy change or public interest, etc. 127. The sanctity of contracts is a fundamental principle that underpins the stability and predictability of legal and commercial relationships. When public authorities enter into contracts, they create legitimate expectations that the State will honour its obligations. Arbitrary or unreasonable terminations undermine these expectations and erode the trust of private players from the public procurement processes and tenders. Once a contract is entered, there is a legitimate expectation that the obligations arising from the contract will be honoured and that the rights arising from it will not be arbitrarily divested except for a breach or non- compliance of the terms agreed thereunder. In this regard we may make a reference to the decision of this Court in Sivanandan C.T. v. High Court of Kerala wherein it was held that a promise made by a public authority will give rise to a legitimate expectation that it will adhere to its assurances. …. 130. Cancellation of a contract deprives a person of his very valuable rights and is a very drastic step, often [2026:RJ-JP:20730] (98 of 106) [CW-8120/2025] due to significant investments having already been made by the parties involved during the subsistence of the contract. Failure on the part of the courts to zealously protect the binding nature of a lawful and valid tender would erode public faith in contracts and tenders. Arbitrary terminations of contract create uncertainty and unpredictability, thereby discouraging public participation in the tendering process. When private parties perceive that their contractual rights can be easily trampled by the State, they would be dissuaded from participating in public procurement processes which may have a negative impact on such other public-private partnership ventures and ultimately it is the public who would have to bear the brunt thereby frustrating the very object of public interest. 131. We caution the public authorities to be circumspect in disturbing or wriggling out of its contractual obligations through means beyond the terms of the contract in exercise of their executive powers. We do not say for a moment that the State has no power to alter or cancel a contract that it has entered into. However, if the State deems it necessary to alter or cancel a contract on the ground of public interest or change in policy then such considerations must be bona fide and should be earnestly reflected in the decision-making process and also in the final decision itself. Otherwise, it would [2026:RJ-JP:20730] (99 of 106) [CW-8120/2025] have a very chilling effect as participating and winning a tender would tend to be viewed as a situation worse than losing one at the threshold.” (emphasis supplied) CONCLUSION: 59. In addition to the findings recorded hereinabove, this Court deems it appropriate to observe that the present writ petitions are maintainable inasmuch as the challenge laid is not to a mere contractual dispute but to the arbitrary and unreasonable exercise of State power, thereby attracting the rigours of Article 14 of the Constitution of India. The decision making process adopted by the respondents fails to satisfy the settled parameters of judicial review, being vitiated by non-application of mind, disproportionality, and manifest unreasonableness, particularly when less drastic alternatives such as modification of scope, phased execution, or contractual adjustments, were admittedly available under the contract itself. The contemporaneous record further establishes that the respondents, by granting extensions without levy of liquidated damages, returning bank guarantees, and permitting continued performance, had effectively waived any alleged default and induced legitimate expectation in favour of the petitioner, who, acting upon such representation, altered its position by making substantial financial investments. The subsequent attempt to attribute delay to the petitioner is thus hit by the doctrines of promissory estoppel and waiver, and cannot be countenanced. [2026:RJ-JP:20730] (100 of 106) [CW-8120/2025] 60. Further, the abrupt abandonment of the subsisting contract and initiation of a fresh DPR process, in absence of any documented policy change or technical justification, is not only arbitrary but also indicative of malice in law, being founded on extraneous considerations rather than public interest. The respondents have failed to demonstrate that such action advances any larger public good; rather, the same results in avoidable delay, escalation of costs, and wastage of public resources, thereby failing the test of proportionality. This Court also finds that the impugned action is contrary to the principles governing State contracts, as the petitioner has approached this Court with clean hands and established its continuous readiness and willingness to perform, while the respondents’ own record belies their stand taken before this Court, rendering their defence unsustainable. 61. It is noteworthy that this Court has rendered its findings strictly on the basis of contemporaneous official record produced by the respondents themselves, and not on disputed questions of fact, thereby obviating the necessity of relegating the petitioner to an alternate remedy. The record, particularly the internal note-sheets of the respondent–authority, unmistakably reflects an admission on the part of the State that the withdrawal of the contract was occasioned on account of site-related constraints and other administrative reasons, none of which can be attributed to the petitioner. It is hereby opined that from the very inception of the contract, the petitioner was kept uninformed of the material impediments affecting execution, on the contrary, encouraged to proceed with mobilization, resulting in substantial [2026:RJ-JP:20730] (101 of 106) [CW-8120/2025] investment in machinery, manpower, and procurement of materials. Despite the existence of contractual provisions permitting alteration or modification of scope of work, the respondents, for reasons best known to them, failed to exercise such enabling provisions; and instead of adopting a pragmatic and legally permissible course of restructuring the project, the respondents proceeded to abruptly terminate a legally enforceable contract by erroneously invoking Clause 32 of the contract, and this Court is of an opinion that invocation of Clause 32 without determination of default renders the action void ab initio, as also addressed in details hereinabove; and that the same was wholly inapplicable in the absence of any contractor default. 62. What further compounds the arbitrariness of the respondents’ conduct is the immediate issuance of a fresh tender for preparation of a DPR qua the same OTS flyover project, without disclosing any rational basis or change in circumstances warranting such action. This decision, viewed in light of the existing contractual framework and the petitioner’s ongoing performance, is manifestly arbitrary and indicative of non- application of mind. The submissions advanced on behalf of the respondents attributing delay and non-performance to the petitioner stand squarely contradicted by their own record, including the note-sheets and official correspondence placed before this Court. Such conduct not only undermines the credibility of the decision-making process but also borders upon misrepresentation before the Court. From the material placed on record, it prima facie emerges that the withdrawal of the contract [2026:RJ-JP:20730] (102 of 106) [CW-8120/2025] was influenced by extraneous considerations, including the need to accommodate objections raised by certain institutions such as MNIT and OTS, as well as other influential stakeholders. The consequential decision to alter the project configuration, inter alia, reducing the flyover capacity from eight lanes to six lanes and eliminating service roads, further demonstrates a departure from the original project objectives, thereby frustrating the very purpose for which the contract was awarded. In light of the foregoing analysis, this Court is of the considered opinion that the impugned action of the respondents is arbitrary, unreasonable, and violative of Article 14 of the Constitution of India, and the principle of legitimate expectation, and cannot be sustained in law. DIRECTIONS: 63. The writ petitions are accordingly allowed in terms of the prayers made, with the following directions: 63.1 The impugned order dated 24.04.2024, issued under Clause 32 of the Special Conditions of Contract, is hereby quashed and set aside. 63.2 The Notice Inviting Bid (NIB/NIT) for preparation of DPR, to the extent it pertains to the OTS flyover project, is also quashed. 63.3 The petitioner shall get all consequential benefits, and it be entitled to pursue its lawful claims arising out of the contract in accordance with law. 63.4 The respondents are directed to proceed with the execution of the project forthwith, in accordance with the subsisting contract, and to take all necessary steps to ensure its [2026:RJ-JP:20730] (103 of 106) [CW-8120/2025] timely completion. While doing so, the respondents shall duly consider price variation, contractual adjustments, and other permissible claims, in accordance with law and the terms of the contract. 63.5 The respondents shall also ensure that the project is implemented in its true spirit, in alignment with the policy vision reflected in the State Budget announcements for the years 2021– 2022 and 2024–2025. 64. This Court further deems it necessary to direct an inquiry into the decision-making process leading to the withdrawal of the contract, in view of the glaring inconsistencies between the stand taken by the respondents before this Court and the contemporaneous official record, including the note-sheets and internal communications. The material placed on record prima facie discloses that the impugned decision was not founded upon any objective assessment of contractual breach, but was instead influenced by extraneous considerations and administrative lapses, thereby resulting in arbitrary exercise of power. This Court is of a stern view that in matters involving public contracts, the State and its instrumentalities are under a heightened obligation to act in a fair, transparent, and accountable manner, particularly when decisions entail significant financial implications and affect public interest. The present case reveals that despite the availability of lawful and contractual alternatives, the respondents chose to adopt a course which not only defeated a subsisting contract, but also led to potential loss to the public exchequer and delay in execution of a project of public importance. Further, the fact that [2026:RJ-JP:20730] (104 of 106) [CW-8120/2025] the respondents have advanced submissions before this Court which are not borne out from their own record raises serious concerns regarding the integrity of the decision making process; and it is opined that such conduct, if left unchecked, would erode public confidence in administrative functioning and undermine the rule of law. 65. This Court further considers it apposite to underscore that while the State is entitled to act in furtherance of sovereign and public interest, such doctrine cannot be invoked as a carte blanche to justify actions which are otherwise arbitrary, disproportionate, or unsupported by the record. The doctrine of sovereign interest, read in conjunction with the principles of public trust, fairness in administrative action, and accountability, mandates that every decision of the State must demonstrably serve a legitimate public purpose and withstand judicial scrutiny on the touchstone of Article 14 of the Constitution of India. Any departure from an existing contractual obligation must therefore be founded upon cogent, transparent, and bona fide considerations, and not on extraneous or undisclosed factors. Simultaneously, this Court deems it necessary to observe that the Officer-in-Charge representing the department before the Court bears a solemn responsibility. Such officer, while swearing affidavits and placing records before the Court, acts not merely as a departmental functionary but as an extended arm of the justice delivery system, rendering assistance to the learned counsel representing the State. The officer thus assumes a position akin to that of an officer of the Court, and is expected to maintain the highest standards of [2026:RJ-JP:20730] (105 of 106) [CW-8120/2025] candour, accuracy, and responsibility in all submissions made on affidavit. Any statement made must be strictly in consonance with the official record, and due diligence is expected before affirming pleadings. Casual, misleading, or inconsistent averments not only impair the adjudicatory process but also amount to a serious dereliction of duty, warranting appropriate scrutiny. 66. Thus, a structured inquiry to ascertain the circumstances under which such decision was taken, to identify any procedural irregularities, lapses, or misconduct, and to ensure that accountability is fixed upon the officers responsible, be taken. Such a direction is not punitive in nature but is essential to uphold the principles of good governance, administrative accountability, and transparency in State action. Accordingly, the Chief Secretary, of the State of Rajasthan, is directed to take appropriate measures in this regard, strictly in consonance with the directives enumerated herein, against the erring officer(s), within an upper limit of two months from the date of pronouncement of this judgment. 67. In addition, this Court deems it appropriate to record that prima facie misrepresentation has been made before this Court by the Officer-in-charge/erring officers, whose pleadings were found to be inconsistent with the official record. The competent authority is directed to initiate appropriate proceedings and take action in accordance with law. 68. Consequently, the instant petitions stand allowed, with above mentioned directions. There shall be no order as to costs. Pending applications, if any, shall stand disposed of accordingly. [2026:RJ-JP:20730] (106 of 106) [CW-8120/2025] 69. Registrar (Judicial) is directed to retain a xerox copy of file no. 5 and 6 from the records furnished by the respondent-JDA; and thereafter return the records, in toto, to the concerned officer, strictly in compliance with the due procedure. (SAMEER JAIN),J Pooja /