APHC010367912026
IN THE HIGH COURT OF ANDHRA PRADESH AT AMARAVATI (Special Original Jurisdiction) [3327] MONDAY, THE 17th DAY OF AUGUST 2026 PRESENT THE HONOURABLE SRI JUSTICE K SREENIVASA REDDY WRIT PETITION NO: 19705/2026 Between:
1. D SRINIVASA RAO, S/O VENKATRAMAIAH, AGED 41 YEARS, OCC. CONTRACTOR, R/O D.NO. 8-38, UPPALAPADU VILLAGE, PEDAKAKANI MANDAL, GUNTUR DISTRICT, A.P. PIN. 522509. ...PETITIONER AND
1. THE STATE OF ANDHRA PRADESH, REP. BY ITS PRINCIPAL SECRETARY, DEPARTMENT OF FINANCE AND PLANNING,
SECRETARIAT BUILDINGS, VELAGAPUDI, AMARAVATHI, GUNTUR DISTRICT, A.P.
PIN. 522238. 2. THE STATE OF ANDHRA PRADESH, REP., BY ITS PRINCIPAL SECRETARY,
DEPARTMENT OF PANCHAYAT RAJ AND RURAL DEVELOPMENT, SECRETARIAT BUILDINGS, VELAGAPUDI, AMARAVATI, GUNTUR DISTRICT, A.P. PIN. 522238. 3. THE MANDAL PARISHAD DEVELOPMENT OFFICER FAC, MANDAL PRAJA PARISHAD, PEDAKAKANI
2 SRK, J W.P.No.19705 of 2026
MANDAL, GUNTUR DISTRICT, A.P. PIN. 507211. ...RESPONDENT(S): Petition under Article 226 of the Constitution of India praying that in the circumstances stated in the affidavit filed therewith, the High Court may be pleased topleased to issue an appropriate Writ, Order or direction more particularly one in the nature of Writ of Mandamus declaring the action of the respondents no. 1 to 3 in withholding the admitted amount of Rs. 3,00,000/- even after finalizing the bills, payable to the petitioner in relation to the work i.e., 'Gravelling the R/F Panchayathraj Road to Sibar Hospital Compound Wall in S.C. Colony of Takkellapadu Village, Pedakakani Mandal', vide Articles of Agreement, dt.Ol.03.2024, for amount of Rs. 3,00,000/- is waiting for fund clearance with respondents no. 1 to 3 as illegal, arbitrary and violative of Article 14, 19 and 21 of the Constitution of India and consequently direct the respondents no. 1 to 3 to forthwith consider for payment of the cumulative amount of Rs. 3,00,000/- with interest @24percent per annum for the delayed amount to the petitioner in respect of execution of above-mentioned work forthwith in terms of Agreement for 'Gravelling the R/F Panchayathraj Road to Sibar Hospital Compound Wall in S.C. Colony of Takkellapadu Village, Pedakakani Mandal', and pass IA NO: 1 OF 2026 Petition under Section 151 CPC praying that in the circumstances stated in the affidavit filed in support of the petition, the High Court may be pleased pleased to direct the respondents no. 1 to 3 to forthwith consider for payment of the cumulative amount of Rs.
3,00,000/- with interest @24% per annum for the delayed amount to the petitioner in respect of execution of abovementioned work forthwith in terms of Agreement for "Gravelling the R/F Panchayathraj Road to Sibar Hospital Compound Wall in S.C. Colony of Takkellapadu Village, Pedakakani Mandal”, vide Articles of Agreement, dt.01.03.2024 and pass
3 SRK, J W.P.No.19705 of 2026
Counsel for the Petitioner:
1. DASARI RAMAKOTESWAR RAO Counsel for the Respondent(S):
1. GP FOR PANCHAYAT RAJ RURAL DEV
2. GP FOR FINANCE PLANNING
3. Mattegunta.Sudhir,Standing Counsel For Z.P.Ps,M.P.Ps,Gram Panchayats The Court made the following:
4 SRK, J W.P.No.19705 of 2026
O R D E R
This Writ Petition is filed seeking the following relief:
“….to issue a Writ or order or direction more particularly one in the nature of Writ of Mandamus declaring the action of respondents Nos. 1 to 3 in withholding the admitted amount of Rs.3,00,000/- even after finalizing the bills payable to the petitioner in relation to the work, i.e., Gravelling the R/F Panchayath Raj Road to Sibar Hospital Compound Wall in S.C. Colony of Takkellapadu Village, Pedakakani Mandal, vide Agreement dated 01.03.2024, for amount of Rs. 3,00,000/-, is waiting for fund clearance with respondents Nos. 1 to 3, as illegal, arbitrary and violative of Article 14, 19 and 21 of the Constitution of India and consequently, direct the respondents Nos.1 to 3 to forthwith consider for payment of the cumulative amount of Rs.3,00,000/- with interest at 24% per annum for the delayed amount to the petitioner in respect of execution of above-mentioned work in terms of Agreement dated 01.03.2024 and pass such other order…”
2. Heard learned counsel for the petitioner, the learned Assistant Government Pleader for Panchayat Raj and Rural Development and the learned Standing Counsel for the Gram Panchayat. 3. The petitioner claims to be a registered contractor engaged in the execution of civil works and that he was entrusted with the work of the Panchayat Raj Department on a tender basis. It is the case of the petitioner that he was awarded a contract for execution of the work as mentioned above. It is the case of the petitioner that he executed the work to the satisfaction of the authorities concerned, and upon completion of the work, the respondent authorities measured the same and recorded the measurements in the Measurement Books.
5 SRK, J W.P.No.19705 of 2026
4. It is the grievance of the petitioner that notwithstanding the completion of the work and its measurement by the competent authorities, the amount due towards the executed work has not been paid till date. According to the petitioner, although the work was completed long back, the respondent authorities are not releasing the admitted amount payable to him. Aggrieved by the non-payment of the said amount, the petitioner filed the present Writ Petition. 5. Having regard to the fact that in spite of granting number of adjournments, the respondent authorities neither secured written instructions nor filed counter-affidavits, the respondent authorities are directed to verify and pay the admitted amount for the works executed by the petitioner within a period of Eight (08) weeks from the date of receipt of the order. It is made clear that the petitioner shall execute an indemnity bond to the effect that in case, if it is found that the petitioner has not executed the work, he would repay the amount so paid. 6. Accordingly, the Writ Petition is disposed of. There shall be no order as to costs. As a sequel thereto, the miscellaneous applications, if any, pending in this Writ Petition, shall stand closed. ______________________________ JUSTICE K. SREENIVASA REDDY Date: 17.08.2026 ANS