IN THE HIGH COURT OF ANDHRA PRADESH AT AMARAVATI (Special Original Jurisdiction)
THURSDAY, THE 12th DAY OF NOVEMBER 2026 PRESENT THE HONOURABLE SRI JUSTICE VENKATESWARLU NIMMAGADDA WRIT PETITION NO: 33960 OF 2017 Between:
1. SALADI VEERA BADRA RAO, EG DIST, S/o Nagabhusanam, Hindu, aged about 58 years, Occ : Aqua Culture, Rio. Cheyyeru Jellagunta, H/o. Cheyyeru Village, Katrenikona Mandal, East Godavari District. ...PETITIONER AND
1. PRL SECRETARY ENERGY DEPT VELAGAPUDI 2 OTHERS, rep.by its Principal Secretary, Energy Department, Secretariat, Velagapudi, Tullur Mandal, Guntur District. 2. The Assistant Engineer, A.P. Eastern Power Distribution Company Limited, Operation Circle, Katrenikona, East Godavari District. 3. The Tahsildar Katrenikona Mandal East Godavari District, - ...RESPONDENTs Petition under Article 226 of the Constitution of India praying that in the circumstances stated in the affidavit filed therewith, the High Court may be pleased toto issue a Writ, order or direction, more particularly one in the nature of WRIT OF MANDAMUS, declaring the impugned Letter bearing LR.No. AE/O/K.Kona, D.No. 321/2017, dated 22.09.2017 of the 2nd respondent as illegal, arbitrary, unconstitutional, non-application of mind,
2
under the dictation of the 3rd respondent and violative of Art. 14, 21 and 19 of the Constitution of India and consequently set-aside the same, and pass. IA NO: 1 OF 2017(WPMP 42242 OF 2017 Petition under Section 151 CPC praying that in the circumstances stated in the affidavit filed in support of the petition, the High Court may be pleased to direct the 2nd respondent not to disconnect the power supply to the petitioner by suspending the operation of the impugned Letter bearing LR No. AE/O/K.Kona, D.No. 321/2017, dated 22.09.2017, passed by the 2nd respondent, in the interest of justice and in the interest of the petitioner, pending disposal of the main Writ Petition, and pass Counsel for the Petitioner: ELEVATED AS JUDGE Counsel for the Respondents: GP FOR REVENUE (AP) Counsel for the Respondents: V V SATISH (SC for APEPDCL) Counsel for the Respondents: GP FOR ENERGY (AP)
3
THE HONOURABLE SRI JUSTICE VENKATESWARLU NIMMAGADDA WRIT PETITION NO: 33960 OF 2017 The Court made the following order:
None appears for the writ petitioner. Heard learned Standing Counsel for the Respondents. 2. The case of the writ petitioner is that, the respondent has issued impugned letter bearing LR.No.AE/O/K.Konda, D.No.321/2017 for proposing disconnection of service of the petitioner, in view of the letter addressed by the Tahsildar, Katrenikona Mandal dated 18.09.2017. 3.
At the time of admission of hearing, on 11.10.2017, this Hon’ble Court was pleased to grant interim order as under:
“In the meanwhile, the respondents shall not disconnect the power supply so long as the petitioner pays the regular electricity charges as this Court prima facie found that the action is proposed to be taken on the instructions of the Tahsildar, who is a third party to the contract between the petitioner and the electricity Department.”
4. Learned Standing Counsel for the respondents submits that in view of the interim orders of this Court, the service connection of the petitioner has been restored and at present the service connection is still in ‘live’ status, hence nothing survives in this writ petition for further adjudication. 5. Considering the submission of the learned Standing Counsel for the respondents that, pursuant to the interim orders of this Court dated
4
11.10.2017, the service connection of the petitioner has been restored and at present status of service connection is in ‘live’, this Court deems it appropriate to dispose of this Writ Petition with a direction to the respondents that if the respondents are intended to initiate any action or disconnection of the service connection of the petitioner, the respondents shall follow due process as contemplated as per the Electricity Act, 2003 as well as the General Terms and Conditions of Supply. 6. With the above observations and directions, this Writ Petition is disposed of. No order as to costs. 7. Consequently, Miscellaneous Petitions, if any, pending in this Writ Petition shall stand closed. ________________________________ VENKATESWARLU NIMMAGADDA, J Dt: 12.11.2026 Mnr
5
156
THE HONOURABLE SRI JUSTICE VENKATESWARLU NIMMAGADDA
WRIT PETITION No.33960 OF 2017
Dt: 12.11.2026 Mnr