SRI KILARI SRINIVASULU v. The State of Andhra Pradesh
WP/20397/2026 · 2026-07-30
Harinath N
body2026
DailyLaw.ai
[ 2026 DAILYLAW 37207 (AP) · dailylaw.ai ]
DailyLaw.ai
[ 2026 DAILYLAW 37207 (AP) · dailylaw.ai ]
Judgment text
Extracted from the PDF above. The PDF is authoritative.
1 HN, J W.P.No.20397_2026 APHC010375562026
IN THE HIGH COURT OF ANDHRA PRADESH AT AMARAVATI (Special Original Jurisdiction) [3457] FRIDAY, THE 31st DAY OF JULY 2026 PRESENT THE HONOURABLE SRI JUSTICE HARINATH.N WRIT PETITION NO: 20397/2026 Between:
1. SRI KILARI SRINIVASULU, S/O.K.GOPALAIAH, AGED 47 YEARS,3- 1-238,NAGENDRA NAGAR,
NAWABPET, NELLORE, SPSR NELLORE DISTRICT. ...PETITIONER AND
1. THE STATE OF ANDHRA PRADESH, REP BY ITS PRINCIPAL SECRETARY, DEPARTMENT OF MUNICIPAL, ADMINISTRATION URBAN DEVELOPMENT, SECRETARIAT BUILDING, VELAGAPUDI, AMARAVATHI, GUNTUR.522238
2. THE STATE OF ANDHRA PRADESH,
2. THE EXECUTIVE ENGINEER, NELLORE MUNICIPAL CORPORATION , NELLORE, SPSR NELLORE DISTRICT.524001
3. THE NELLORE MUNICIPAL CORPORATION, REP.BY. COMMISSIONER,NELLORE, SPSR NELLORE DISTRICT.524001
4. THE STATE OF ANDHRA PRADESH, REP. BY ITS PRINCIPAL SECRETARY,
DEPARTMENT OF FINANCE
PLANNING, SECRETARIAT BUILDINGS, VELAGAPUDI, AMARAVATHI, GUNTUR DISTRICT.522238
...RESPONDENT(S): Petition under Article 226 of the Constitution of India praying that in the circumstances stated in the affidavit filed therewith, the High Court may be pleased topleased to issue an appropriate Writ Order or direction more particularly one in the nature of Writ of Mandamus declaring the action of the
2 HN, J W.P.No.20397_2026 Respondents in withholding the payments of pending amounts of Rs. 47,81,944/- (Rupees Forty Seven Lakhs, Eighty One Thousand Nine Hundred and Forty Four Rupees only) even after finalizing the bills payable to the petitioner in relation to the works Laying ofCC Roads a) From Mekala Nagabhushanamma House to Akki Suresh House in Gudipailipadu b) From Kurudumpa Girichenchaiah House to Narayanareddypeta Link Road Gudipailipadu Construction of CC Drain and Culverts c) from Mathamma Temple Outlet Drain near 2/3 Sachivalayam in Guduipallipadu d) From Arundathiyawada Outlet Drain to Layout Drain in Guduipallipadu e) From Satyamraju House, Rangula Factory to Outlet Drain in Guduipallipadu f) From Balaramapuram ST Colony outlet Drain to Main Road in Gidipallipadu in Division No. 2 of Nellore Municipal Corporation. Agreement no.47/SE/JTO- ii/2024-25 ,Dt17.03.2025,as bad ,illegal, arbitrary, improper, unjust and against the Article 21 of constitution of india and consequently direct the respondents to pay the amounts of Rs.
47,81,944/- (Rupees Forty Seven Lakhs, Eighty One Thousand Nine Hundred and Forty Four Rupees only) with interest 24per annum for the delayed amount till date of realization for the works executed by the petitioner and pass IA NO: 1 OF 2026 Petition under Section 151 CPC praying that in the circumstances stated in the affidavit filed in support of the petition, the High Court may be pleased Pleased to direct the respondents to forthwith consider releasing the amounts Rs. 47,81,944/-(Rupees Forty Seven Lakhs, Eighty One Thousand Nine Hundred and Forty Four Rupees only) herein, pending disposal of the writ petition and pass Counsel for the Petitioner:
1. DEVASRI ROSHAN KANCHARLA Counsel for the Respondent(S):
1. 3 HN, J W.P.No.20397_2026
ORDER:
1. The petitioner is aggrieved by the action of the respondents in withholding the payments of pending amounts of Rs. 47,81,944/- (Rupees Forty Seven Lakhs, Eighty One Thousand Nine Hundred and Forty Four Rupees only) even after finalizing the bills payable to the petitioner in relation to the works Laying of CC Roads a) From Mekala Nagabhushanamma House to Akki Suresh House in Gudipailipadu b) From Kurudumpa Girichenchaiah House to Narayanareddypeta Link Road Gudipailipadu Construction of CC Drain and Culverts c) from Mathamma Temple Outlet Drain near 2/3 Sachivalayam in Guduipallipadu d) From Arundathiyawada Outlet Drain to Layout Drain in Guduipallipadu e) From Satyamraju House, Rangula Factory to Outlet Drain in Guduipallipadu f) From Balaramapuram ST Colony outlet Drain to Main Road in Gidipallipadu in Division No. 2 of Nellore Municipal Corporation. Agreement no.47/SE/JTO-ii/2024-25 , dated 17.03.2025.
2. The learned counsel further submits that the petitioner duly executed all the works and thereafter submitted final bills, which were duly endorsed by the competent authority. A statement detailing the works executed by the petitioner was prepared, and the progress of the work was recorded in the M-book. However, in spite of the completion of all procedural formalities, the payment towards the completed works has not been released till date.
3. Heard the submissions of the learned counsel for the petitioner, the learned Government Pleader for Municipal Administration & Urban
4 HN, J W.P.No.20397_2026 Development, Sri A.S.C.Bose, learned Standing Counsel for the Municipality and the learned Assistant Government Pleader for Finance and Planning.
4. During the course of hearing, the learned Standing Counsel appearing for the respondents does not dispute the submissions made by the petitioner with respect to the completion of the work undertaken and that the non- payment of bills is due to paucity of funds.
5. Considering the submissions, the concerned respondents are hereby
directed to verify and release the payments due payable to the petitioner as expeditiously as possible preferably within a period of eight weeks from the date of receipt of a copy of this order.
6. Accordingly, the writ petition is disposed of. No costs. Pending miscellaneous petitions, if any, shall stand closed.
___________________ JUSTICE HARINATH.N Date:31.07.2026 NKA
Whether the order is : Speaking Yes/No / Reasoned Yes/No Reportable Yes/No / Non-Reportable Yes/No
5 HN, J W.P.No.20397_2026 268 THE HONOURABLE SRI JUSTICE HARINATH.N
WRIT PETITION NO: 20397 of 2026 Date: 31.07.2026
NKA