M/s K. Ramalingaraju Infra Project v. The State of Andhra Pradesh
WP/27286/2025 · 2026-08-17
B S Bhanumathi
body2026
DailyLaw.ai
[ 2026 DAILYLAW 38586 (AP) · dailylaw.ai ]
DailyLaw.ai
[ 2026 DAILYLAW 38586 (AP) · dailylaw.ai ]
Judgment text
Extracted from the PDF above. The PDF is authoritative.
APHC010516542025
IN THE HIGH COURT OF ANDHRA PRADESH
Tuesday, the 18 The Honourable Ms. Justice B. S. Bhanumathi Writ Between:
1. M/s. K. Ramalingaraju Infra K. Ramalingaraju S/o near R.T.O. office, Puram, Vizianagaram. 2. Bollam Seshagiri Rao, S/o Occupation : Civil Contractor, Classic Avenue, near Syndicate
1. The State of Andhra Pradesh, Secretary, Irrigation Department, Secretariat Buildings Velagapudi, Amaravathi, Guntur
2. The State of Andhra Pradesh, Secretary, Finance and Planning Department, Secretariat Buildings, Velagapudi, Amaravathi
3. The Engineer-in Guntur district. IN THE HIGH COURT OF ANDHRA PRADESH AT AMARAVATI [3311] (Special Original Jurisdiction) Tuesday, the 18th day of August, 2026 Present The Honourable Ms. Justice B. S. Bhanumathi Writ Petition No.27286 of 2025 malingaraju Infra Project represented by Ramalingaraju S/o. K. Jagannadharaju, Managing Partner, 1 office, opposite to Sitam Engineering College, K Puram, Vizianagaram. 2. Bollam Seshagiri Rao, S/o. Abaddam, Aged 46 years Civil Contractor, R/o. Flat No. 202, Prides Virgo ear Syndicate Bank. Ring Road, Vizianagaram. ... Petitioners and
1. The State of Andhra Pradesh, represented by its Pr Secretary, Irrigation Department, Secretariat Buildings Velagapudi, Amaravathi, Guntur district. 2. The State of Andhra Pradesh, represented by its Princip Secretary, Finance and Planning Department, Secretariat Buildings, Velagapudi, Amaravathi, Guntur district. in-Chief, Irrigation Department, Amaravathi, IN THE HIGH COURT OF ANDHRA PRADESH [3311]
represented by artner, 1-0, Sitam Engineering College, K. L. Abaddam, Aged 46 years, 202, Prides Virgo ank. Ring Road, Vizianagaram. Petitioners by its Principal Secretary, Irrigation Department, Secretariat Buildings by its Principal Secretary, Finance and Planning Department, Secretariat Chief, Irrigation Department, Amaravathi,
2 W.P.No.27286 of 2025
4. The District Collector, West Godavari district at Bhimavaram. 5. The Superintendent Engineer, Irrigation Department, Eluru. 6. The Executive Engineer, Godavari Western Division, Nidadavolu West Godavari District. ... Respondents
Counsel for the Petitioner:
1. K. L. N. Swamy Counsel for the Respondent(S):
1. Government Pleader for Irrigation and C. A. D.
2. Government Pleader for Finance Planning
3 W.P.No.27286 of 2025
The Court made the following Order:
This writ petition is filed to issue a Writ, Order or direction, more particularly one in the nature of Writ of Mandamus, to declare the action of the respondents in not paying the bills for execution of four works by the petitioner under 1. Agreement No.17/2024-25, dt.09-07-2024; 2. Agreement No.15/2024-25, dt.09-07-2024; 3.Agreement No.16/2024-25, dt.09-07-2024; 4.
Agreement No.14/2024-25, dt.09-07-2024; for an amount of Rs.41,56,253/- to the petitioner with interest @ 6% p.a., till today from the date of completion of respective works, as illegal, arbitrary violative of the principles of natural justice and Articles 14, 19 (1) (g) and 21 of the Constitution of India and consequently direct the respondents to immediately release the bills for the above completed works immediately with 6% interest and to pass such other order or orders, which this Court deems proper in the interest of justice. 02. It is the contention of the petitioners that even though the respondents admitted that the petitioners are entitled to the aforesaid amount, no payment has been made. The petitioners contended that such non-payment of money is clearly arbitrary and high-handed requiring interference of this Court. 03. On the other hand, learned Government Pleader for Irrigation, while admitting about the claim of the petitioners, placed on record a copy of the written instructions received from the Executive Engineer (F.A.C.), Godavari Western Division, Nidadavolu, dated 18.08.2026. He submitted that the works had been completed by the petitioner in all respects, and necessary
4 W.P.No.27286 of 2025
Quality Control Check Certificates had been issued, and that the final bills have not been uploaded into the NIDHI portal due to lack of funds. The instructions further indicate that (i) gross amount of Rs. 7,13,227/- out of which Rs.45,936/- to be recovered, and thereby a net amount of Rs.6,67,291/- is payable to M/s.K.Ramalinga Raju Infra Project (Petitioner – 1) and (ii) gross amount of Rs.32,27,317/-, out of which Rs.1,80,507/- to be recovered and thereby a net amount of Rs.30,46,810/- is payable to Sri Bollam Seshagiri Rao (petitioner No.2). 04.
In view of the submissions of the learned counsel for the petitioner and the learned Government Pleader for Irrigation, this Writ Petition is disposed of with a direction to the respondents to release the amount of Rs.37,14,101/- (Gross value of Rs.39,40,544/- with statutory recoveries Rs.2,26,443/-) to the petitioners, along with the interest as per the entitlement within a period of two (02) months from the date of receipt of a copy of this order. However, if the petitioner is entitled to any higher amount, the same shall also be paid as per the entitlement. Consequently, Miscellaneous Petitions, if any, pending in this Writ Petition shall stand closed. ___________________ ___ JUSTICE B.S. BHANUMATHI
Date: 18.08.2026 GRL
5 W.P.No.27286 of 2025
248
THE HONOURABLE MS JUSTICE B S BHANUMATHI
WRIT PETITION NO:27286 of 2025
Date: 18.08.2026 GRL
6 W.P.No.27286 of 2025