C.M.P.No.18708 of 2026 __________ Page1 of 2 IN THE HIGH COURT OF JUDICATURE AT MADRAS DATED: 22-07-2026 CORAM THE HON'BLE MR.JUSTICE S.M.SUBRAMANIAM AND THE HON'BLE MR.JUSTICE N.SENTHILKUMAR C.M.P.No.18708 of 2026 AND W.A.SR.No.111446 OF 2026
1. The Chairman cum Managing Director Tamil Nadu Generation Distribution Corporation Ltd No 144 Anna Salai Chennai 600 002 and 3 Others. … Appellants -vs-
1. Natrajan and 6 Others … Respondents Prayer: To condone the delay of 457 days in filing the Writ appeal against the order dated 06.03.2025 passed in W.P.No.17826 of 2019. For Appellants: Mr.Venkatesh Prasad For M/s.Advit Law Chambers For Respondents: Ms.R.Shruthi for R1 To R6 ***** O R D E R (Order of the Court was made by S.M.Subramaniam J.) This petition has been filed to condone the delay of 457 days in filing the Writ appeal against the order dated 06.03.2025 passed in W.P.No.17826 of 2019. https://www.mhc.tn.gov.in/judis
C.M.P.No.18708 of 2026 __________ Page2 of 2
2. Learned counsel for R1 to R6 stated that respondents have no objection in condoning the delay.
3. Being satisfied with the reasons stated in the affidavit filed in support of the petitioner, the present Miscellaneous Petition is ordered. The delay of 457 days is condoned.
(S.M.S.,J.) (N.S.,J.) 22-07-2026 AR Note:Registry is directed to number the appeal, if it is otherwise in order and list the same for hearing in usual course. https://www.mhc.tn.gov.in/judis