CNR: KAHC010526802026 NC: 2026:KHC:48121-DB WP No. 23997 of 2026
IN THE HIGH COURT OF KARNATAKA AT BENGALURU DATED THIS THE 3RD DAY OF SEPTEMBER, 2026 PRESENT THE HON'BLE MR. JUSTICE D K SINGH AND THE HON'BLE MR. JUSTICE H.SHANTHI BHUSHAN WRIT PETITION NO. 23997 OF 2026 (GM-CON) BETWEEN:
ABHIJITH RAMAPRIYAN AGED ABOUT 34 YEARS, SON OF N RAMAPRIYAN, HAVING HIS OFFICE AT NO. D-2-201, SHRIRAM WHITE HOUSE, 2ND BLOCK, R.T. NAGAR, BENGALURU 560 032 …PETITIONER (BY SRI. VIVEK.B.R.,ADVOCATE)
AND:
C. SHIVARAJU SON OF LATE CHINNAMAREGOWDA, AGED MAJOR, RESIDING AT NO. 249, 12TH CROSS, B BLOCK, SBM LAYOUT, BOGADI, MYSURU- 570 026. …RESPONDENT
THIS WRIT PETITION IS FILED UNDER ARTICLES 226 AND 227 OF THE CONSTITUTION OF INDIA, PRAYING TO A) ISSUE A WRIT OF CERTIORARI, OR A WRIT IN THE NATURE OF CERTIORARI, OR ANY OTHER APPROPRIATE WRIT, ORDER OR DIRECTION, QUASHING AND SETTING ASIDE THE ORDER DATED 04/02/2025 PASSED BY THE DISTRICT CONSUMER DISPUTES REDRESSAL COMMISSION IN CONSUMER COMPLAINT NO.104/2024 (ANNEXURE-A), THE ORDER DATED 30/07/2025 PASSED BY THE STATE CONSUMER DISPUTES REDRESSAL COMMISSION IN FIRST APPEAL NO.SC/29/FA/558/2025 (ANNEXURE-B) AND ORDER DATED
Digitally signed by MALA K N Location:
HIGH COURT OF KARNATAKA
- 2 -
HC-KAR
CNR: KAHC010526802026 NC: 2026:KHC:48121-DB WP No. 23997 of 2026
08/06/2026 PASSED BY THE LEARNED NATIONAL CONSUMER DISPUTES REDRESSAL COMMISSION, NEW DELHI IN SECOND APPEAL NO.367/2026 (ANNEXURE-C) AND ETC.,
THIS PETITION, COMING ON FOR ORDERS, THIS DAY,
ORDER WAS MADE THEREIN AS UNDER:
CORAM: HON'BLE MR. JUSTICE D K SINGH AND HON'BLE MR. JUSTICE H.SHANTHI BHUSHAN
ORAL ORDER
(PER: HON'BLE MR. JUSTICE H.SHANTHI BHUSHAN)
This Writ Petition filed under Article 227 of the Constitution of India, invokes the supervisory jurisdiction of this Court to challenge the order dated 08.06.2026 passed by the National Consumer Disputes Redressal Commission, New Delhi in Second Appeal No.367 of 2026, confirming the order dated 30.07.2025 passed by the Karnataka State Consumer Disputes Redressal Commission, Bengaluru, in First Appeal No. SC/29/FA/558/2025, affirming the
order dated 04.02.2025 passed by the District Consumer Disputes Redressal Commission, Mysore, in Consumer Complaint No.104/2024. 2. Parties are referred as per their ranking before the District Forum. - 3 -
HC-KAR
CNR: KAHC010526802026 NC: 2026:KHC:48121-DB WP No. 23997 of 2026
3. The Complainant, C.Shivaraju, entered into a construction agreement dated 12.06.2020 with M/s Scenic Beauty Homes Private Limited for construction of a residential building at Site No.249, ‘B’ Block, SBM Layout, Bogadi, Mysuru, for a total consideration of Rs.49,90,000/-. According to the complainant, the Company had represented that the construction would be completed within the stipulated time and that there would be no hidden charges and that the construction would be carried out with proper quality. The original date for completion and handing over was stated to be
29.05.2021. The complainant alleged that the construction was not completed within the agreed time and that, though additional time was granted having regard to the COVID-19 pandemic, the work was not completed even by the revised date. He referred to the correspondence exchanged from April 2021 onwards and ultimately issued a termination notice dated
31.03.2022. 4. The Complainant further alleged several defects and incomplete work in the building. The allegations included defects in waterproofing, cracks in the walls and terrace,
- 4 -
HC-KAR
CNR: KAHC010526802026 NC: 2026:KHC:48121-DB WP No. 23997 of 2026
rainwater leakage through the skylight and windows, variation in floor-to-floor height, inadequate beams in the pergola, defects in the staircase and sanitary fittings, improper fixing of floor tiles, electrical works not being carried out according to the drawing and shortfall in the built-up area. It was alleged that the agreed built-up area was 1285 sq.ft. on the ground floor and 1256 sq.ft. on the first floor, whereas only 1206 sq.ft. and 1155 sq.ft. respectively were constructed, resulting in an alleged shortfall of 180 sq.ft. The Complainant also alleged that an additional amount of Rs.20,000/- was collected towards epoxy for the floor tiles and that an amount of Rs.5,41,472/- towards GST had been collected. A technical inspection was subsequently conducted on 28.12.2023, and the complaint was filed before the District Commission on 26.03.2024, claiming compensation and other amounts on the allegation of deficiency in service. 5. The Opposite Party, in his version filed on 10.06.2024, disputed the maintainability of the complaint itself.
It was contended that the construction agreement dated 12.06.2020 had been entered into between the Complainant
- 5 -
HC-KAR
CNR: KAHC010526802026 NC: 2026:KHC:48121-DB WP No. 23997 of 2026
and M/s Scenic Beauty Homes Private Limited and not with the Opposite Party in his individual capacity. The Company had not been impleaded as a party. It was therefore contended that there was no privity of contract between the Complainant and the Opposite Party and that no personal liability could be fastened upon him merely on account of his association with the Company. Objections were also raised on limitation, pecuniary jurisdiction and the existence of an arbitration clause in the agreement. 6. On the factual aspect, the Opposite Party contended that the delay was not attributable to the Company alone. It was stated that the COVID-19 pandemic and lockdowns had affected availability of labour and movement of materials and that, in July 2021, the Complainant had himself commenced interior works at the site despite being requested not to do so until completion of the Company's work. According to the Version, those interior works continued for more than six months and denied the Company free access to the property. It was also contended that the Complainant had withheld payments and had repeatedly altered requirements and
- 6 -
HC-KAR
CNR: KAHC010526802026 NC: 2026:KHC:48121-DB WP No. 23997 of 2026
specifications. The Company issued a detailed reply dated 27.04.2022, followed by the Complainant's reply dated 14.05.2022, and maintained that a substantial portion of the construction had already been completed. The technical report dated 28.12.2023 was disputed on the ground that it had been obtained without notice to or participation of the Opposite Party or the Company. 7. By order dated 04.02.2025 in C.C. No.104/2024, the District Consumer Disputes Redressal Commission, Mysuru, considered the agreement for Rs.49,90,000/-, the stipulated date of handing over as 29.05.2021, the subsequent extension and the correspondence exchanged between the parties.
The Commission referred to the Complainant's notices dated 17.11.2021, 01.12.2021, 28.01.2022, 30.01.2022 and 24.03.2022, and the termination notice dated 31.03.2022. It also referred to the technical report dated 28.12.2023 and the photographs produced by the Complainant. The Commission recorded the defence contained in the reply dated 27.04.2022, including the allegation that the Complainant had commenced
- 7 -
HC-KAR
CNR: KAHC010526802026 NC: 2026:KHC:48121-DB WP No. 23997 of 2026
interior works in July 2021 and thereby affected the progress of the remaining work. 8. The District Commission answered the first point regarding deficiency in service in the affirmative and the second point regarding relief partly in favour of the Complainant. It awarded Rs.2,29,000/- towards the pending work, with interest at 9% per annum from the date of filing of the complaint, together with Rs.1,00,000/- towards mental agony and deficiency in service and Rs.25,000/- towards litigation expenses. The Commission recorded that the Complainant had not produced documents showing the actual amount spent towards completion of the work and proceeded to quantify the amount with reference to the pending work. 9. Aggrieved by the order dated 04.02.2025, the Opposite Party preferred First Appeal No. SC/29/FA/558/2025 before the Karnataka State Consumer Disputes Redressal Commission. The appeal was heard on admission and, by order dated 30.07.2025, styled as an “Order on Admission”, the State Commission dismissed the appeal and confirmed the order of the District Commission. The State Commission referred to the
- 8 -
HC-KAR
CNR: KAHC010526802026 NC: 2026:KHC:48121-DB WP No. 23997 of 2026
evidence regarding delay in completion and the amount
directed to be paid by the District Commission and observed that no valid ground had been urged for interference. The appeal was accordingly dismissed with no order as to costs.
10. The Opposite party thereafter preferred Second Appeal No.367/2026 before the National Consumer Disputes Redressal Commission, New Delhi, along with an application seeking for condonation of 210 days' delay. The State Commission's order dated 30.07.2025 was received by the opposite party on 01.09.2025. According to the National Commission, the period of limitation expired on 30.09.2025, whereas the Second Appeal was filed on 29.04.2026, resulting in the delay from 01.10.2025 to 28.04.2026.
11. In the application for condonation, the Opposite party attributed the delay to personal circumstances and his involvement in attending to the medical needs of his aged grandparents, stating that he was required to attend hospitals and provide care and consequently could not effectively pursue the litigation and furnish timely instructions to counsel. The National Commission considered the explanation and the
- 9 -
HC-KAR
CNR: KAHC010526802026 NC: 2026:KHC:48121-DB WP No. 23997 of 2026
material placed before it. It referred to the requirement that the delay should be satisfactorily explained and observed that the explanation furnished did not account for the delay in the manner required.
12. By
order dated 08.06.2026, the National Commission declined to condone the delay, holding that the Opposite party had failed to show sufficient cause for the delay of 210 days. The Second Appeal was consequently disposed of without examination of the merits of the controversy between the parties. At the same time, the National Commission granted the Complainant, liberty to comply with the District Forum's
order dated 04.02.2025, along with interest at 9% per annum, within two months from the date of the order, while directing that the remaining directions in the District Commission's order would remain unchanged. 13. Aggrieved by the said order, the opposite party has challenged the order of the National Consumer Dispute Redressal Commission before this Court. - 10 -
HC-KAR
CNR: KAHC010526802026 NC: 2026:KHC:48121-DB WP No. 23997 of 2026
14. In the Second Appeal, the Opposite party contended that the Construction Agreement dated 12.06.2020 was between the Complainant and M/s Scenic Beauty Homes Private Limited and that the Opposite party, being an individual Director/Managing Director, was not a party to the agreement in his personal capacity. It was therefore urged that the complaint against him personally was not maintainable in the absence of privity of contract and without impleading the Company. The Opposite party also relied upon the defence regarding the revised completion period, the COVID-19 disruption, the Complainant's commencement of interior works in July 2021, the alleged withholding of payments and the reply notice dated 27.04.2022. 15. The Opposite party further questioned the findings based upon the technical report dated 28.12.2023, contending that the inspection had been conducted without his or the Company's participation. The appeal also raised the pleas of limitation, pecuniary jurisdiction, the arbitration clause contained in the construction agreement, non-consideration of the documents produced with the Version and the absence of
- 11 -
HC-KAR
CNR: KAHC010526802026 NC: 2026:KHC:48121-DB WP No. 23997 of 2026
proof of the actual expenditure allegedly incurred by the Complainant for completing the remaining work. The Opposite party also questioned the manner in which the State Commission, by its order dated 30.07.2025, dismissed the First Appeal without separately dealing with these grounds. 16. The order passed by the District Consumer Disputes Redressal Commission, Mysuru, dated 04.02.2025, is based upon the material placed before it. The construction agreement dated 12.06.2020 stipulated completion and handing over of the house by 29.05.2021. Even the revised date of 28.08.2021 was not adhered to. The complainant had issued communications on 17.11.2021, 01.12.2021, 28.01.2022, 30.01.2022 and 24.03.2022, followed by the termination notice dated 31.03.2022. The District Commission considered the evidence regarding the incomplete and pending works and, on the material before it, recorded deficiency in service. The amount of Rs.2,29,000/- was quantified with reference to the pending works.
The District Commission did not grant the entire amount claimed by the complainant, but awarded
- 12 -
HC-KAR
CNR: KAHC010526802026 NC: 2026:KHC:48121-DB WP No. 23997 of 2026
Rs.1,00,000/- towards mental agony and deficiency in service and Rs.25,000/- towards litigation expenses. 17. The petitioner challenged the said order before the Karnataka State Consumer Disputes Redressal Commission in First Appeal No. SC/29/FA/558/2025. The State Commission, by
order dated 30.07.2025, considered the contention regarding the delay in completion and the explanation offered by the petitioner that the complainant himself had interfered with the construction work and that the Covid-19 situation had affected the work. The State Commission, on consideration of the material which had been placed before the District Commission, recorded that the delay in completion was admitted and that the reasons assigned for non-completion were not acceptable. It further recorded that the evidence disclosed delay in completion of the work and that the complainant was required to complete the remaining work by incurring expenditure. The order of the District Commission was accordingly confirmed.
18. There is also no material before this Court to take a different view of the factual findings recorded by the District
- 13 -
HC-KAR
CNR: KAHC010526802026 NC: 2026:KHC:48121-DB WP No. 23997 of 2026
Commission and affirmed by the State Commission. The
contentions now sought to be urged regarding the role of the complainant in the construction, the effect of the Covid-19 restrictions, the pending works and the technical material had already been raised in the proceedings before the Consumer Commissions. The District Commission considered the evidence and quantified the amount payable only to the extent found established. The State Commission, in appeal, found no valid ground to interfere with that assessment. Thus, the findings are not based merely on the assertion of the complainant, but upon the material which was considered in the proceedings before the District Commission and thereafter examined in appeal.
19. As regards the subsequent proceedings, the order of the State Commission dated 30.07.2025 was received by the petitioner on 01.09.2025. The period for filing the Second Appeal expired on 30.09.2025, whereas the Second Appeal was filed before the National Commission only on 29.04.2026 with an application seeking condonation of 210 days' delay. The explanation placed before the National Commission related principally to the medical condition and treatment of the
- 14 -
HC-KAR
CNR: KAHC010526802026 NC: 2026:KHC:48121-DB WP No. 23997 of 2026
petitioner's grandparents. The National Commission considered the medical documents and the circumstances relied upon, but found that the delay for the entire period had not been satisfactorily explained and declined to condone the delay by
order dated
08.06.2026. The National Commission consequently did not examine the Second Appeal on merits and granted the complainant liberty to comply with the order of the District Commission dated 04.02.2025, along with interest at 9% per annum, within the period stipulated therein.
20. Thus, the order of the District Commission dated 04.02.2025, which contains findings on the delay in completion, the pending works and the resultant deficiency in service, has already been considered and affirmed by the State Commission. The National Commission, in the subsequent proceedings, declined to condone the delay in carrying the matter further and did not disturb the operative directions of the District Commission.
21. Under these circumstances, we find no ground to take a different view of the factual findings recorded by the
- 15 -
HC-KAR
CNR: KAHC010526802026 NC: 2026:KHC:48121-DB WP No. 23997 of 2026
District Commission, which are affirmed by the State Commission and National Commission. The Writ Petition fails and is, accordingly, dismissed. Sd/- (D K SINGH) JUDGE
Sd/- (H.SHANTHI BHUSHAN) JUDGE