M/S SKB PROJECT (I) PVT. LTD. v. ARMY WELFARE HOUSING ORGANIZATION
O.M.P.(MISC.)(COMM.)/188/2026 · 2026-02-20
Avneesh Jhingan
body2026
DailyLaw.ai
[ 2026 DAILYLAW 7109 (DEL) · dailylaw.ai ]
DailyLaw.ai
[ 2026 DAILYLAW 7109 (DEL) · dailylaw.ai ]
Judgment text
Extracted from the PDF above. The PDF is authoritative.
$~25 * IN THE HIGH COURT OF DELHI AT NEW DELHI + O.M.P.(MISC.)(COMM.) 188/2026
M/S SKB PROJECT (I) PVT. LTD.
.....Petitioner Through: Ms. Risha Mittal, Mr. Rohan Narula & Ms. Salevino Chale, Advs.
versus
ARMY WELFARE HOUSING ORGANIZATION .....Respondent
Through: Mr. A.K. Tewari, Adv. (through VC)
CORAM:
HON'BLE MR. JUSTICE AVNEESH JHINGAN
O R D E R %
20.02.2026
1. This petition is filed under Section 29A of the Arbitration & Conciliation Act, 1996 seeking extension of period for concluding the arbitration proceedings.
2.
Learned counsel for the respondent has no serious objection to the prayer made.
3. In view of the above, the time period for conclusion of the proceedings is extended by six months as prayed for.
4. This petition is disposed of in the aforesaid terms.
AVNEESH JHINGAN, J FEBRUARY 20, 2026 ‘ha’
This is a digitally signed order. The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above. The Order is downloaded from the DHC Server on 24/02/2026 at 12:31:04