1
APHC010299252026
IN THE HIGH COURT OF ANDHRA PRADESH AT AMARAVATI (Special Original Jurisdiction)
THURSDAY, THE 20th DAY OF AUGUST 2026 PRESENT THE HONOURABLE SRI JUSTICE K SREENIVASA REDDY WRIT PETITION NO: 15971 OF 2026 Between:
1. M/s Bhargav Constructions,, Rep. by its Managing Director, Sri Bommisetty Madhusudhan Rao, S/o. Babu Rao, Aged about 48 years, R/o. D. No. 4-57 C, Kothapet Bazar, Chimakurthy Mandal, Prakasam district. ...Petitioner AND
1. THE STATE OF ANDHRA PRADESH, Rep. by its Principal Secretary, Panchyat Raj Department, Secretariat, Velagapudi Guntur District-522238. 2. The State of Andhra Pradesh, Rep. by its Principal Secretary to Government, Department of Finance and Planning, Secretariat, Velagapudi, Guntur District-522238. 3. The Superintending Engineer, Panchayat Raj Circle, Ongole, Prakasam District-523001. 2
4. The Executive Engineer, PR.PIU Division, Ongole, Prakasam District-523001. 5. The Chief Engineer, Panchayat Raj Department Vijayawada, Krishana (NTR) District. 6. The State of Andhra Pradesh, rep, by its Principal Secretary,Agriculture and Marketing MKTGII Department,Secretariat, Velagapudi, Amaravathi, Guntur district-
522238. 7. The Commissioner and Director of Agricultural Marketing, Vijayawada, NTR District-520012. ...Respondents Petition under Article 226 of the Constitution of India praying that in the circumstances stated in the affidavit filed therewith, the High Court may be pleased to issue an appropriate writ, order or direction, more particularly one in the nature of Writ of Mandamus declaring the action of the respondent authorities in not releasing an amount of Rs. 2,62,24,532/- to the petitioner for the execution of works. Vide Agreement No. 5/2022-23, dated 12-09-2022, respectively as arbitrary, illegal, contrary to Law and against the Principles of Natural Justice and against the Norms of the Public Policy and to issue consequential direction directing the respondent authorities to release the amounts payable to the petitioner with an interest at 18percent per annum and to pass such IA NO: 1 OF 2026
3
Petition under Section 151 CPC praying that in the circumstances stated in the affidavit filed in support of the petition, the High Court may be pleased may be pleased to direct the respondent authorities to release an amount of Rs. 2,62,24,532/- to the petitioner for the execution of work.
Vide Agreement No. 5/2022-23, dated 12-09-2022, respectively, pending disposal of the above writ petition and to pass such Counsel for the Petitioner: VENKAT SAILENDRA G Counsel for the Respondents: GP FOR PANCHAYAT RAJ RURAL DEV Counsel for the Respondents:GP FOR FINANCE PLANNING The Court made the following order:
4
THE HONOURABLE SRI JUSTICE K.SREENIVASA REDDY WRIT PETITION NO.15971 of 2026 ORDER:
This Writ Petition is filed under Article 226 of the Constitution of India seeking the following relief:
“….to issue an appropriate writ, order or direction, more particularly one in the nature of Writ of Mandamus declaring the action of the respondent authorities in not releasing an amount of Rs. 2,62,24,532/- to the petitioner for the execution of works. Vide Agreement No. 5/2022-23, dated 12- 09-2022, respectively as arbitrary, illegal, contrary to Law and against the Principles of Natural Justice and against the Norms of the Public Policy and to issue consequential direction
directing the respondent authorities to release the amounts payable to the petitioner with an interest at 18percent per annum and to pass such……..….”
2. Heard the learned counsel for the petitioner and the learned Assistant Government Pleader for Panchayat Raj and Rural Development appearing for the respondents. 5
3. Case of the petitioner is that it was entrusted with the aforesaid works and duly executed the same to the satisfaction of the authorities concerned. Upon completion of the works, the respondent authorities measured the works and recorded the measurements in the relevant Measurement Books. Despite completion of the works long ago, the respondent authorities have failed to release the admitted amounts payable to the petitioner. Aggrieved by the non-payment of the said amounts, the petitioner has filed the present Writ Petition. 4. The counter-affidavit has been filed by 4th respondent stating that the Deputy Executive Engineer, PIU(PR) Sub- Division, Ongole, submitted LS 1st & final for the above works duly recording in M.book for an amount of Rs.2,18,22,167.81 on 03.06.2026. Further the bill is to be processed in accordance to standards and specification mentioned in the agreement. Further, the Agriculture and Cooperation Department who accorded administrative sanction has to provide Head of Account for which the Expenditure is to be booked against this works. A letter was also addressed by 4th respondent on 18.06.2026 and 01.07.2026 for providing of
6
Head of Account.
After receipt of Head of Account and after scrutiny of work bill payment will be processed to contractor. Since contractor liability is not yet completed on this work, payment will be arranged in due course. 5. Since the amount payable is admitted and undisputed, Writ Petition is maintainable. In M/s Utkal Highways Engineer and Contractors V. Chief General Manager & Ors1, it was held at paragraph No.8, as under:
“Be that as it may, the High court has not dealt with the merits of the writ petition. Moreover, it is not an inviolable rule that no money claim can be adjudicated upon in exercise of writ jurisdiction. Non-payment of admitted dues, inter alia, may be considered an arbitrary action on the part of respondents and for claiming the same, a writ petition may lie. Further, throwing a writ petition on ground of availability of alternative remedy after 10 years, particularly, when parties have exchanged their affidavits, is not the correct course unless there are disputed questions of fact which by their very nature cannot be adjudicated upon without recording formal evidence”. 6. Having regard to the fact that there is no dispute with regard to the works executed by the petitioner and the amount payable to it, and in view of the submissions of the learned Assistant Government Pleader for Panchayat Raj and Rural
1 2025 SCC online SC 1400
7
Development, the respondent authorities are directed to pay the admitted amount to the petitioner within a period of four(4) months from the date of receipt of a copy of this order. 7. Accordingly, the Writ Petition is disposed of. There shall be no order as to costs. As a sequel, interlocutory applications pending if any, shall stand closed. _______________________ K.SREENIVASA REDDY, J
Date: 20.08.2026. PAB
8
THE HONOURABLE SRI JUSTICE K.SREENIVASA REDDY
WRIT PETITION NO. DATE: .2026