- 1 -
HC-KAR
CNR: KAHC010682082026 NC: 2026:KHC:55241 WP No. 31128 of 2026
IN THE HIGH COURT OF KARNATAKA AT BENGALURU DATED THIS THE 5TH DAY OF OCTOBER, 2026 BEFORE THE HON'BLE MR. JUSTICE B M SHYAM PRASAD WRIT PETITION NO. 31128 OF 2026 (LB-BMP) BETWEEN:
1. SRI. E. ANTONY CLIVE, AGED ABOUT 29 YEARS, S/O MR. DHANARAJ EMMENUEL
2. SMT. SUSHMA P, AGED ABOUT 30 YEARS, W/O E. ANTONY CLIVE
PETITIONER 1 & 2 ARE RESIDING AT FLAT NO.402, FOURTH FLOOR, JEYA PRIDE, KAGADASAPURA VILLAGE, (FORMERLY KR PURA HOBLL), MARATHAHALLI HOBLL, BENGALURU EAST TALUK, BENGALURU- 560093. 3. SRI.SOMPALLE PHANINDRA, AGED ABOUT 36 YEARS, S/O SRI. S. SUDARSHAN
4. SMT. RAJEEVI B E AGED ABOUT 33 YEARS, W/O SRI.SOMPALLE PHANINDRA PETITIONER 3 & 4 ARE RESIDING AT FLAT NO.304, THIRD FLOOR, JEYA PRIDE, KAGADASAPURA VILLAGE, (FORMERLY KR PURA HOBLI),
Digitally signed by VANAMALA N Location: HIGH COURT OF KARNATAKA
- 2 -
HC-KAR
CNR: KAHC010682082026 NC: 2026:KHC:55241 WP No. 31128 of 2026
MARATHAHALLI HOBLI, BENGALURU EAST TALUK, BENGALURU- 560093. …PETITIONERS (BY SRI. D.R. RAVI SHANKAR., SENIOR ADVOCATE FOR SRI. NAVEEN G.S., ADVOCATE)
AND:
1. THE CHIEF COMMISSIONER, GREATER BENGALURU AUTHORITY, N.R. SQUARE, BENGALURU 560 002. 2. THE DEPUTY DIRECTOR, TOWN PLANNING, CENTRAL CVR ZONE-1, BENGALURU CENTRAL CITY CORPORATION, BENGALURU 560 002. 3. THE ASST. DIRECTOR, TOWN PLANNING, CENTRAL CVR ZONE-1, BENGALURU CENTRAL CITY CORPORATION, BENGALURU - 560 002. 4. SRI. C. ARUN KUMAR, AGED ABOUT 55 YEARS, SON OF CHIKKAVEERAPPA REDDY EXTENSION KAGGADASAPURA, C.V. RAMAN NAGAR
5. SMT. SHOBHA, W/O SRI C. ARUN KUMAR, AGED ABOUT 53
6. MS. VIDYASHREE, D/O SRI C. ARUN KUMAR, AGED ABOUT 26 YEARS
7. MS. RAMYASHREE,
- 3 -
HC-KAR
CNR: KAHC010682082026 NC: 2026:KHC:55241 WP No. 31128 of 2026
D/O SRI C. ARUN KUMAR, AGED ABOUT 23 YEARS
RESPONDENTS 4 TO 7 RESIDING AT NO. 65, 6TH C CROSS, PATEL EXTENSION KAGGADASAPURA, C.V. RAMAN NAGAR BENGALURU-560 093. 8. M/S JEYA BUILDERS, A REGISTERED PARTNERSHIP FIRM, HAVING ITS OFFICE AT NO. 15, 1ST FLOOR SUNITHA RESIDENCY, 5TH A MAIN ROAD MALLESHPALYA, BENGALURU - 560 075. (REPRESENTED BY ITS PARTNER SRI. N. KALYANA SRINIVASA RAO). 9. SRI. MUKKU THIRUPATHI REDDY, AGED ABOUT 43 YEARS SON OF KRISHNA REDDY MUKKU RESIDING AT SITE NO. 56, MCI LAYOUT, NEAR ACHARYA COLLEGE, SOLADEVANAHALLI, CHIKKABANAVARA BENGALURU - 560 090. …RESPONDENTS (BY SRI.PAWAN KUMAR., ADVOCATE FOR R1 TO R3; SRI.
SURESH S., ADVOCATE FOR R9)
THIS WP IS FILED UNDER ARTICLE 226 OF THE CONSTITUTION OF INDIA PRAYING TO (A) QUASHING THE CONFIRMATION
ORDER BEARING NO.UO.NI.NA.YO./CVR/PR/05/26-27 DATED 28.08.2026 PASSED BY RESPONDENT NO.2 UNDER SECTION 243(3)(E) AND 244(1) OF THE GREATER BENGALURU GOVERNANCE ACT, 2024 PRODUCED AS ANNEXURE-E;
(B) QUASHING THE PROVISIONAL ORDER/NOTICE DATED 07.07.2026 ISSUED BY RESPONDENT NO.2 UNDER SECTION 243(3)(C) AND (D) OF THE ACT PRODUCED AS ANNEXURE D AND D-1 RESPECTIVELY;
(C) QUASHING THE CONSEQUENTIAL NOTICES DATED
- 4 -
HC-KAR
CNR: KAHC010682082026 NC: 2026:KHC:55241 WP No. 31128 of 2026
02.09.2026 ISSUED BY RESPONDENT NO.3 TO (BESCOM) BEARING NO. SA NE NA YO (CV RA NA)/PR/218/26-27 AND (BWSSB) BEARING NO. SA NE NA YO (CV RA NA)/PR/218/26-27 DIRECTING DISCONNECTION OF ELECTRICITY AND WATER SUPPLY RESPECTIVELY TO THE PETITIONERS RESIDENTIAL BUILDING THE SAID NOTICES ARE PRODUCED AS ANNEXURE-F AND F-1 RESPECTIVELY.
THIS PETITION, COMING ON FOR ORDERS, THIS DAY, ORDER WAS MADE THEREIN AS UNDER:
CORAM: HON'BLE MR. JUSTICE B M SHYAM PRASAD
ORAL ORDER
The petitioners assert that they have purchased certain units in a residential flat complex called ‘Jeya Pride’ constructed in Kagadasapura Village, Marathahalli Hobli, Bengaluru East Taluk. The petitioner’s grievance is with the Provisional and Confirmation Orders under Section 243 of the Greater Bengaluru Governance Act, 2024 [for short, ‘the Act’] and the consequential notices addressed to M/s. BESCOM and BWSSB for disruption of power and water connections to the building. - 5 -
HC-KAR
CNR: KAHC010682082026 NC: 2026:KHC:55241 WP No. 31128 of 2026
2. This Court must observe that the impugned Provisional Order is after this Court's order dated 03.07.2026 in W.P.No.22483/2025 [LB-BMP]. The seventh respondent has filed this petition alleging that the Greater Bengaluru Authority [GBA] and its officers have not acted upon his complaint about illegal construction by a developer [the eighth respondent] asserting Agreement to Sell dated 02.01.2024 to purchase a unit in the residential building. This Court has disposed of this petition calling upon the jurisdictional Assistant Executive Engineer/Assistant Director of Town Planning to file a report with the jurisdictional Joint Commissioner or such other authority for the purposes of commencement of proceedings under the GBG Act in the light of the following submissions on behalf of the authorities:
“Mr. B.V. Muralidhar submits that because of census and other responsibilities, the officers have not taken action as contemplated under
- 6 -
HC-KAR
CNR: KAHC010682082026 NC: 2026:KHC:55241 WP No. 31128 of 2026
Section 243 of the Greater Bengaluru Governance Act, 2024 [for short, the GBG Act’], and when queried, the learned counsel submits that proceedings would be begun and a Report in these regards woud be filed into the Court within four [4] weeks from today.”
3. Sri. D. R. Ravishankar, the learned Senior Counsel for the petitioners, submits that this Court must interfere with both the impugned Provisional and Confirmation Orders because of the following circumstances. [A] The proceedings are initiated because of a report consequent to this Court's direction without even an inspection; and even if there is any inspection, it is during the pendency of the earlier petition but that could not be an effective inspection as it is not with due notice to the concerned.
[B] The developer and the owner of the property in which the construction is complete have
- 7 -
HC-KAR
CNR: KAHC010682082026 NC: 2026:KHC:55241 WP No. 31128 of 2026
no subsisting interest because they have sold all the units and the purchasers have not been issued with either notice of inspection or of the Provisional Order. [C] These clearly violate the principles of natural justice, and there is lack of opportunity that is contemplated under Section 243[3][d] of the GBG Act which provides for a personal hearing before there is confirmation of the Provisional Order. 4. Sri. D. R. Ravishankar proposes to canvass that recourse to the proceedings under Section 243 of the GBG Act must not be had only to demolish the building and the scheme under the GBG Act with a Provisional Order and opportunities, including an opportunity of personal hearing and a subsequent Confirmation thereof, is to ensure that the concerned can remove deviations, if any, and
- 8 -
HC-KAR
CNR: KAHC010682082026 NC: 2026:KHC:55241 WP No. 31128 of 2026
ensure that the construction is brought within the compoundable limits or even seek regularization as could be permissible under the statute before there is demolition. 5. Sri. Pawan Kumar, a learned standing counsel who accepts notice for the first to third respondents, and Sri Suresh S., a learned counsel who seeks leave to accept notice for the ninth respondent, are heard in the light of these
submissions and on perusal of records. It stands out that the Provisional Order under Section 243[3][d] of the GBG Act, which records certain deviations in the setback and construction of an additional floor, does not even refer to whom these notices are addressed and it cannot be gainsaid that notice must be addressed to the concerned after due inspection as contemplated under Section 243[2] of the GBG Act.
- 9 -
HC-KAR
CNR: KAHC010682082026 NC: 2026:KHC:55241 WP No. 31128 of 2026
6. This particular failure lends credence to the petitioner's case that the Confirmation Order is without an opportunity that is imperative in the light of the statutory Scheme under Section 243[3] of the GBG Act. The next question is: should this petition be allowed in its entirety quashing both the impugned Provisional and Confirmation Orders as also the communications addressed for disruption of electricity and water supply to the building? This Court is also persuaded to examine the locus of the ninth respondent.
7. The ninth respondent asserts a sale agreement with the builder, which according to the
learned counsel for this respondent, has gone sour with his investments not yielding returns. This only speaks of a private dispute between this respondent and the builder, and this respondent must work out his remedy against the builder. Insofar as the present proceedings, it would suffice for this Court to observe
- 10 -
HC-KAR
CNR: KAHC010682082026 NC: 2026:KHC:55241 WP No. 31128 of 2026
that this respondent has exhausted his locus in initiating the process and it must now be for the petitioners, and those who are similarly placed as purchasers of the units in the complex, to respond to the allegations of deviations in the Sanctioned Plan. This is apart from what the owner and the builder themselves may have to say.
8. The petitioners and the others, including the owner/builder, have not been put on notice as observed earlier and this Court is of the considered view that the Confirmation Order, which refers to the builder as the GPA holder for the owner of the land which is now developed, must be read down to be in continuation of the Provisional Order under Section 243[3][c] with opportunity to the petitioners and the other occupants to respond so that they can avail themselves of the opportunity of personal hearing to demonstrate whether there should be confirmation of the proposition for demolition. Hence, the following:
- 11 -
HC-KAR
CNR: KAHC010682082026 NC: 2026:KHC:55241 WP No. 31128 of 2026
ORDER
[A] The petition is allowed-in-part. The Confirmation Order dated 07.07.2026 is read down as being in continuation of the original Provisional Order dated
28.08.2026.
[B] The petitioners are reserved with liberty to file response to these two orders within eight [8] weeks from today calling upon the second respondent to ensure copies of these two orders are served on every occupant of the complex giving them an opportunity to file response/reply thereto and extend an opportunity of personal hearing to the petitioners and these persons as contemplated under the proviso to
- 12 -
HC-KAR
CNR: KAHC010682082026 NC: 2026:KHC:55241 WP No. 31128 of 2026
Section 243[3][d] of the GBG Act and then decide on whether there must be confirmation.
[C] The communications for disruption of electricity and water supply [Annexures- F and F1] are quashed.
Sd/- (B M SHYAM PRASAD) JUDGE SA Ct:sr