Extracted from the PDF above. The PDF is authoritative.
$~39 * IN THE HIGH COURT OF DELHI AT NEW DELHI + O.M.P.(MISC.)(COMM.) 182/2026, I.A. 4581/2026 & I.A. 4582/2026
CMM INFRAPROJECTS LTD
.....Petitioner Through: Mr. Harshit Agarwal & Mr. Aasheesh Gupta, Advs.
versus
IRCON INTERNATIONAL LTD
.....Respondent
Through: Mr. Debarshi Bhadra, Adv.
CORAM:
HON'BLE MR. JUSTICE AVNEESH JHINGAN
O R D E R %
18.02.2026
1. This petition is filed under Section 29A of the Arbitration & Conciliation Act, 1996 seeking extension of period for concluding the arbitration proceedings.
2.
Learned counsel for the respondent has no serious objection to the prayer made.
3. In view of the above, the time period for conclusion of the proceedings is extended by eight months as prayed for.
4. This petition is disposed of in the aforesaid terms.
AVNEESH JHINGAN, J FEBRUARY 18, 2026 Ch
This is a digitally signed order. The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above. The Order is downloaded from the DHC Server on 21/02/2026 at 12:00:32