Extracted from the PDF above. The PDF is authoritative.
WP No. 8421 of 2026 IN THE HIGH COURT OF JUDICATURE AT MADRAS DATED: 04-03-2026 CORAM THE HONOURABLE MR JUSTICE M.DHANDAPANI WP No. 8421 of 2026 B.Pothumani Petitioner(s) Vs
1. The Additional principal Secretary, Department of Housing and urban Development, St George Fort, Chennai. 2.Tamilnadu urban habitat Development Board, Represented By The Managing Director, No 5 Kamarajar Salai, Mylapore, Chennai 5 Respondent(s) PRAYER; This writ petition is filed under Article 226 of Constitution of India, to issue a Writ of Mandamus, directing the 1st Respondent herein to consider the representation of the petitioner dated 29.04.2025 for allotment of tenement in the pattinapakkam Scheme. For Petitioner(s): Mr.R.Sivakumar For Respondent: Mr.S.Balamurugan, GA R1 Mr.G.Venkatesan
ORDER This petition has been filed seeking a direction to the 1st Respondent herein to consider the representation of the petitioner dated 29.04.2025 for allotment of tennement in the pattinapakkam Scheme. https://www.mhc.tn.gov.in/judis
WP No. 8421 of 2026
2. It is the case of the petitioner that she belongs to fishermen community and living near Marina Beach area. She has no house in her name and therefore, she has applied for a tenement in the second respondent Board. The second respondent did not allot a tenement. The petitioner's family members did not get any tenement in the Tsunami scheme. Therefore, the petitioner made a representation to the second respondent on 19.01.2024 for allotment of a house and the same is not considered. Hence, the present writ petition.
3. The learned counsel for the petitioner submitted that this Court may direct the respondents to consider and pass orders on the petitioners representation within the stipulated time as fixed by this Court.
4. The learned counsel appearing for the respondent submitted that the representation will be considered and orders will be passed within the stipulated time as fixed by this Court.
5. Heard the learned counsel for both side and perused the materials available on record.
6. Considering the facts and circumstances of the case and in view of the limited request sought for by the petitioner, this court directs the second respondent to consider and pass orders on the petitioner's representation dated https://www.mhc.tn.gov.in/judis
WP No. 8421 of 2026 29.04.2025 within a period of six weeks from the date of receipt of a copy of this
order.
7. With the above directions, the writ petition is disposed of. No costs. 04-03-2026 rli Index:Yes/No Speaking/Non-speaking order Internet:Yes Neutral Citation:Yes/No To 1.The Additional principal Secretary Department of Housing and urban Development St George Fort, Chennai 2.Tamilnadu urban habitat Development Board Represented By The Managing Director No 5 Kamarajar Salai, Mylapore, Chennai 5 https://www.mhc.tn.gov.in/judis
WP No. 8421 of 2026 M.DHANDAPANI J. rli WP No. 8421 of 2026 04-03-2026 https://www.mhc.tn.gov.in/judis