2026 DAILYLAW 39503 (AP)

G.V. SUBBA RAO, SPSR NELLORE DISTRICT & 3 OTHERS v. SECRETARY, INDUSTRIES & COMMERCE DEPT., HYD & 6 OTHERS

WP/10409/2014 · 2026-08-24

Venkateswarlu Nimmagadda

body2026

Judgment text

Extracted from the PDF above. The PDF is authoritative.

APHC010132662014 IN THE HIGH COURT OF ANDHRA PRADESH AT AMARAVATI (Special Original Jurisdiction) TUESDAY, THE 25th DAY OF AUGUST 2026 PRESENT THE HONOURABLE SRI JUSTICE VENKATESWARLU NIMMAGADDA WRIT PETITION NO: 10409 OF 2014 Between: 1. G.V. SUBBA RAO, SPSR NELLORE DISTRICT & 3 OTHERS, S/o. Kotaiah, aged about 71 years, Occ.: Contractor, R/o. 8-777, Vikram Sara Bhai Marg, Sullurupet, SPSR Nellore District. 2. G. Krishna Reddy,, S/o. Venkat Reddy, aged about 50 years, Occ.: Contractor, R/o. Kollamitta, Sullurupet, SPSR Nellore District. 3. M.V. Subba Reddy,, S/o. Sanjeeva Reddy, aged about 78 years, Occ.: Contractor, R/o. Bapuji Colony,Sullurupet, SPSR Nellore District. 4. A. Kishore Kumar Reddy,, S/o. Venugopal Reddy, aged about 51 years, Occ.: Contractor, R/o. Kotapolur Village, Sullurupet Mandal, SPSR Nellore District. ...Petitioners AND 1. SECRETARY INDUSTRIES COMMERCE DEPT HYD 6 OTHERS, rep. by its Secretary, Industries & Commerce Department, Secretariat, Hyderabad. 2. The Director of Mines Geology, B.R.K.R. Bhavan, 8th Floor, Tank Bund Road, Andhra Pradesh, Hyderabad. 3. The Deputy Director of Mines Geology, 1/1, Ramannapet, Guntur, Guntur District. 2 4. The Asst Director of Mines Geology Vig Nellore, SPSR Nellore District. 5. The Government of India, Department of Space Civil Engineering Division, Sriharikota Range, Nellore District, rep. by its Chief Construction Engineer. 6. The District Collector SPSR Nellore District at Nellore, - 7. Revenue Divisional Officer, Naidupet, SPSR Nellore District. ...Respondents Petition under Article 226 of the Constitution of India praying that in the circumstances stated in the affidavit filed therewith, the High Court may be pleased to issue an appropriate Writ, Order or direction preferably one in the nature of Writ of Mandamus declaring the action of the 3rd respondent dated 04-03-2014 in addressing letters to the 6th respondent for authorizing 7th respondent to proceed against the petitioners for recovery of alleged amounts towards normal seignorage fee together with 5 times penalty in respect of the works of the 5th respondent carried out by the petitioners during the years 2000 to 2004 under demand notices of the 4th respondent dated 10-11-2004 as arbitrary, illegal and contrary to law and consequently direct the respondents not to proceed further pursuant to the said letters of the 3rd respondent dated 04-03-2014 in the interest of justice and pass. IA NO: 1 OF 2014 (WPMP 13071 OF 2014 Petition under Section 151 CPC praying that in the circumstances stated in the affidavit filed in support of the petition, the High Court may be pleased to stay all further proceedings pursuant to the letter of the 3rd respondent dated 04-03-2014 in addressing letters to the 6th respondent proposing to proceed against the petitioners under Section 3 (1) of Revenue Recovery Act, 1890 pending disposal of the main Writ Petition. Counsel for the Petitioners: GP FOR MINES AND GEOLOGY,GP FOR MINES AND GEOLOGY ,T BALAJI 3 Counsel for the Respondents: GP FOR REVENUE Counsel for the Respondents:BETHAPALLI SURYANARAYANA (CENTRAL GOVT COUNSEL) Counsel for the Respondents:HARINATH N (DEPUTY SOLICITOR GENERAL OF INDIA) Counsel for the Respondents:GP FOR MINES AND GEOLOGY The Court made the following order: 4 THE HONOURABLE SRI JUSTICE VENKATESWARLU NIMMAGADDA WRIT PETITION NO: 10409 OF 2014 ORDER: The present writ petition is filed under Article 226 of the Constitution of India seeking following relief: “to issue an appropriate Writ, Order or direction preferably one in the nature of Writ of Mandamus declaring the action of the 3rd respondent dated 04.03.2014 in addressing letters to the 6th respondent for authorizing 7th respondent to proceed against the petitioners for recovery of alleged amounts towards normal seignorage fee together with 5 times penalty in respect of the works of the 5th respondent carried out by the petitioners during the years 2000 to 2004 under demand notices of the 4th respondent dated 10.11.2004 as arbitrary, illegal and contrary to law and consequently direct the respondents not to proceed further pursuant to the said letters of the 3rd respondent dated 04.03.2014 in the interest of justice and pass such other order or orders….” 2. Heard learned counsel for the petitioners and learned Government Pleader for the respondents. 3. The case of the petitioners is that the petitioners herein are the registered contractors for Civil works with the Government of Andhra Pradesh. While so, after award of contract in all respects, the petitioners executed works as per the terms as directed by the 5th respondent herein. In execution of the subject contracts, the petitioners were provided material like metal, stone, gravel etc., after having paid the seigniorage fee as required. But to the 5 surprise of the petitioners, the respondents herein issued a demand notice dated 10.11.2004 alleging that the petitioners avoided the seigniorage fee and extracted the metal, gravel and supplied to the respondent No.5 pursuant to the contract without paying seigniorage fee. After issuing demand notice dated 10.11.2004, the respondent No.4 issued a letter dated 10.01.2014 to respondent No.3, wherein, the petitioners are directed to pay the alleged amount of due towards seignorage fee together with 5 times penalty in order to avoid coercive proceedings under the Revenue Recovery Act, 1890. Later, on 04.03.2014, the respondent No.3 also issued orders of attachment of the property under the Revenue Recovery Act, 1890. The said action of the respondent No.3 pursuant to the letter dated 04.03.2014 is assailed before this Court. 4. Learned counsel for the petitioners submits that at the time of hearing the matter, this Court passed an interim order dated 04.04.2014, which reads as follows: “Subject to the writ petitioners depositing 1/4th of the amount demanded, stay of all further proceedings, pursuant to the impugned notices issued under the Revenue Recovery Act, 1890 against each of the petitioners.” 5. Pursuant to the interim order dated 04.04.2014, the petitioners herein paid 1/4th of the demanded amount as directed. Whereas, pending the Writ Petition, the respondent No.1 issued G.O.Rt.No.131 Industries & Commerce (Mines-II) Department dated 07.08.2025. Under the said G.O., the petitioners 6 are entitled to avail the benefit of the One Time Settlement (OTS) scheme, subject to the terms and conditions stipulated therein. He further submits that under Clause E(c) of the said G.O., although the respondents had imposed a penalty and fee equivalent to five times of normal seigniorage fee under the One Time Settlement scheme, the petitioners are liable to pay the seigniorage fee and other permissible amounts, namely, the consideration amount, DMF, MERIT and one-time penalty, in accordance with the terms of the said G.O. He further submits that the petitioners are ready to pay the subject amount as per the terms of the G.O.Rt.No.131, dated 07.08.2025 after having deductions in respect of the amount already paid at the time of admission of the present writ petition pursuant to the interim orders dated 04.04.2014. 6. On the other hand, learned Government Pleader for the respondents, furnished written instructions issued by the respondent No.4, wherein, it is stated that petitioners have not deposited any amount pursuant to the interim orders as directed. Therefore, the petitioners are not entitled for any relief as prayed in the writ petition since the petitioners have not complied with the interim orders of this Court. 7. Considering the submissions made by the learned counsel for both the parties and on perusal of the material placed on record, it is observed that this Court passed an interim order dated 04.04.2014 directing the petitioners to deposit 1/4th the demanded amount and subject to payment of 1/4th amount all further proceedings pursuant to the impugned proceeding remain stayed. In compliance of the interim orders of this Court, the respondents not initiated 7 any further steps against the petitioners. As contended by the learned counsel for the petitioners regarding payment of 1/4th the demanded amount as directed was already deposited but the same was deferred by the learned Government Pleader through the written instructions submitted by the respondents that the amounts as directed were not paid by the petitioners. It is settled law that once the petitioners failed to comply with the interim orders, having invited the same, the petitioner are not entitled for any further relief in view of the violation of the orders of this Court. As per the instructions, the respondents not furnished full particulars except stating the amounts as demanded were not paid/cleared. However, in view of the G.O.Rt.No.131 dated 07.08.2025, the petitioners are entitled for consideration to pay and to clear the admitted amount as per the terms of G.O.Rt.No.131, dated 07.08.2025. 8. Therefore, the respondents herein are directed to consider the case of the petitioner as per the terms of G.O.Rt.No.131, dated 07.08.2025, subject to eligibility as per the terms of the G.O.Rt.No.131, dated 07.08.2025, within a period of two (02) months from the date of receipt of a copy of this order. However, it is further observed that if the petitioners did not pay any amount in compliance of the interim orders as directed, the petitioners are not entitled for any relief including consideration as directed above and the respondents are at liberty to proceed further in accordance with law. 9. With the above directions, the Writ Petition is disposed of. There shall be no order as to costs. 8 Consequently, Miscellaneous Petitions, if any, pending in the writ petition shall stand closed. ________________________________ VENKATESWARLU NIMMAGADDA, J 25.08.2026 BSP 9 135 THE HON’BLE SRI JUSTICE VENKATESWARLU NIMMAGADDA WRIT PETITION NO: 10409 OF 2014 25.08.2026 BSP