Research › Search › Judgment

High Court of Andhra Pradesh · body

2026 DAILYLAW 42665 (AP)

SRI SAI TEJA ENGINEERS PRIVATE LIMITED v. The State of Andhra Pradesh

WP/27171/2026 · 2026-10-06

K Sreenivasa Reddy

body2026

Judgment text

Extracted from the PDF above. The PDF is authoritative.

APHC010487782026 IN THE HIGH COURT OF ANDHRA PRADESH AT AMARAVATI (Special Original Jurisdiction) [3327] WEDNESDAY, THE 7th DAY OF OCTOBER 2026 PRESENT THE HONOURABLE SRI JUSTICE K. SREENIVASA REDDY WRIT PETITION NO: 27171/2026 Between: 1. SRI SAI TEJA ENGINEERS PRIVATE LIMITED, REP. BY ITS MANAGING DIRECTOR, P. UMA LAKSHMANA KUMAR, S/O. SEETHARAMUDU, AGED 46 YEARS, OCC CONTRACTOR, RIO. D.NO.5-97/1, RAJU VARRI PALEM, KOMARAGIRIPATNAM, ALLAVARAM, EAST GODAVARI DISTRICT- 533210. PETITIONER ...PETITIONER AND 1. THE STATE OF ANDHRA PRADESH, REP BY ITS' PRINCIPAL SECRETARY TO GOVERNMENT IRRIGATION AND CAD WATER RESOURCES DEPARTMENT, SECRETARIAT BUILDINGS, A.P. SECRETARIAT, VELAGAPUDI, AMARAVATHI, GUNTUR DISTRICT- 522237. 2. THE STATE OF ANDHRA PRADESH, REP. BY IT'S PRINCIPAL SECRETARY, FINANCE DEPARTMENT, SECRETARIAT BUILDINGS, VELAGAPUDI, AMARAVATI, GUNTUR DISTRICT-522237. 3. THE DISTRICT COLLECTOR IRRIGATION WING, BHIMAVARAM, WEST GODAVARI DISTRICT-534201. 4. THE ENGINEER INCHIEF, MINOR AND MAJOR IRRIGATION DEPARTMENT, GOVERNMENT OF ANDHRA PRADESH, IRRIGATION BHAVAN, VIJAYAWADA, NTR DISTRICT-520002. 5. THE SUPERINTENDING ENGINEER, IRRIGATION AND WATER RESOURCES DEPARTMENT, IRRIGATION CIRCLE, ELURU, ELURU DISTRICT- 534001. 2 SRK, J WP No.27171 of 2026 6. THE EXECUTIVE ENGINEER, GODAVARI WESTERN DIVISION, NIDADAVOLE, WEST GODAVARI DISTRICT- 534301. ...RESPONDENT(S): Petition under Article 226 of the Constitution of India praying that in the circumstances stated in the affidavit filed therewith, the High Court may be pleased to issue an appropriate Writ, Order or direction more particularly one in the nature of Writ of Mandamus declare the inaction on part of the respondents herein not releasing the final bill total amount worth Rs.7,30,506/-,in respect of irrigation work vide Quality Control Certificate No.2050, dated 10.10.2025, and its Agreement No.89/2024-25, dated 13.09.2024, M. Book No. 3492 GW, with interest of execution of completion of works O and M Desilting to the Digamarru Channel from Km. 0.000 to 3.500 km in the jurisdiction of Irrigation Section, Palakollu in West Godavari District,under Water Resources Department as per agreements to the petitioner till today and causing heavy loss with interest even though total work were completed as per the agreements as illegal arbitrary and violation of Articles 14, 16 and 21 of The Constitution of India and consequently direct the respondent to release the total final bill amount of Rs.7,30,506/-, for the works under Water Resources Department as per agreement to the petitioner forthwith IA NO: 1 OF 2026 Petition under Section 151 CPC praying that in the circumstances stated in the affidavit filed in support of the petition, the High Court may be pleased direct the respondents releasing the Final Bill amount of Rs.7,30,506/- under Water Resources Department as per agreement to the petitioner forthwith, pending disposal of the above writ petition Counsel for the Petitioner: 1. ANNAMNEEDI BALAKRISHNA Counsel for the Respondent(S): 1. GP FOR IRRI AND CAD 2. GP FOR FINANCE PLANNING The Court made the following: 3 SRK, J WP No.27171 of 2026 O R D E R This Writ Petition is filed seeking the following relief: “….to issue an appropriate Writ, Order or direction more particularly one in the nature of Writ of Mandamus declare the inaction on part of the respondents herein not releasing the final bill total amount worth Rs.7,30,506/-,in respect of irrigation work vide Quality Control Certificate No.2050, dated 10.10.2025, and its Agreement No.89/2024-25, dated 13.09.2024, M. Book No. 3492 GW, with interest of execution of completion of works O and M Desilting to the Digamarru Channel from Km. 0.000 to 3.500 km in the jurisdiction of Irrigation Section, Palakollu in West Godavari District, under Water Resources Department as per agreements to the petitioner till today and causing heavy loss with interest even though total work were completed as per the agreements as illegal arbitrary and violation of Articles 14, 16 and 21 of The Constitution of India and consequently direct the respondent to release the total final bill amount of Rs.7,30,506/-, for the works under Water Resources Department as per agreement to the petitioner forthwith and pass such other order…” 2. Heard the learned counsel for the petitioner, the learned Assistant Government Pleader for Irrigation and the learned Assistant Government Pleader for Planning. 3. The petitioner claims to be engaged in the execution of civil works and that it was entrusted with various works like laying of roads, drains and constructions of buildings in the governmental organizations along with Irrigation and other Departments. It is its case that it was awarded a contract for execution of the work viz. O&M Desilting to the Digamarru Channel from Km. 0.000 to 3.500 km in the jurisdiction of Irrigation Section, Palakollu in West Godavari District. It is its case that it executed the work to the 4 SRK, J WP No.27171 of 2026 satisfaction of the authorities concerned, and upon completion of the work, the respondent authorities measured the same and recorded the measurements in the Measurement Book. 4. It is the grievance of the petitioner that notwithstanding the completion of the work and its measurement by the competent authorities, the amount due towards the executed work has not been paid till date. According to the petitioner, although the work was completed long back, the respondent authorities are not releasing the admitted amount payable to it. Aggrieved by the non-payment of the said amount, the petitioner filed the present Writ Petition. 5. Having regard to the fact that in spite of granting number of adjournments, the respondent authorities neither secured written instructions nor filed counter-affidavits, the respondent authorities are directed to verify and pay the admitted amount for the work executed by the petitioner within a period of Eight (8) weeks from the date of receipt of a copy of this order. It is made clear that the petitioner shall execute an indemnity bond to the effect that in case, if it is found that the petitioner has not executed the work, it would repay the amount so paid. 6. Accordingly, the Writ Petition is disposed of. There shall be no order as to costs. As a sequel thereto, the miscellaneous applications, if any, pending in this Writ Petition, shall stand closed. _____________________________ JUSTICE K. SREENIVASA REDDY Date:07.10.2026. MS 5 SRK, J WP No.27171 of 2026 HON’BLE SRI JUSTICE K. SREENIVASA REDDY Writ Petition No:27171 of 2026 Date: 07.10.2026 MS