CHAITANYA CONSTRUCTIONS v. AP EDUCATION AND WELFARE INFRASTRUCTURE
WP/19456/2026 · 2026-08-03
Venkateswarlu Nimmagadda
body2026
DailyLaw.ai
[ 2026 DAILYLAW 37796 (AP) · dailylaw.ai ]
DailyLaw.ai
[ 2026 DAILYLAW 37796 (AP) · dailylaw.ai ]
Judgment text
Extracted from the PDF above. The PDF is authoritative.
APHC010358212026
IN THE HIGH COURT OF ANDHRA PRADESH AT AMARAVATI (Special Original Jurisdiction)
TUESDAY, THE 4th DAY OF AUGUST 2026 PRESENT THE HONOURABLE SRI JUSTICE VENKATESWARLU NIMMAGADDA WRIT PETITION NO: 19456 OF 2026 Between:
1. CHAITANYA CONSTRUCTIONS, Rep by its proprietor, Arnepalli Sankara Rao, S/o Late Surynaryana, Aged about 54 years, R/o.D.No.16/8, Plot No. 109, Satya Surya Nilayam, MIG-II, Housing Board Colony, Visakhapatnam, Visakhapatnam District ...Petitioner AND
1. AP EDUCATION AND WELFARE INFRASTRUCTURE, Development Corporation (APEWIDC), Rep,by its Managing Director, R/o D. No. 9-76, Sai Fortune Heights, Block-A, Vaddeswaram Village, Guntur District-522502. 2. The Chief Engineer, AP Education and Welfare Infrastructure Development Corporation (APEWIDC), Vijayawada, NTR District. 3. The Superintending Engineer, AP Education and Welfare Infrastructure Development Corporation (APEWIDC), Guntur District. 4. The Executive Engineer, AP Education and Welfare Infrastructure Development Corporation (APEWIDC), Machilipatnam, Krishna District. ...Respondents Petition under Article 226 of the Constitution of India praying that in the circumstances stated in the affidavit filed therewith, the High Court may be
2
pleased toleased to issue writ, order or direction, more particularly one in the nature of writ of mandamus declaring the inaction on part of the respondents in considering the representations, dated 10.12.2025 and 11.12.2025 submitted by the petitioner to immediately grant permission to commence the work and to hand over the required site and to provide the approved drawings and structural designs, as illegal, arbitrary, abdication of statutory duty apart from being violative of the Fundamental Right guaranteed to me under Articles 14, 19 and 21 of the Constitution of India and consequently direct the respondents to immediately grant permission to commence the work and to hand over the required site and to provide the approved drawings and structural designs to the Petitioner and pass IA NO: 1 OF 2026 Petition under Section 151 CPC praying that in the circumstances stated in the affidavit filed in support of the petition, the High Court may be pleased pleased to direct the Respondents to consider the representation in considering the representations, dated 10.12.2025 and 11.12.2025 submitted by the Petitioner firm, pending disposal of the Writ Petition and pass Counsel for the Petitioner: YARRAMSETTY VENKATESH Counsel for the Respondents:
3
THE HONOURABLE SRI JUSTICE VENKATESWARLU NIMMAGADDA WRIT PETITION NO: 19456 OF 2026 The Court made the following order:
Heard learned counsel for the Writ petitioner and the learned Standing Counsel for the APEWID Corporation. 2.
2. This Writ Petition is filed seeking direction to the respondents to immediately grant permission to commence the work and to hand over the required site and to provide the approved drawings and structural designs to the Petitioner. 3. Learned counsel for the petitioner submits that on 12.02.2024 the respondent No.1 had issued tender notification for construction of the Integrated Finance Complex Building at Machilipatnam in Krishna District and bids were also invited on the e-procurement platform. The Petitioner’s firm has participated in the e-procurement bids and submitted its’ bid as the petitioner firm is interested in executing the work. Thereafter, the respondent no.3 had issued a letter to the petitioner’s firm by accepting the bid of the petitioner’s company and directs the petitioner’s firm to attend the respondent office with all the documents/certificates for concluding the contract by way of agreement on or before 20.03.2024. Thereafter, the petitioner firm had complied with all the conditions as required by the respondents. Though, the petitioner had complied with all the conditions, he did not receive approved drawings to start the work for early completion of work, for which, he has submitted two representations dated 10.12.2025 and 11.12.2025 to the petitioners, but so far the respondents did not act on the representations. Hence, learned counsel for the writ petitioner requested this court to direct the respondents to consider the above representations by passing orders. 4. Per contra, learned Standing Counsel for the Respondents had expressed his consent to direct the respondents to dispose of the two
4
representations dated 10.12.2025 and 11.12.2025 by granting reasonable time. 5. Having heard the submissions of both counsels, this Court deems it appropriate to dispose of this Writ Petition by directing the concerned respondents to pass speaking order on the representations dated 10.12.2025 and 11.12.2025 submitted by the writ petitioner as per law, after providing opportunity of hearing to the writ petitioner, within six weeks from the date of receipt of this Order. 6. With these directions, this Writ Petition is disposed of. No order as to costs. 7. Consequently, Miscellaneous Petitions, if any, pending in this Writ Petition shall stand closed. ________________________________ VENKATESWARLU NIMMAGADDA, J Dt: 04.08.2026 Mnr
5
83
THE HONOURABLE SRI JUSTICE VENKATESWARLU NIMMAGADDA
WRIT PETITION No.19456 OF 2026
Dt: 04.08.2026 Mnr