TEJA CORPORATE RELATIONS v. THE STATE OF ANDHRA PRADESH
WP/19549/2026 · 2026-08-09
K Sreenivasa Reddy
body2026
DailyLaw.ai
[ 2026 DAILYLAW 37525 (AP) · dailylaw.ai ]
DailyLaw.ai
[ 2026 DAILYLAW 37525 (AP) · dailylaw.ai ]
Judgment text
Extracted from the PDF above. The PDF is authoritative.
APHC010351122026
IN THE HIGH COURT OF ANDHRA PRADESH AT AMARAVATI (Special Original Jurisdiction) [3327] MONDAY, THE 10th DAY OF AUGUST 2026 PRESENT THE HONOURABLE SRI JUSTICE K. SREENIVASA REDDY WRIT PETITION NO: 19549/2026 Between:
1. TEJA CORPORATE RELATIONS, REP. BY ITS MANAGING PARTNER, SRI KOTHURU VENKATESH, OFFICE AT PLOT NO. 101, NARAYANAPURAM COLONY, VIJAYAWADA - 521137, ANDHRA PRADESH. ...PETITIONER AND
1. THE STATE OF ANDHRA PRADESH, REP. BY ITS PRINCIPAL SECRETARY, RURAL WATER SUPPLY AND SANITATION DEPARTMENT, A.P. SECRETARIAT, VELAGAPUDI, AMARAVATI - 522238, ANDHRA PRADESH. 2. THE STATE OF ANDHRA PRADESH, REP. BY ITS PRINCIPAL SECRETARY, FINANCE DEPARTMENT, A.P. SECRETARIAT, VELAGAPUDI, AMARAVATI - 522238, ANDHRA PRADESH. 3. THE DISTRICT COLLECTOR AND DISTRICT MAGISTRATE, PRAKASAM DISTRICT, ONGOLE-523001, ANDHRA PRADESH. 4. THE SUPERINTENDING ENGINEER, RURAL WATER SUPPLY AND SANITATION CIRCLE, ONGOLE-523001, PRAKASAM DISTRICT, ANDHRA PRADESH. 5. THE EXECUTIVE ENGINEER, RURAL WATER SUPPLY AND SANITATION (P) DIVISION PODILI - 523240, PRAKASAM DISTRICT, ANDHRA PRADESH. 6. THE DEPUTY EXECUTIVE ENGINEER, RURAL WATER SUPPLY AND SANITATION SUB-DIVISION, PODILI - 523240, PRAKASAM
2 SRK, J WP.No.19549 of 2026
DISTRICT, ANDHRA PRADESH. 7. THE ENGINEERINCHIEF, RURAL WATER SUPPLY AND SANITATION, GOLLAPUDI, VIJAYAWADA - 521225, ANDHRA PRADESH. ...RESPONDENT(S): Petition under Article 226 of the Constitution of India praying that in the circumstances stated in the affidavit filed therewith, the High Court may be pleased to issue a Writ, Order or Direction more particularly one in the nature of Writ of Mandamus by directing the Respondents to release the pending payments due of a total amount of Rs. 23,35,367.90/- (comprising Rs.15,50,691/- as per RTI reply and Rs.7,84,676.90/- as per M.Book records) to the Petitioner, M/s Teja Corporate Relations, for the geo-tagging services rendered in the Podili Division of Kanigiri, Yerragondapalem ( Y.Palem ), Podili Sub-divisions of Prakasam District from January 2018 to March 2020, Vide (I) Agreement No. 47/2017-18, dated 09.01.2018, (II) Agreement No. 1/47/2017-18, dated 05.09.2018 and (III) Agreement No. 2/47/2017-18, dated 19.09.2020, along with interest at 12percent per annum for the delayand to pass such IA NO: 1 OF 2026 Petition under Section 151 CPC praying that in the circumstances stated in the affidavit filed in support of the petition, the High Court may be pleased may be pleased to direct the Respondents to process the pending payments due of a total amount of Rs.
23,35,367.90/-, as verified through the RTI response dated 12.12.2024 and M.Book records, to mitigate the financial hardship faced by the Petitioner, pending disposal of the Writ Petition and pass such Counsel for the Petitioner:
1. HANUMANTHA RAO BACHINA Counsel for the Respondent(S):
1. GP FOR PANCHAYAT RAJ RURAL DEV
2. GP FOR FINANCE PLANNING The Court made the following:
3 SRK, J WP.No.19549 of 2026
O R D E R
This Writ Petition is filed, seeking the following relief:
“….to issue a Writ, Order or Direction more particularly one in the nature of Writ of Mandamus by directing the Respondents to release the pending payments due of a total amount of Rs. 23,35,367.90/- (comprising Rs.15,50,691/- as per RTI reply and Rs.7,84,676.90/- as per M.Book records) to the Petitioner, M/s Teja Corporate Relations, for the geo-tagging services rendered in the Podili Division of Kanigiri, Yerragondapalem ( Y.Palem ), Podili Sub-divisions of Prakasam District from January 2018 to March 2020, Vide (I) Agreement No. 47/2017-18, dated 09.01.2018, (II) Agreement No.1/47/2017-18, dated 05.09.2018 and (III) Agreement No. 2/47/2017-18, dated 19.09.2020, along with interest at 12% per annum for the delay and pass such other order…”
2. Heard the learned counsel for the petitioner, the learned Assistant Government Pleader for Panchayat Raj and Rural Development and the learned Standing Counsel for the Gram Panchayat. 3. The petitioner claims to be engaged in the execution of civil works and that it was entrusted with various works of the Panchayat Raj Department and the Roads & Buildings Department on a tender basis. It is its case that it was awarded a contract for execution of the work viz. For the Geo-tagging services rendered in the Podili Division of Kanigiri, Yerragondapalem (Y.Palem), Podili Sub-divisions of Prakasam District from January, 2018 to March, 2020. It is its case that it executed the work to the satisfaction of the authorities concerned, and upon completion of the work, the respondent authorities measured the same and recorded the measurement in the Measurement Book. 4. It is the grievance of the petitioner that notwithstanding the completion of the work and its measurement by the competent authorities, the amount due towards the executed work has not been paid till date. According to the
4 SRK, J WP.No.19549 of 2026
petitioner, although the work was completed long back, the respondent authorities are not releasing the admitted amount payable to it.
Aggrieved by the non-payment of the said amount, the petitioner filed the present Writ Petition. 5. Learned Assistant Government Pleader for Panchayat Raj, on oral instructions received from the Executive Engineer, RWS (P) Division, Podili- 5th respondent, submits that there is no dispute with regard to the execution of the subject work by the petitioner herein. He further submits that the bill was passed and approved by the SW Engineer in CFMS on 05.03.2024 and was subsequently approved by the Pay and Accounts Officer on the same day. He further submits that Vigilance enquiry is being continued in respect of the work executed by the petitioner herein. 6. A perusal of the material on record goes to show that even according to the respondents, there is no dispute with regard to execution of the subject works by the petitioner, and the petitioner‟s entitlement for the net amount. On this aspect, it is pertinent to refer to a decision of the Hon‟ble Apex Court in M/s. Utkal Highways Engineers and Contractors v. Chief General Manager & Ors.1, wherein it was held as under: (Paragraph No.8)
“Be that as it may, the High Court has not dealt with the merits of the Writ Petition. Moreover, it is not an inviolable rule that no money claim can be adjudicated upon in exercise of Writ jurisdiction. Non-payment of admitted dues, inter alia, may be considered an arbitrary action on the part of respondents and for claiming the same, a Writ Petition may lie. Further, throwing a Writ Petition on ground of availability of alternative remedy after 10 years, particularly, when parties have exchanged their affidavits, is not the correct course unless there are disputed questions of fact which by their very nature
1 2025 SCC OnLine SC 1400. 5 SRK, J WP.No.19549 of 2026
cannot be adjudicated upon without recording formal evidence.”
7.
On this aspect, it is also pertinent to refer to a decision of the Hon‟ble Apex Court in Hari Krishna Mandir Trust v. State of Maharashtra and Others2 wherein it is held as under: (paragraph Nos.100 and 101)
“100. The High Courts‟ exercising their jurisdiction under Article 226 of the Constitution of India, not only have the power to issue a Writ of Mandamus or in the nature of Mandamus, but are duty-bound to exercise such power, where the Government or a public authority has failed to exercise or has wrongly exercised discretion conferred upon it by a statute, or a rule, or a policy decision of the Government or has exercised such discretion mala fide, or on irrelevant consideration. 101. In all such cases, the High Court must issue a Writ of Mandamus and give directions to compel performance in an appropriate and lawful manner of the discretion conferred upon the Government or a public authority.”
8. Further, in Kashmir Wood Products v. Verinag Development Authority and Others3, the High Court of Jammu & Kashmir held as under: (paragraph No.8)
“8. It is astonishing to note that despite there being no dispute as regards the claim of the petitioners, the respondents have sit over the matter for the last more than six years and they have not released the payment in favour of the petitioner. If the requisite funds were not available with the respondents, they had no business to allot the work to the petitioner and if in spite of financial constraints, the respondents have made the petitioner
2 AIR 2020 Supreme Court 3969. 3 2021 SCC OnLine J&K 814. 6 SRK, J WP.No.19549 of 2026
to execute the work out of his own funds, it is their bounden duty to reimburse the petitioner at the earliest, that too with interest.”
9. Since, in the case on hand, the amounts payable are admitted and undisputed, non-payment thereof amounts to arbitrary action on the part of the respondents, and hence, the Writ Petitions are maintainable. 10.
The only contention of the learned Assistant Government Pleader is that a Vigilance Inquiry was initiated basing on the complaints received with regard to some irregularities that occurred in execution of the subject works, and that the Director General (Vigilance and Enforcement), Vijayawada is conducting inquiry and the Inquiry Report is awaited. In regard to pendency of Vigilance Inquiry, it is also pertinent to refer to a decision rendered by Coordinate Bench of this Court, in Katta Chinna Kotaiah v. The State of Andhra Pradesh4 wherein, this Court held as under:
“The Apex Court and this Court in catena of decisions held that when there is non-payment of the undisputed bills, the same is violative of Articles 14 and 16 of the Constitution of India. The counsel for the petitioner rightly placed reliance on the decision of the Apex Court in M/s. Surya Constructions v. State of Uttar Pradesh and others [(2019) 16 SCC 794], following the judgment in ABL International Ltd. v. Export Credit Guarantee Corporation of India Ltd. [2004 (3) SCC 553]. In view of the Apex Court
judgment, the contention of the learned Government Pleader that the Writ Petition is not maintainable before this Court could not be countenanced. The bills of the petitioner dated 13.03.2019 are admitted by the respondents and forwarded for payment after due measurements and obtaining quality control and the Vigilance report. Hence, the authorities are stopped from stating that the bills are submitted without executing the works. On the mere
4 MANU/AP/0721/2022. 7 SRK, J WP.No.19549 of 2026
ground of pendency of Vigilance report, payment cannot be stopped. Accordingly, there shall be a direction to the respondents to pay the bill amount of Rs.8,08,828/- to the petitioner within a period of six weeks from the date of receipt of copy of this order.”
11. In the case on hand, the only ground for not releasing the amounts to the petitioner is that the authorities are awaiting Vigilance Inquiry Report. As held in the aforesaid decision, mere pending receipt of the Vigilance Inquiry Report is not a ground to withhold the payments. Pendency of a file before the Vigilance Department, without any incidence, cannot be a ground to indefinitely postpone or deny the payment for the works duly executed. 12. There cannot be any dispute that the vigilance inquiry is independent of the statutory and administrative functions of the executing Departments relating to the scrutiny, processing, and release of payments, and that the vigilance authorities are not competent to issue directions restraining the competent authorities from considering the claim of the contractors who executed the works or advise them to await completion of the vigilance inquiry before taking an appropriate decision in accordance with applicable Rules. It is also not disputed that the findings, if any, of the Vigilance and Enforcement Department, are only advisory and recommendatory in nature, and are placed before the competent authorities for such action as may be deemed appropriate in accordance with law. In the event any irregularity warranting recovery is noticed subsequently, it is always open to the competent authorities to initiate appropriate action in accordance with law. 13. The respondent-authorities cannot withhold the legitimate payments due to the contractors who admittedly and genuinely executed the works entrusted to them. Once the works have been duly executed and the amounts have become payable, the respondent-authorities are under an obligation to take a decision on the claims in accordance with law.
The State
8 SRK, J WP.No.19549 of 2026
and its instrumentalities cannot withhold legitimate payments on extraneous considerations. Administrative inaction cannot be allowed to defeat a legitimate claim, particularly when the respondents do not dispute the execution of the works or demonstrate any lawful impediment to the release of the admitted dues. 14. The Hon‟ble Apex Court in Surya Constructions v. State of Uttar Pradesh and Others5 held as under: (paragraph Nos.3 and 4)
“3. It is clear, therefore, from the aforesaid Order dated 22.03.2014 that there is no dispute as to the amount that has to be paid to the appellant. Despite this, when the appellant knocked at the doors of the High Court in a Writ Petition being Writ Civil No.25216 of 2014, the impugned judgment dated 02.05.2014 [Surya Construction v. State of U.P., 2014 SCC OnLine All 6071] dismissed the Writ Petition stating that disputed questions of fact arise and that the amount due arises out of a contract. We are afraid the High court was wholly incorrect inasmuch as there was no disputed question of fact. On the contrary, the amount payable to the appellant is wholly undisputed. Equally, it is well settled that where the State behaves arbitrarily, even in the realm of contract, the High Court could interfere under Article 226 of the Constitution of India (ABL International Ltd. v. Export Credit Guarantee Corpn. Of India Ltd. [ABL International Ltd. v. Export Credit Guarantee Corpn. of India Ltd., (2004) 3 SCC 553]). 4. This being the case and the work having been completed long back in 2009, we direct Uttar Pradesh Jal Nigam to make the necessary payment within a period of four weeks from today. 5 (2019) 16 SCC 794. 9 SRK, J WP.No.19549 of 2026
Given the long period of delay, interest @ 6% p.s. may also be awarded.”
15.
Learned counsel for the writ petitioner relied on a decision of a Co- ordinate Bench of this Court dated 04.07.2025 in W.P.No.12525 of 2024, wherein it is held thus: (paragraphs 7 and 8)
“7. This Court after hearing the respective counsel is of the considered opinion that as there is no dispute to the execution of the works and the amounts due to the petitioner, as apparent from Paragraph No.5 of the Counter Affidavit, the petitioners in that scenario cannot be called upon to wait peremptorily for conclusion of vigilance enquiry to receive their rightful amounts. At the same time, this Court cannot foreclose the vigilance enquiry.
8. Therefore, a balance has to be maintained vis-à-vis the ongoing vigilance enquiry and petitioners, whose execution of works and amounts due are not in dispute. Therefore, it would be appropriate to dispose of the Writ Petition with the following directions: (i) The petitioner shall submit a security bond undertaking to reimburse the amount to the Respondent-Corporation, if any on account of deficiency in the work or excess payment is made by the Respondent-Corporation pursuant to the ongoing vigilance enquiry; (ii) On furnishing of security bond, the Respondent authorities are
directed to pay the amounts due to the Petitioner within a period of six (6) months from today…”
16. The aforesaid order has been followed by another learned single Judge of this Court, in the Common Order dated 10.04.2026 in Writ Petition Nos. 1916 of 2026, 2111 of 2026 and 2116 of 2026,
10 SRK, J WP.No.19549 of 2026
17. The maxim „Justice delayed is justice denied‟ is one of the most enduring principles of the administration of justice. It conveys a simple, yet profound truth,- „justice loses much of its meaning when it is delivered too late‟. A remedy obtained after years of waiting may, in practical terms, ceases to be a remedy at all. The essence of justice is not merely deciding a dispute correctly, but in deciding it fairly, efficiently, and within a reasonable time. 18. For a successful litigant, a judgment that comes after years of struggle may offer little solace, and the relief would have lost much of its practical value. The maxim also reminds us that the right to speedy justice is an essential component of the rule of law. As Lord Hewart observed, “Justice should not only be done, but should manifestly and undoubtedly be seen to be done.”
19. To this, I am of the opinion to further add that justice should also be done in time. Justice, therefore, is not complete when it is pronounced, but it is complete when it is delivered in time to make it remedy effective. 20. When an instrumentality of the State acts contrary to the public good and public interest, unfairly, unjustly and unreasonably, in its contractual, constitutional or statutory obligations, it really acts contrary to the constitutional guarantee under Article 14 of the Constitution of India. It is not the case of the respondents that the contracts in question were obtained either by fraud or misrepresentation. Therefore, there is no other reason for the respondent authorities for not releasing the amounts in favour of the petitioner. Apart from this, when State or State instrumentalities act in an arbitrary manner or fail to act within time, the Writ Court does have jurisdiction to entertain the matter. In the aforesaid circumstances, in the considered opinion of this Court, mere pending receipt of the Vigilance Inquiry Report is not a ground for withholding the amounts for the works which are admittedly executed by the petitioner.
11 SRK, J WP.No.19549 of 2026
21. In view of the foregoing discussion and having regard to all the facts and circumstances of the case, the respondent-authorities are directed to verify and pay the respective admitted amounts due to the petitioner within a period of Eight (8) weeks from the date of receipt of this Order. 22. It is made clear that in the event of any irregularity noticed in the Vigilance Inquiry Report, warranting recovery, it is open to the authority concerned to initiate appropriate action in accordance with law. The petitioner shall execute an indemnity bond to the above effect that if it is found that the petitioner has not executed the subject contract works, it would repay the amount so paid. 23. Accordingly, the Writ Petition is disposed of. There shall be no order as to costs. As a sequel thereto, the miscellaneous applications, if any, pending in this Writ Petition, shall stand closed. _____________________________ JUSTICE K. SREENIVASA REDDY Date: 10.08.2026. MS
12 SRK, J WP.No.19549 of 2026
HON’BLE SRI JUSTICE K. SREENIVASA REDDY
Writ Petition No:19549 of 2026 Date: 10.08.2026
MS