IN THE HIGH COURT OF ANDHRA PRADESH AT AMARAVATI (Special Original Jurisdiction) [3457] FRIDAY, THE 24th DAY OF SEPTEMBER 2026 PRESENT THE HONOURABLE SRI JUSTICE HARINATH.N WRIT PETITION NO: 26381/2026 Between:
1. P. PAVAN KUMAR, S/O. P. PARASURAMUDU, AGED ABOUT 40 YEARS, OCC CONTRACTOR, R/O. D.NO. 3/17/47/12A, LAKSHMI NAGAR, GUDARIGUNTA, KAKINADA, EAST GODAVARI DISTRICT. ...PETITIONER AND
1. THE STATE OF ANDHRA PRADESH, REP., BY ITS PRINCIPAL SECRETARY, TRIBAL WELFARE DEPARTMENT, SECRETARIAT BUILDINGS, VELAGAPUDI, GUNTUR DISTRICT. (522238)
2. THE SUPERINTENDENT ENGINEER, TRIBAL WELFARE DEPARTMENT, VISHAKHAPATNAM. (530017)
3. THE EXECUTIVE ENGINEER, TRIBAL WELFARE DEPARTMENT, RAMPACHODAVARAM, EAST GODAVARI DISTRICT. (533288)
4. THE ASSISTANT EXECUTIVE ENGINEER, TRIBAL WELFARE DEPARTMENT, MAREDUMILLI, EAST GODAVARI DISTRICT. (533295)
5. THE STATE OF ANDHRA PRADESH, REP., BY ITS PRINCIPAL SECRETARY, DEPARTMENT OF FINANCE AND PLANNING, SECRETARIAT BUILDINGS, VELAGAPUDI, AMARAVATHI, GUNTUR DISTRICT. (522 238)
...RESPONDENT(S): Petition under Article 226 of the Constitution of India praying that in the circumstances stated in the affidavit filed therewith, the High Court may be pleased toissue a WRIT OF MANDAMUS declaring the action of the
2
Respondents in not refunding the deposit amounts i.e., EMD Rs.1,41,333/-, H.W 7.5 percent of Rs. 88,754/-, and pending due of Rs.49,761/- , totally to an amount of Rs. 2,79,848/- in respect of work i.e., 'Construction of Additional Class Rooms to Government Jr. College at Maredumilli (Vand M) of East Godavari District' vide circle Agreement No. /2018-19/DB/, dt.16.10.2018', is questioned, as the same is illegal, arbitrary and contrary to the order passed in WP.No.19922/2023 on Dt 24.08.2023 and consequently direct the respondents to refund the deposit an amount of deposit amounts i.e., EMD Rs.1,41,333/-, H.W 7.5 percent of Rs. 88,754/-, and pending due of Rs.49,761/-, totally to an amount of Rs. 2,79,848/ - with interest @ 12 percent per annum for the delayed amount to the petitioner in respect of execution of above-mentioned work forthwith IA NO: 1 OF 2026 Petition under Section 151 CPC praying that in the circumstances stated in the affidavit filed in support of the petition, the High Court may be pleased DIRECT the respondents to refund the deposit amounts i.e., EMD Rs.1,41,333/-, H.W 7.5% of Rs. 88,754/-, and pending due of Rs.49,761/- , totally to an amount of Rs. 2,79,848/- with an interest of 12% per annum for the delayed payment in respect of work i.e., "Construction of Additional Class Rooms to Government Jr.
College at Maredumilli Wand M) of East Godavari District" vide circle agreement No. /2018-19/DB/, dt.16.10.2018., Pending disposal of the Writ Petition Counsel for the Petitioner:
1. SURESH KUMAR REDDY KALAVA Counsel for the Respondent(S):
1. GP FOR SOCIAL WELFARE
2. GP FOR FINANCE PLANNING
3
The Court made the following Order:
The learned counsel for the petitioner submits that the petitioner is aggrieved by the action of the respondents in not refunding the deposit amounts i.e., EMD Rs.1,41,333/-, H.W 7.5 percent of Rs. 88,754/-, and pending due of Rs.49,761/- , totally to an amount of Rs. 2,79,848/- in respect of work i.e., 'Construction of Additional Class Rooms to Government Jr. College at Maredumilli (Vand M) of East Godavari District' vide circle Agreement No. /2018-19/DB/, dated 16.10.2018. 2. It is submitted that the petitioner had completed the works entrusted to him and that the competent authority of the respondents had also approved the payments due and payable to the petitioner. The respondents have also released the payments due payable for the executed works. 3. Heard the submissions of the learned counsel for the petitioner, the learned Government Pleader for the Respondents. 4. During the course of hearing, the learned Government Pleader appearing for the respondents submits that the works have been completed and that the final bills are also paid. No reasons are assigned for withholding the EMD amounts after completion of the defect liability period. 5. Thus the Writ Petition is disposed of at the admission stage, directing the respondents to verify and release the EMD, H.W and pending dues payable to the petitioner as expeditiously as possible, preferably within a period of four
4
(04) weeks from the date of receipt of a copy of this order. There shall be no order as to costs. 6. Pending miscellaneous petitions, if any, shall stand closed. ___________________ JUSTICE HARINATH.N Date:24.09.2026 RSD
5
113 THE HONOURABLE SRI JUSTICE HARINATH.N
WRIT PETITION NO: 26381 of 2026
Date:24.09.2026 RSD