M/S AMAR CONSTRUCTION v. GOVERNMENT OF NCT OF DELHI
O.M.P.(MISC.)(COMM.)/258/2026 · 2026-03-23
Avneesh Jhingan
body2026
DailyLaw.ai
[ 2026 DAILYLAW 5551 (DEL) · dailylaw.ai ]
DailyLaw.ai
[ 2026 DAILYLAW 5551 (DEL) · dailylaw.ai ]
Judgment text
Extracted from the PDF above. The PDF is authoritative.
$~77 * IN THE HIGH COURT OF DELHI AT NEW DELHI + O.M.P.(MISC.)(COMM.) 258/2026
M/S AMAR CONSTRUCTION
.....Petitioner
Through: Mr. Rajeev Kumar, Adv.
versus
GOVERNMENT OF NCT OF DELHI
.....Respondent Through: Mr. Bharat Singh Sisodia, Adv. (through VC)
CORAM:
HON'BLE MR. JUSTICE AVNEESH JHINGAN
O R D E R %
23.03.2026
1. This petition is filed under Section 29A of the Arbitration & Conciliation Act, 1996 seeking extension of period for concluding the arbitration proceedings.
2.
Learned counsel for the respondent has no serious objection to the prayer made.
3. In view of the above, the time period for conclusion of the proceedings is extended by six months as prayed for.
4. This petition is disposed of in the aforesaid terms.
AVNEESH JHINGAN, J MARCH 23, 2026 ‘ha’
This is a digitally signed order. The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above. The Order is downloaded from the DHC Server on 30/03/2026 at 16:06:26