07.10.2026 Item No.29 Court No. 30 g.b. WPA 21351 of 2024
Nemai Sardar -vs- Employees’ Provident Fund Organization & Ors.
Ms. Aparna Banerjee … for the P.F. Authority
Ms. Amrita Pandey Mr. Ghanshyam Pandey … for the Delta Ltd.
1. None appears for the petitioner.
2. Ms. Banerjee, learned counsel appearing for the Provident Fund Authority submits that the amount received by the RPF Authority has been disbursed on prorata basis.
3. It is now submitted by Ms. Banerjee that the petitioner is also getting his pension as the matter has been processed.
4. It is submitted by the respondent authorities that as the provident fund amount has been paid by the private respondent when it was due, and no specific calculation of interest has been provided by the petitioner, the petitioner’s claim is to be treated as fully settled.
5. In view of the said fact and circumstances, the writ application is disposed of.
2
2
6. Connected application, if any, stands disposed of.
7. Urgent photostat certified copy of this order, if applied for, be supplied to the parties upon compliance with all requisite formalities.
(Shampa Dutt (Paul), J.)