GLOSTER LTD AND ANOTHER v. ULUBERIA MUNICIPALITY AND OTHERS
WPA/20145/2026 · 2026-10-05
Raja Basu Chowdhury
body2026
DailyLaw.ai
[ 2026 DAILYLAW 48165 (CAL) · dailylaw.ai ]
DailyLaw.ai
[ 2026 DAILYLAW 48165 (CAL) · dailylaw.ai ]
Judgment text
Extracted from the PDF above. The PDF is authoritative.
05.10.2026 Ct. 3 Item No.
AD 12 Saswata
WPA 20145 of 2026 Gloster India & anr. Versus Uluberia Municipality & Ors. Mr. Saptanshu Basu, Sr. Adv. Mr. S. Sen Gupta Mr. Sushovit Dutt Majumder Ms. Mini Agarwal Mr. Sagnik Shaw …For the petitioner Mr. Gobindo Chandra Bandyopadhyay Mr. Sourav Goswami …For the Uluberia Municipality Mr. Pinak Kumar Mitra Mr. Subhanwita Ghosh Ms. Ankita Dutta …For the respondent nos. 6 and 7
1. Complaining illegal construction at the behest of the respondent nos. 6 and 7 and the failure on the part of the municipal authorities to take note of such illegal construction and to proceed in accordance with law on the basis of the petitioners’ representations dated 3rd April 2026 and 17th July 2026, the instant writ petition has been filed. 2. The private respondents are represented. 3. Learned advocate appearing for the private respondents would submit that there a suit pending between the private parties and there is a subsisting order of injunction as well. 4. The Uluberia municipality is also represented. 5. Learned advocate appearing for the municipality by placing before this Court a notice dated 10th April 2026 submits that on the basis of the inspection carried out by the municipality, two several stop work notices have been issued which are individually addressed to the respondent
2 nos. 6 and 7. Let copies of both the stop work notices and the inspection report as placed before this Court by the learned advocate appearing for the municipality be retained with the record. 6. Having regard to the disclosure made, and noting that the municipality had already taken steps and had issued stop work notices, I am of the view that the municipality must bring the proceeding to a logical conclusion. Till such time a decision is taken by the municipality in accordance with the provisions of Section 218 of the West Bengal Municipal Act, 1993, no further construction can be carried out at the locale. 7. It is expected that the decision shall be taken on an expeditious basis preferably within a period of 12 weeks from the date of communication of this order by passing a reasoned order upon giving opportunity of hearing to the interested parties including the petitioners. 8. With the above direction and observations the writ petition is disposed of. 9.
All parties shall act on the basis of server copy of this order duly downloaded from this Court’s official website. (Raja Basu Chowdhury, J.)