DODDAPATI LAKSHMI PRASANNA v. ANDHRA PRADESH CENTRAL POWER DISTRIBUTION CORPORATION LTD
WP/26395/2026 · 2026-09-22
Venkateswarlu Nimmagadda
body2026
DailyLaw.ai
[ 2026 DAILYLAW 41715 (AP) · dailylaw.ai ]
DailyLaw.ai
[ 2026 DAILYLAW 41715 (AP) · dailylaw.ai ]
Judgment text
Extracted from the PDF above. The PDF is authoritative.
APHC010479192026
IN THE HIGH COURT OF ANDHRA PRADESH AT AMARAVATI (Special Original Jurisdiction)
WEDNESDAY, THE 23rd DAY OF SEPTEMBER 2026 PRESENT THE HONOURABLE SRI JUSTICE VENKATESWARLU NIMMAGADDA WRIT PETITION NO: 26395 OF 2026 Between:
1. DODDAPATI LAKSHMI PRASANNA, W/o Srinivasa Rao, age 54 years, Housewife, R/o D.No.1-30, Turpu Bazar, Koppolu Rural, Ongle Mandal, Prakasam Dist -523 286
2. Singamuneni Revanth Kumar, S/o Madhava Rao, age 39 years, Private Employee, R/o D.No.1-30, Turpu Bazar, Koppolu Rural, Ongle Mandal, Prakasam Dist -523 286 ...Petitioners AND
1. ANDHRA PRADESH CENTRAL POWER DISTRIBUTION CORPORATION LTD, Rep by Chairman and Managing Director, Vidyut Soudha, Visnu Nagar, Gunadala, Vijayawada. 520002
2. The Executive Engineer, Operations, APCPDCL, Old Power House, Ramnagar, Ongole, Prakasam District. 52300 ...Respondents Petition under Article 226 of the Constitution of India praying that in the circumstances stated in the affidavit filed therewith, the High Court may be pleased toissue a writ order or direction more particularly one in the nature of
Writ of Mandamus declaring the action of the 2nd Respondent in not erection/installation of the transformer despite Estimate sanctionNo.EE/O/ONGUJE.COML/CAP.N0189-2026-27 dt.11- 08-2026 on receiving the requisite charges an amount of Rs.7,29,784/- to the petitioner land for the purpose of forming aquaculture is illegal, arbitrary, capricious, and contrary to the section 43 of the Electricity Act, 2003 and also violative of Articles 14, 21 and 300A of Constitution of India. Consequently, direct the 2nd Respondent to erect the transformer in the Petitioner's land as per the sanction
order by forthwith IA NO: 1 OF 2026 Petition under Section 151 CPC praying that in the circumstances stated in the affidavit filed in support of the petition, the High Court may be pleased pleased to direct the 2nd Respondent erect/installation of the transformer in the Petitioner's land as per the Estimate sanction No.EE/O/ONGL/JE.COML/CAP.N0189-2026-27 dt.11-08-2026 by forthwith pending disposal of the above writ petition and to pass s Counsel for the Petitioners: N A RAMACHANDRA MURTHY Counsel for the Respondents: Counsel for the Respondents:V V SATISH The Court made the following order:
THE HON’BLE SRI JUSTICE VENKATESWARLU NIMMAGADDA WRIT PETITION NO: 26395 OF 2026
ORDER:
The present Writ Petition is filed under Article 226 of the Constitution of India seeking following relief:
“to issue a writ order or direction more particularly one in the nature of writ of Mandamus declaring the action of the 2nd Respondent in not erection/installation of the transformer despite Estimate Sanction No.EE/O/ONGL/JE.COML/CAP.NO189-2026 on receiving the requisite charges an amount of Rs.7,29,784/- to the petitioner land for the purpose for forming aquaculture is illegal, arbitrary, capricious, and contrary to section 43 of the Electricity Act, 2003 and also violative of Articles 14, 21 and 300A of Constitution of India.”
2. Heard the learned counsel for the petitioner and the learned standing counsel for the respondents.
3.
Learned Counsel for the petitioner submits that the petitioner herein is the absolute owner and possessor of the subject land admeasuring to an extent of Ac.1.51 cents situated in Sy.No.206/2 and to an extent of Ac.0.16 cents in Sy.No.205/2A situated at Koppolu Village, Ongole Mandal, having acquired the same through registered sale deed in the year 2022, since the date of acquisition, the petitioner has been cultivating the land by doing agricultural operations. Later, the petitioner intended to do aqua-culture farming and for the same, the petitioner submitted an application seeking for the required permission from the Competent Authority i.e. Aqua Culture Authority on 04.11.2025. After
obtaining necessary permissions from the said authority, the petitioner made an application for granting electricity service connection to the subject land. By considering the application submitted by the petitioner, the respondents proceeded further and issued a demand notice dated 11.08.2026, demanding an amount of Rs.7,29,784/- for the purpose of farming and for granting new electricity service connection with additional load. On receipt of the said demand notice, the petitioner paid the entire amount and the same was acknowledged by the respondents. Even after acknowledgement of the receipt of the amount and after receipt of No Objection Certificate on 03.10.2025, but for one reason or the other, the respondents are not granting electricity service connection so far. Hence the Writ Petition. 4. On the other hand, learned Standing Counsel for the respondents furnished written instructions on 22.09.2026, wherein it is stated as under:
“With reference cited above, the petitioner (2) Sri Singamaneni Revanth Kumar, S/o. Madhava Rao was applied for Aqua Service at Koppolu Village in Sy.No.205/2A, 206/2 Ongole Mandal. After submission of all necessary documents duly following the departmental procedures the estimate was sanctioned vide Sanction Number: 188/2026-27, dt: 11.08.226. This work will be taken up and complete as soon as possible”
6. Learned Standing Counsel further submits that the respondents are taking steps for granting electricity service connection to the petitioner
aqua farm, for which the respondents have to erect a transformer. Therefore, they are in the process of erection of the transformer. After the erection of the same, the petitioner would be granted electricity service connection. 7.
Heard learned Counsel for the petitioner and the learned Standing Counsel for the respondents and after perusing the material available on record, this Court is of the considered opinion that the present Writ Petition can be disposed of, directing the respondent Nos.1 and 2 herein to grant electricity service connection to the petitioner’s form, after completion of the erection of transformer, with immediate effect within a reasonable time. 8. Accordingly, the Writ Petition is disposed of, directing the respondents to complete the entire erection of transformer and to grant new electricity service connection to the petitioner’s Farm within a period of two (2) months from the date of copy of this order. There shall be no order as to costs. As a sequel, miscellaneous petitions, if any, pending shall stand closed. _________________________________
VENKATESWARLU NIMMAGADDA, J
23.09.2026 PVS/BAK
HON’BLE SRI JUSTICE VENKATESWARLU NIMMAGADDA
WRIT PETITION NO: 26395 OF 2026
23.09.2026 PVS/BAK