KARNATAKA POWER CORPORATION LIMITED v. UNION OF INDIA
WP/30636/2018 · 2026-08-04
M G S Kamal
body2026
DailyLaw.ai
[ 2026 DAILYLAW 62384 (KAR) · dailylaw.ai ]
DailyLaw.ai
[ 2026 DAILYLAW 62384 (KAR) · dailylaw.ai ]
Judgment text
Extracted from the PDF above. The PDF is authoritative.
- 1 -
HC-KAR
CNR: KAHC010098462018 NC: 2026:KHC:40942 WP No. 30636 of 2018
IN THE HIGH COURT OF KARNATAKA AT BENGALURU DATED THIS THE 4TH DAY OF AUGUST, 2026 BEFORE THE HON'BLE MR. JUSTICE M.G.S. KAMAL WRIT PETITION NO. 30636 OF 2018 (GM-RES) BETWEEN:
KARNATAKA POWER CORPORATION LIMITED SHAKTI BHAVAN 82, RACE COURSE ROAD BANGALORE 560001 REP. BY ITS AUTHORISED REPRESENTATIVE MR. D. GANGE GOWDA. …PETITIONER
(BY SRI K. SHASHI KIRAN SHETTY, SENIOR COUNSEL A/W SRI AJAY J. NANDALIKE, ADVOCATE)
AND:
1.
UNION OF INDIA MINISTRY OF COAL REPRESENTED BY THE NOMINATED AUTHORITY 120 F-WING, SHASTRI BHAWAN NEW DELHI - 110001.
2.
STATE BANK OF INDIA INDUSTRIAL FINANCE BRANCH NO.61, "RESIDENCY PLAZA" RESIDENCY ROAD BAGNALROE 560025. …RESPONDENTS (BY SRI H. SHANTHI BHUSHAN, DSGI FOR R1;
SRI B.N. TULSI KUMAR, ADVOCATE FOR R2-VC)
Digitally signed by SUMA B N Location: HIGH COURT OF KARNATAKA
- 2 -
HC-KAR
CNR: KAHC010098462018 NC: 2026:KHC:40942 WP No. 30636 of 2018
THIS WRIT PETITION IS FILED UNDER ARTICLES 226 AND 227 OF THE CONSTITUTION OF INDIA PRAYING TO QUASH BY A WRIT OF CERTIORARI OR ANY OTHER APPROPRIATE WRIT OR DIRECTION THE COMMUNICATION OF THE 1ST RESPONDENT BEARING NO.F.NO.103/14/2015/NA DATED 13.07.2018, AT ANNEXURE-A AND ETC.,
THIS PETITION, COMING ON FOR PRELIMINARY HEARING IN 'B' GROUP, THIS DAY, ORDER WAS MADE THEREIN AS UNDER:
CORAM: HON'BLE MR. JUSTICE M.G.S. KAMAL
ORAL ORDER
1. Petitioner-Karnataka Power Corporation Ltd., a State of Karnataka undertaking, is before this Court being aggrieved by the communication dated 13.07.2018 issued by respondent No.1, proposing to appropriate bank guarantee of Rs.6,22,80,000/-, which was furnished by the petitioner towards performance guarantee, on the premise of non compliance of terms of allotment agreement governing allocation of coal mines of Baranj-I-IV, Kiloni and Manora Deep, seeking following reliefs:
"a. Quash by a writ of Certiorari or any other appropriate writ or direction the communication of the 1st Respondent bearing No.F.No.103/14/2015/NA dated 13/07/2018, at Annexure A; OR, in the alternative,
- 3 -
HC-KAR
CNR: KAHC010098462018 NC: 2026:KHC:40942 WP No. 30636 of 2018
b. Restrain the 1st Respondent from taking any coercive action under the Coal Mines (Special Provisions) Act, 2015; c. Issue such other writ or order as this Hon'ble Court may deem fit in the circumstance of the case. d. Award costs of the writ petition."
2. Facts of the case in brief are: (a) That petitioner corporation has a total installed capacity of about 8824 MW consisting of Hydro- Electric Stations, Thermal Power Plants (Coal based and Gas based) Windmills and Solar PV Plants. (b) Respondent No.1, a Nominated Authority set up under Section 6 of the Coal Mines (Special Provisions) Act, 2015, (for short `Act, 2015) which controls the process of coal block allotment. (c)Respondent No.2-bank is the one which had issued the bank guarantee dated 17.04.2015 for a sum of Rs.77,85,00,000/- towards performance security. (d)Karnataka EMTA Coal Mines Limited(KECML) in which the petitioner holds 26% share had been allotted Baranj-I-IV, Kiloni and Manora Deep Coal Blocks with the condition that the coal so
- 4 -
HC-KAR
CNR: KAHC010098462018 NC: 2026:KHC:40942 WP No. 30636 of 2018
mined will be utilized only in the petitioner's Thermal Power Plant at Ballari. The mining lease was granted by the Ministry of Coal and State of Maharashtra in the name of said KECML. (e) A Fuel Supply Agreement was entered into between petitioner and KECML and operations were commenced and were running till
31.03.2015. The process of allotment was challenged before the Apex Court in the case of Manohar Lal Sharma Vs Principal Secretary and Others reported in (2014) 9 SCC 516. Pursuant to which all coal block allotments made were set aside by order dated 25.08.2014.
All mining leases thus stood cancelled and the agreements i.e. mining lease, JV agreements, fuel supply agreements entered into with KECML stood nullified. (f) Thereafter the Coal Mines (Special Provisions) Act, 2015 (referred to as `Act, 2015) came into force which governed the allotment of cancelled coal blocks, payment of compensation to the prior allottees and other ancillary issues which were not covered in the aforesaid judgment of the Apex Court. Said Act, 2015 provided for fresh application to be filed by the Government companies such as the petitioner under Section 5
- 5 -
HC-KAR
CNR: KAHC010098462018 NC: 2026:KHC:40942 WP No. 30636 of 2018
of the Act, 2015. Accordingly, petitioner herein had made an application for allotment of coal block under the said Act, 2015. (g) Pursuant to such application, petitioner had been allotted Baranj-I-IV, Kiloni and Manora Deep Coal Blocks and an allotment agreement dated 26.03.2015 was entered into between the petitioner and respondent No.1, providing details of the operation of the mines. Pursuant thereof, an allotment order dated 31.03.2015 was issued in favour of the petitioner for the purpose of meeting the coal requirements for its Ballari Thermal Power Station. Petitioner had given an undertaking dated 27.03.2015 to the respondent No.1, agreeing to furnish a performance guarantee, upfront payment and fixed amount. Accordingly, a bank guarantee for Rs.77,85,00,000/- was furnished by the petitioner. (h) Clause 10 of the Allotment Agreement entered into between the petitioner and respondent No.1 to conduct mining operations at the coal mine provided milestones (Efficiency Parameters) to be achieved as provided at Schedule E to the agreement. Annexures 3 and 4 of the allotment
order listed out various statutory licenses, permits, permissions, approval or consents to be obtained
- 6 -
HC-KAR
CNR: KAHC010098462018 NC: 2026:KHC:40942 WP No. 30636 of 2018
by the petitioner from the Central Government and the State Governments respectively. Fulfillment of these requirements were considered to form part of the efficiency parameters mentioned at Schedule E to the allotment agreement. The allotment agreement was subsequently amended by amendment agreement dated 26.12.2016 whereby, Schedule E indicating efficiency parameters was amended to include the weightage of calculating the deduction of performance security in the event of failure or delay in achieving the milestones. (i) It is contended that petitioner made all necessary application to the Central Government, various State Governments and the State Authorities seeking transfer of approvals/licenses/clearances in favour of the petitioner. Major approvals were obtained. However some clearances like land mutation and Forest Stage II clearance were pending before the District Collector of Chandrapur despite diligent follow-up by the petitioner. Permission from the Director General of Mine Safety(DGMS), Explosives licence and Mine Opening Permission from Coal Controllers Office (CCO) is pending due to non appointment of Mine Development Operator (MDO). Petitioner had been submitting monthly pre-commencement reports as
- 7 -
HC-KAR
CNR: KAHC010098462018 NC: 2026:KHC:40942 WP No. 30636 of 2018
required under Clause 7.1(a) of the Allotment Agreement dated 26.03.2015. (j) Things stood thus, respondent No.1 issued a show cause notice on 06.11.2017 for purported non-compliance of efficiency parameters provided under allotment agreement by the petitioner stating the alleged non-compliance by the petitioner. On receipt of the said show cause notice, petitioner has submitted a comprehensive reply dated 24.11.2017. (k) Scrutiny Committee constituted by Ministry of Coal, Government of India at New Delhi convened meeting on 30.01.2018, examined the issues of non-compliance and efficiency parameters as well as the reply submitted by the petitioner. The Scrutiny Committee on examination of the matter held petitioner was directly responsible only to the extent of issue of permissions from Director General of Mine Safety -DGMS. (l) As regards delays in grant/execution of the mining lease, the Scrutiny Committee observed that the State of Maharashtra had delayed in providing clarity regarding pendency of payment of royalty which in turn had delayed grant/execution of mining lease.
Scrutiny Committee had also observed delay in obtaining
- 8 -
HC-KAR
CNR: KAHC010098462018 NC: 2026:KHC:40942 WP No. 30636 of 2018
the Explosives licence was caused due to delay in issuance of NOC from the District Collector at Chandrapur. Scrutiny Committee had also noted the Forest Stage II clearance had not been obtained by the prior allottee of the mine and as such had to be obtained afresh by the petitioner. It had further observed that Forest Stage II clearance did not form part of the list of clearances that were required to be obtained by the petitioner in keeping with efficiency parameters. Committee had called upon the respondent No.1 to clarify the issue further. It had also found that application had been made in time by the petitioner. The delay in obtaining the environmental clearance was not attributable to the petitioner. (m) As regards the mining operation permission, the Scrutiny Committee found the same was contingent upon obtaining all statutory clearance including Forest Stage II clearance which was pending and the delay could not be attributable to petitioner. The committee therefore held that there was no delay attributable to the petitioner and the same was beyond the control of the petitioner. (n)The committee accordingly directed the State of Maharashtra to give its response to the
- 9 -
HC-KAR
CNR: KAHC010098462018 NC: 2026:KHC:40942 WP No. 30636 of 2018
observation made by the committee regarding delay. Petitioner has not been informed as to any response issued by the State of Maharashtra. (o) Petitioner was given an option of adopting and continuing with the prior contract entered into in relation to coal mining operations in terms of Section 11 of the Act, 2015. Petitioner however did not exercise the said option.
(p) Thus, despite there being a scrutiny and finding of reasons for delay by the Scrutiny Committee, which is the constituent of nominated authority, impugned Communication dated 13.07.2018 as per Annexure-A has been issued causing hardship and prejudice to the petitioner constraining it to approach this Court seeking aforesaid reliefs. 3. Sri.K.Shashi Kiran Shetty, learned Senior counsel reiterating the facts and the grounds and taking this Court through the records more particularly to Clause 10 of the Allotment Agreement and Schedule E efficiency parameters and juxtaposing the same with the opinion of the Scrutiny Committee even as extracted by the respondent No.1 in the impugned communication at paragraphs 3 and 4, submitted that the respondent-
- 10 -
HC-KAR
CNR: KAHC010098462018 NC: 2026:KHC:40942 WP No. 30636 of 2018
nominated authority is unjustified in issuing the impugned communication without application of mind to the reasoning and the conclusion arrived at by its very own constituent, namely the Scrutiny Committee. Therefore seeks for allowing of the petition. 4. Sri.H.Shanthi Bhushan, learned DSGI appearing for the respondent-Union of India, at the outset questioned the maintainability of the writ petition citing Section 27 of the Act, 2015, providing for appeal. He also refers to Clause 25 of the allotment agreement providing for dispute resolution mechanism. Thus, he insists dispute if any between the petitioner and the respondent No.1 falling within Clause 25 and the dispute involving performance, non-performance, breach of the terms in the contract requires to be adjudicated in the manner provided thereunder. 5. That the communication impugned is preceded by two show cause notices dated 21.07.2016 and 06.11.2017 and petitioner not furnishing the cause for the delay has resulted in issuance of impugned communication. That
- 11 -
HC-KAR
CNR: KAHC010098462018 NC: 2026:KHC:40942 WP No. 30636 of 2018
failing to comply with the efficiency parameters provided under Schedule E has resulted in the present stalemate which requires to be adjudicated in the manner known to law and agreed between the parties and writ petition of this nature cannot be entertained. Hence seeks for dismissal of the petition. 6.
Heard and perused the records. 7. The facts noted above do not require reiteration. Appropriate for the purpose of this dispute is Clause 10 of the agreement which read as under:
"10. EFFICIENCY PARAMETERS
10.1. The conduct of mining operations at the Coal Mine shall be subject to the milestones listed in SCHEDULE E (the
"Efficiency Parameters"). 10.2. The Allottee would provide periodic information to the Nominated Authority and the Central Government regarding compliance with the Efficiency Parameters in the manner stipulated in Clause 7 (INFORMATION). 10.3. Any non compliance with the Efficiency Parameters would result in appropriation of the Performance Security in the manner stipulated in Clause 6 (PERFORMANCE SECURITY) and in case where such non-compliance exceeds for more than five instances, such non-compliance may also result in termination of this Agreement as provided in Clause 24 (EFFECTIVE DATE, TERM AND TERMINATION)."
- 12 -
HC-KAR
CNR: KAHC010098462018 NC: 2026:KHC:40942 WP No. 30636 of 2018
SCHEDULE E-EFFICIENCY PARAMETERS Sl. No. Milestone Time Limit in Months (from the date of the Allotment Order)
1. Application for transfer of Statutory permission to the successful bidder 1
2. Completion of transfer of Statutory permissions obtained by the Prior Allottees 3
3. Reporting of Deviations from approved Mining Plan (if any) 4
4. Ratification of Deviations/Approval of Revised Mining Plan including Mine Closure Plan (if necessary) 10
5. Approval of Mine Closure Plan (if not approved earlier) 6 (in case of no deviation)
6. Opening of Escrow Account (if not opened earlier) 6 (in case of no deviation)
7. Schedule of Production/ Reaching Rated Capacity As per approved Mining Plan
8. EUP Synchronisation As per approved Mining Plan
8. Relevant also to refer Annexures- 2, 3 and 4 providing for statutory licences, permits, permissions, approvals or consents issued by the Central Government which are being transferred to be obtained by the allottee.
- 13 -
HC-KAR
CNR: KAHC010098462018 NC: 2026:KHC:40942 WP No. 30636 of 2018
Annexure-2: Particulars of statutory licences, permits, permissions, approvals or consents issued by the Central Government which are being transferred along with this Allotment order
Sl. No. Statutory Clearance Ministry Letter No. Date Approval of a) Mining Plan and 13016/12/2004 -CA 08.12.2004
1. b) Revised Mining Plan and Mine Closure Plan- Approval of Revised Mining Plan (April 2011) and Mine Closure Plan (June 2011) for Kiloni, Manoradeep and Baranj I-IV Captive Coal blocks of Wardha - Valley Coalfield, District Chandrapur, Maharasthra of M/s Karnataka Emta Coal Mines Limited.- Reg. Ministry of Coal 13016/18/2004 -CA-I (Part) 24.08.2011
2. Mining Lease- Administrative Approval of the Central Government under Section 5 (1) and/ or Section 6(1) of MMDR Act, 1957 Ministry of Coal 13016/33/2003- CA-I 21.01.2006
- 14 -
HC-KAR
CNR: KAHC010098462018 NC: 2026:KHC:40942 WP No. 30636 of 2018
Annexure -3 Particulars of statutory licences, permits permissions, approvals or consents issued by the Central Government to be obtained on application by the Allottee Sl. No. Statutory Clearance Ministry Letter No. Date
1. Environment Clearance Ministry of Environment and Forests J- 11015/400/2005- IA.II(M) 18.05.2006
2. Forest Clearance Stage 1 Ministry of Environment and Forests F.No.8-52/2011- FC 09.12.2011
3. Mine Opening permission Ministry of Coal CCO CC/MCBA/Open/ Baranj OCP/KECML/07- 08/2 04.06.2007
4. Opening of Escrow Account Ministry of Coal CCO
5. Permission from DGMS for Mine Opening Notice in Form I regarding opening of mine under CMR, 1957 Ministry of Labour-DGMS KECML/NGP/AO/ 626 24.01.2007
6. Permission of installation/Trial Operation of Equipment Ministry of Labour - DGMS
7. Ground Water clearance Ministry of Environment and Forests- Central Ground Water Board GSDA/Sr. Geo/Chn/Tech/ KECML/ Consent 14.12.2015
8. Railway Siding Approvals Ministry of Railway
9. Explosive Licenses Ministry of Commerce, DIPP
10. Diesel Storage Tank Ministry of Commerce, DIPP
11.
(Any Other Clearance)
- 15 -
HC-KAR
CNR: KAHC010098462018 NC: 2026:KHC:40942 WP No. 30636 of 2018
Annexure -4: Particulars of statutory licences, permits, permissions approvals or consents issued by the State Government to be obtained on application by the Allottee Sl. No. Statutory Clearance Ministry Letter No. Date
1. Consent to establish State pollution Control Board BO/RO/(P&P)/ CC-28 29.10.2005
2. Project Import Benefit State Mineral Resource Department
3. Grant of Mining Lease State Government MMN- 1005/C.R.813 /Ind-9 12.09.2006
4. Land Mutation State Government
5. Power Line from State Electricity Board State Electricity Board
6. (Any Other Clearance)
9. The show cause notices dated 21.07.2016 and 06.11.2017 issued by the respondent No.1 alleging non-compliance with the timeline of various milestones provided under the allotment agreement is extracted at paragraph 2 of the impugned communication which read as under:
2. M/s.KPCL has been issued two Show Cause Notices dated 21.07.2016 and 06.11.2017 for non compliance with the timelines of various Milestones listed in Allotment Agreement in respect of Baranj-I-IV, Kiloni & Manora Deep coal mine, as detailed below. - 16 -
HC-KAR
CNR: KAHC010098462018 NC: 2026:KHC:40942 WP No. 30636 of 2018
Sl. No. Milestone as per Efficiency Parameters Due Date for Completion of Milestone Actual Date of achievement of Milestone Weightage prescribed for apportion of performance Security (in %)
1. Application for transfer of Statutory permissions
i Explosive License 01.05.2015 30.05.2015 12 ii Permissions from DGMS 01.05.2015 30.05.2015
iii Land Mutation 01.05.2015 03.06.2015
Transfer of following Statutory Permissions which has not been complied with 8 I Grant/Execution of Mining Lease 01.07.2015 07.11.2015 ii Environment Clearance 01.07.2015 06.07.2015 iii Forest Clearance Stage -II 01.07.2015 NO iv Mine opening permission 01.07.2015 NO V Permission from DGMS 01.07.2015 NO vi Explosive License 01.07.2015 NO
vii Land Mutation 01.07.2015 NO
viii Power Line from State Electricity Board 01.07.2015 02.02.2016
Schedule of Production/Reaching Peak Rated Capacity Target Schedule of Production Actual Production
For Year 2015-16
2.50 MT NO 20
3.
For year 2016-17 2.50 MT NO 20
10. Perusal of the aforesaid annexures and the alleged non- compliance of timeline more particularly the grant of
- 17 -
HC-KAR
CNR: KAHC010098462018 NC: 2026:KHC:40942 WP No. 30636 of 2018
mining lease and environmental clearance as rightly pointed out by learned Senior counsel are insignificant and are highly disproportionate to the steps sought to be taken i.e., appropriation of bank guarantee in a sum of Rs.6,22,80,000/-. 11. The impugned communication also refers to constitution of a Scrutiny Committee to consider/examine the
submissions/replies made by the Successful Bidders/Allottees of the coal mines in respect of deviation from the Efficiency Parameters as mentioned in the Coal Mine Development and Production Agreement/Allotment Agreement. The reply to the said Show Cause Notice(s) submitted by the Allottee was admittedly placed before the Scrutiny Committee in its fifth meeting held on 30.01.2018. 12. Learned Senior counsel submitted that the matter was considered threadbare by Scrutiny Committee, which is none other than the constituent of the respondent No.1 and that the respondent No.1 without adverting to the report of the scrutiny committee has concluded that the petitioner has not complied with the timeline in achieving the
- 18 -
HC-KAR
CNR: KAHC010098462018 NC: 2026:KHC:40942 WP No. 30636 of 2018
milestones/efficiency parameters provided at Schedule E to the agreement. 13. Scrutiny Committee admittedly has been constituted in terms of Rule 6 of the Coal Mine (Special Provisions) Rules, 2014, which read as under:
6. Central Government to Act through Nominated Authority. (1) The Central Government shall appoint an officer not below the rank of a Joint Secretary to the Government of India as the nominated authority who shall act for and on behalf of the Central Government for the purposes of this Act and shall exercise such powers as may be prescribed. (2) The nominated authority may engage any expert having such qualifications and experience and on such terms and conditions as may be prescribed to make recommendations to the authority for the conduct of auction and in drawing up of the vesting order or allotment order in relation to Schedule I coal mines. (3) The Central Government shall act through the nominated authority for the following purposes, namely:—
(a) conduct the auction process and allotment with the assistance of experts;
(b) execution of the vesting order for transfer and vesting of Schedule I coal mines pursuant to the auction;
(c) executing the allotment order for any Government company or corporation in pursuance of section 5;
(d) recording and mutating incorporeal rights of whatsoever nature including, consents, permissions, permits, approvals, grants, registrations;
(e) collection of auction proceeds, adjustment of preferential payments and transfer of amount to the respective State Governments where Schedule I coal mine is located in accordance with the provisions of this Act.
- 19 -
HC-KAR
CNR: KAHC010098462018 NC: 2026:KHC:40942 WP No. 30636 of 2018
(4) The nominated authority shall complete the auction or execute the allotment orders of Schedule I coal mines within such time and in accordance with such rules as may be prescribed. (5) The Central Government may appoint such other officers and staff as it may think fit to assist the nominated authority. (6) The salaries and allowances and other terms and conditions of service of the nominated authority and such other officers and staff appointed under this section shall be such as may be prescribed. (7) The nominated authority shall be bound by the written direction given by the Central Government on the question of policy."
14. That there is no dispute that the Scrutiny Committee which was assigned the task of verifying the compliance of the timeline of the petitioner has been nominated by the Central Government in furtherance to Rule 6 and in furtherance to Clause 26.14 of the Allotment Agreement which vests the Central Government with power to act through a nominated authority pursuant to ordinances and rules. 15. Relevant to refer to paragraphs 3 and 4 of the impugned communication which read as under:
3. It is mentioned that a Scrutiny Committee has been constituted to consider/ examine the submissions/ replies
- 20 -
HC-KAR
CNR: KAHC010098462018 NC: 2026:KHC:40942 WP No. 30636 of 2018
made by the Successful Bidders/Allottees of the coal mines in respect of deviation from the Efficiency Parameter as mentioned in the Coal Mine Development and Production Agreement/ Allotment Agreement. The reply to the said Show Cause Notice(s) submitted by the Allottee was placed before the Scrutiny Committee in its fifth meeting held on 30.01.2018. The Allottee company was also given the opportunity to present its case before the Committee. After due deliberation of the submissions in respect of the said coal mine and the recommendation of the Committee, it has been decided that action for apportion of Performance Security in terms of provisions of the Allotment Agreement may be taken for non compliance in respect of below mentioned Milestones. Sl. No. Show Cause Reason Weightage of performance bank guarantee to be apportioned as prescribed as guidelines as per milestones (in %)
Recommendation of the Scrutiny committee Comments of Government of Maharashtra
1.
Delay in grant/Execution of mining lease i.e., on 07.11.2015 (Due Date- 01.07.2015)
8 The application for ML was made timely by the Allottee i.e., on 06.04.2015 • The delay is of small duration (five days) The delay is intermediate stage not directly resulting in delay in production. • The subsequent delay of four months in execution of ML i.e., on 07.11.2015 was caused due to non-clarity regarding payment of Royalty at the end of the State Government. The Government of Maharashtra, Industries Energy and Labour Department Mantralaya, Mumbai has granted the mining lease in favors of M/s.Karnataka Power Corporation Limited vide
Order No MMN- 0515/CR.50/IND-9 dated 16.07.2015 for a period of 30 years. The Director, Geology & Mining Government of Maharashtra, Nagpur has submitted From- K Mining leases agreement vide letter date 05.08.2015 and intimated the amount of Stamp Duty Payable as Rs.7,50,44,800/- with respect to Mining lease agreement. Accordingly the payment of stamp duty was made by E-payment mode in the mahakosh website of Govt. of Maharashtra on 06.11.2015 and the Mining lease agreement has been executed on 07.11.2015. 2. Issued Show Cause for non compliance with
"Transfer of Forest Clearance"
It is to state that only FC-I was vested vide Allotment order which was transferred to KPCL on
13.05.2015. However, Forest Stage-II clearance was not obtained by the Prior FC-1 was transferred from M/s.Karnataka EMTA Coal Mines Ltd. To M/s.Karnataka Power Corporation Ltd. Vide letter on 13.05.2015. Forest Stage-II clearance has not
- 21 -
HC-KAR
CNR: KAHC010098462018 NC: 2026:KHC:40942 WP No. 30636 of 2018
4. On this subject, as per clause 6.2.1(d) of the Allotment Agreement dated 26th March 2015, Performance Security may be appropriated by the Nominated Authority upon failure of the Allottee to comply with the Efficiency Parameters as required under clause 10. Further, Clause 6.3.1 read with Schedule `E' provides the Nominated Authority unconditional right to appropriate the Performance Security for deviation from timeline of Milestones as stated at para 3 above, to the extent of 8% , on the basis of weightages imputed by the Central Government vide its O.M. dated 21.04.2015. 16. Perusal of the aforesaid observations/recommendations made by the Scrutiny Committee clarifies that the delay in petitioner obtaining the mining lease was just 5 days which was not attributable to the petitioner. Further non- compliance with regard to transfer of Forest clearance was also not attributable to the petitioner as that was required to be issued by the District Collector Chandrapur, who had caused the delay. The Scrutiny Committee's finding, as noted above, is with reference to Annexure/Schedule-E, which is not done (Due Date- 01.07.2015) allottee and as such had to be obtained afresh by SB. Timelines of Milestones stipulated in Efficiency Parameters provides for transfer of Statutory Clearances within three months from Allotment Date. Because, stage II forestry clearance is not separately mentioned but included in Forestry clearance as mentioned in the CMPDPA needs to be clarified by the office of Nominated Authority. been issued.
Collector Chandrapur, has informed to the M/s.Karnataka Power Corporation Ltd. vide letter dated 20.03.2018 to depute one officer for liasoning with Gram Panchayat, Panchayat samiti and officer of the Sub Divisional Officer, Warora. - 22 -
HC-KAR
CNR: KAHC010098462018 NC: 2026:KHC:40942 WP No. 30636 of 2018
Annexure-2(2) and Annexure 3(2) and Annexure 4(3) of the allotment agreement. The scrutiny committee has thus, in effect, has not found any delay or non-compliance of the terms of the allotment agreement by the petitioner- corporation. 17.Notwithstanding the above-categoric observation and conclusion by the Scrutiny Committee, the respondent has proceeded to issue the impugned communication with a threat to invoke the bank guarantee. 18. In addition to the aforesaid recommendation, the scrutiny committee has further issued direction calling for response from the State of Maharashtra as seen at Annexure-J, Minutes of fifth meeting of the Scrutiny Committee held on
30.01.2018. 19. In the light of the aforesaid undisputed facts revealed from the records, the opposition to the petition on the question of maintainability in the light of purported availability of the alternate dispute mechanism as raised by learned DSGI cannot be countenanced. If there was a
- 23 -
HC-KAR
CNR: KAHC010098462018 NC: 2026:KHC:40942 WP No. 30636 of 2018
genuine dispute, provisions contained in Clause 25 of the Allotment Agreement and Section 27 of the Act, 2015, could have been invoked. A dispute of a moonshine in nature cannot be referred to as it serves no purpose. The categorical finding by the Scrutiny Committee leaves no doubt firstly, there was no delay; secondly even if there were to be the same could not be attributed to the petitioner-corporation. Invocation of bank guarantee or any stringent action as sought to be taken would arise only in the event of prima facie establishment of failure on the part of the petitioner in fulfilling the efficiency parameters.
That not having been met with, the impugned communication cannot be sustained. The contention regarding writ being not maintainable as it involves contractual and complex issue also cannot be countenanced. 20. Accordingly, following:
ORDER (i) Petition is allowed. (ii) Impugned communication dated 13.07.2018 passed by respondent No.1 at Annexure-A is quashed.
- 24 -
HC-KAR
CNR: KAHC010098462018 NC: 2026:KHC:40942 WP No. 30636 of 2018
(iii) Matter is remitted to respondent No.1- authority, who shall take into consideration the recommendation made by the Scrutiny Committee and re-examine the matter and pass appropriate orders, after giving opportunity to the petitioner of hearing, within an outer limit of six months from the date of receipt of certified copy of this
order. (iv) Petitioner is at liberty to furnish additional documents/ representation, response, if so advised. (v) No precipitative action shall be taken by the respondent No.1- authority in the nature of invoking bank guarantee until passing of the order as directed. It is further made clear if in the event of petitioner being aggrieved by the order to be passed by respondent No.1, petitioner is at liberty to approach the appellate authority and the bank guarantee shall not be invoked until the petitioner approaches the appellate authority within the time provided under law.
SD/- (M.G.S. KAMAL) JUDGE