N SRINIVASULU REDDY v. THE STATE OF ANDHRA PRADESH
WP/9752/2026 · 2026-09-01
K Sreenivasa Reddy
body2026
DailyLaw.ai
[ 2026 DAILYLAW 40308 (AP) · dailylaw.ai ]
DailyLaw.ai
[ 2026 DAILYLAW 40308 (AP) · dailylaw.ai ]
Judgment text
Extracted from the PDF above. The PDF is authoritative.
1
APHC010178372026
IN THE HIGH COURT OF ANDHRA PRADESH AT AMARAVATI (Special Original Jurisdiction)
WEDNESDAY, THE 2nd DAY OF SEPTEMBER 2026 PRESENT THE HONOURABLE SRI JUSTICE K SREENIVASA REDDY WRIT PETITION NO: 9752 OF 2026 Between:
1. N SRINIVASULU REDDY, S/o. Venkata Rami Reddy Civil and Electrical Class-1 Contractor, Kothur (Village and Post), Pendlimarri Mandal, YSR Kadapa District. ...Petitioner AND
1. THE STATE OF ANDHRA PRADESH, Represented through its Principal Secretary, Department of Irrigation and CAD (Water Resources), Secretariat, Velagapudi, Amaravati. 522238
2. The Principal Secretary, Department of Finance, Secretariat, Velagapudi, Amaravati. 522238
3. The Engineer in Chief Irrigation, Water Resources Department, Vijayawada.520001
4. The Superintending Engineer, Minor Irrigation, Koti Reddy Circle, YSR Kadapa, YSR Kadapa District. 516001
2
5. The Executive Engineer, Water Resources Department, Irrigation Division, YSR Kadapa, YSR Kadapa District. 516001
6. The Deputy Executive Engineer, Water Resources Department, Irrigation sub-Division, YSR Kadapa, YSR Kadapa District. 516001 ...Respondents Petition under Article 226 of the Constitution of India praying that in the circumstances stated in the affidavit filed therewith, the High Court may be pleased topleased to issue an appropriate Writ,
Order or direction more particularly one in the nature of Writ of Mandamus declaring the inaction on the part of the Respondents in respect of release of an amount of Rs.29,56,104/- (Rupees Twenty Nine Lakhs Fifty Six Thousands One Hundred and Four only) Rs.17,00,006 plus Rs.12,56,098 to the petitioner in respect of execution of work by the petitioner i.e., shifting of 33 KV, LT and Distribution Transformers with connected lines which obstructing formation of proposed road along Buggavanka near Kagithalapenta bridge under Turnkey basis in Operation Section, Balaji Nagar, Kadapa, pursuant to Agreement No.4 DN/2023-24 dated 27.05.2023, vide M.Books No.192 NC (Token Nos.2024-1196879 and 2024-1881243) during the year 2023-2024, is illegal, irregular, irrational, violation of Government Orders besides violation of Principles of Natural Justice and consequently direct the respondents to pay the above said due amounts to the petitioner immediately in respect of the above said work executed by the petitioner, in the interest of justice and to pass IA NO: 1 OF 2026
3
Petition under Section 151 CPC praying that in the circumstances stated in the affidavit filed in support of the petition, the High Court may be pleased pleased to direct the respondents to release the necessary funds for payment of an amount of Rs.29,56,104/- (Rupees Twenty Nine Lakhs Fifty Six Thousands One Hundred and Four only) {Rs.17,00,006 + Rs.12,56,098} to the petitioner in respect of execution of work by the petitioner i.e., shifting of 33 KV, LT & Distribution Transformers with connected lines which obstructing formation of proposed road along Buggavanka near Kagithalapenta bridge under Turnkey basis in Operation Section, Balaji Nagar, Kadapa, pursuant to Agreement No.4DN/2023-24 dated 27.05.2023, vide M.Books No.192 (Token Nos.2024-1196879 and 2024- 1881243) during the year 2023-2024, in the interest of justice, during the pendency of the writ petition and to pass Counsel for the Petitioner: K JYOTHI PRASAD Counsel for the Respondents: GP FOR IRRI AND CAD Counsel for the Respondents:GP FOR FINANCE PLANNING The Court made the following order:
4
THE HONOURABLE SRI JUSTICE K.SREENIVASA REDDY
WRIT PETITION NO.9752 OF 2026
ORDER:
This Writ Petition is filed under Article 226 of the Constitution of India seeking the following relief:
“….to issue an appropriate Writ, Order or direction more particularly one in the nature of Writ of Mandamus declaring the inaction on the part of the Respondents in respect of release of an amount of Rs.29,56,104/- (Rupees Twenty Nine Lakhs Fifty Six Thousands One Hundred and Four only) Rs.17,00,006 + Rs.12,56,098 to the petitioner in respect of execution of work by the petitioner i.e., shifting of 33 KV, LT and Distribution Transformers with connected lines which obstructing formation of proposed road along Buggavanka near Kagithalapenta bridge under Turnkey basis in Operation Section, Balaji Nagar, Kadapa, pursuant to Agreement No.4 DN/2023-24 dated 27.05.2023, vide M.Books No.192 NC (Token Nos.2024-1196879 and 2024-1881243) during the year 2023-2024, is illegal, irregular, irrational, violation of Government Orders besides violation of Principles of Natural Justice and consequently direct the
5
respondents to pay the above said due amounts to the petitioner immediately in respect of the above said work executed by the petitioner, in the interest of justice and to pass ……..….”
2. Heard learned counsel for the petitioner and learned Assistant Government Pleader for Irrigation appearing for the respondents. 3. Case of the petitioner is that he was entrusted with the aforesaid work and duly executed the same to the satisfaction of the authorities concerned. Upon completion of the work, the respondent authorities measured the work and recorded the measurements in the relevant Measurement Books. Despite completion of the work long ago, the respondent authorities have failed to release the admitted amount payable to the petitioner. Aggrieved by the non-payment of the said amount, the petitioner has filed the present Writ Petition. 4. Learned Assistant Government Pleader for Irrigation, on written instructions dated 31.08.2026, from the Executive Engineer(FAC), Irrigation Division, Kadapa, submitted that there is no dispute with regard to the execution of the subject work by the petitioner. He further submitted that a letter has
6
already been addressed to the higher authorities requesting allocation of budget for settlement of the above bill. The bill will be processed for payment after receipt of budget and necessary approvals from the Government. The written instructions are placed on record. 5. Since the amount payable is admitted and undisputed, the writ petition is maintainable.
In M/s Utkal Highways Engineer and Contractors V. Chief General Manager & Ors1, it was held at paragraph No.8, as under:
“Be that as it may, the High court has not dealt with the merits of the writ petition. Moreover, it is not an inviolable rule that no money claim can be adjudicated upon in exercise of writ jurisdiction. Non-payment of admitted dues, inter alia, may be considered an arbitrary action on the part of respondents and for claiming the same, a writ petition may lie. Further, throwing a writ petition on ground of availability of alternative remedy after 10 years, particularly, when parties have exchanged their affidavits, is not the correct course unless there are disputed questions of fact which by their very nature cannot be adjudicated upon without recording formal evidence”. 6. Having regard to the fact that there is no dispute with regard to the work executed by the petitioner and the amount payable to him, and in view of the submissions of the learned
1 2025 SCC online SC 1400
7
Assistant Government Pleader for Irrigation, the respondent authorities are directed to pay the admitted amount to the petitioner within a period of three(3) months from the date of receipt of a copy of this order. 7. Accordingly, the Writ Petition is disposed of. There shall be no order as to costs. As a sequel, interlocutory applications pending if any, shall stand closed. _______________________ K.SREENIVASA REDDY, J
Date: 02.09.2026. PAB