IN THE HIGH COURT OF ANDHRA PRADESH AT AMARAVATI (Special Original Jurisdiction) [3327] MONDAY, THE 20th DAY OF JULY 2026 PRESENT THE HONOURABLE SRI JUSTICE K SREENIVASA REDDY WRIT PETITION NO: 9940/2026 Between:
1. K S S ENGINEERING SERVICE, REP., BY ITS PROPRIETRIX, JONNALAGADDA VENKATA PAVANI D/O SRINIVASARAO, OCC VWC MEMBER, R/O 1-71/A, B.C COLONY, AMUDALAPALLE, UNGUTURU MANDAL, KRISHNA DISTRICT. ...PETITIONER AND
1. THE STATE OF AP, REP. BY ITS PRINCIPAL SECRETARY, PANCHAYAT RAJ AND RURAL DEVELOPMENT DEPARTMENT, SECRETARIAT BUILDINGS, VELAGAPUDI, AMARAVATHI, GUNTUR DISTRICT. (522238)
2. THE DISTRICT COLLECTOR, KRISHNA DISTRICT AT MACHILIPATNAM. (521002)
3. THE EXECUTIVE ENGINEER, R.W.S AND S DIVISION, MACHILIPATNAM @ GUDIVADA. (521324)
4. THE DEPUTY EXECUTIVE ENGINEER, R.W.S AND S SUB-DIVISION, GANNAVARAM. (521101)
5. THE AMUDALAPALLI GRAM PANCHAYAT, REP., BY ITS SECRETARY, AMUDALAPALLI VILLAGE, UNGUTURU MANDAL, KRISHNA DISTRICT. (521324)
6. THE STATE OF ANDHRA PRADESH, REP., BY ITS PRINCIPAL SECRETARY,
FINANCE AND PLANNING DEPARTMENT, SECRETARIAT BUILDINGS, VELAGAPUDI, AMARAVATHI, GUNTUR
2
DISTRICT. (522238)
...RESPONDENT(S): Petition under Article 226 of the Constitution of India praying that in the circumstances stated in the affidavit filed therewith, the High Court may be pleased to issue a WRIT OF MANDAMUS declaring the action of the Respondents herein, in withholding the payment of 1st and Final Bill, Net Amount of Rs. 4,14,704/- (Gross Amount of Rs. 4,58,480/-), even after finalizing the bills payable to the petitioner in relation to the works i.e., Augmentation of PWS Scheme in Amudalapalli Village of Unguturu Mandal as per the Agreement, Dt. 17.06.2023 (Work Order No Proc.Rc.No. 523/Tl/DB/CMDF-Amudalapalli/2023, Dt. 06.06.2023) is questioned, as the same is illegal, arbitrary and violative of Articles 14, 16, 19 and 300-A of Constitution of India and consequently direct the respondents to consider for payment of Dt 85 Final Bill, Net Amount of Rs. 4,14,704/- (Gross Amount of Rs. 4,58,480/-) with an interest @24 percent per annum for the delayed amount to the petitioner in respect of execution of above-mentioned work forthwith and pass IA NO: 1 OF 2026 Petition under Section 151 CPC praying that in the circumstances stated in the affidavit filed in support of the petition, the High Court may be pleased pleased to DIRECT the respondents to consider for payment of 1st & Final Bill, Net Amount of Rs.
4,14,704/- (Gross Amount of Rs.4,58,480/-) with an interest of 24% per annum for the delayed amount to the petitioner in respect of execution of works i.e., “Augmentation of PWS Scheme in Amudalapalli Village of Unguturu Mandal as per the Agreement, Dt. 17.06.2023 (Work
Order No: Proc.Rc.No.523/Tl/DB/CMDF-Amudalapalli/2023, Dt. 06.06.2023)”, pending disposal of the Writ Petition and pass Counsel for the Petitioner:
1. SURESH KUMAR REDDY KALAVA Counsel for the Respondent(S):
1. GP FOR PANCHAYAT RAJ RURAL DEV
2. GP FOR REVENUE
3. Yarraguntla.Koteswara Rao,Standing Counsel For Zilla Praja
3
Parishads,Mandal Praja Parishads and Gra
4. GP FOR FINANCE PLANNING The Court made the following:
ORDER:-
This Writ Petition is filed under Article 226 of the Constitution of India seeking the following prayer:
“…to issue a WRIT OF MANDAMUS declaring the action of the Respondents herein, in withholding the payment of 1st and Final Bill, Net Amount of Rs.4,14,704/- (Gross Amount of Rs. 4,58,480/-), even after finalizing the bills payable to the petitioner in relation to the works i.e., “Augmentation of PWS Scheme in Amudalapalli Village of Unguturu Mandal as per the Agreement, Dt.17.06.2023 (Work Order No: Proc.Rc.No. 523/ Tl/DB/CMDF-Amudalapalli/2023, Dt.06.06.2023) is questioned, as the same is illegal, arbitrary and violative of Articles 14, 16, 19 and 300-A of Constitution of India and consequently direct the respondents to consider for payment of 1st & Final Bill, Net Amount of Rs. 4,14,704/- (Gross Amount of Rs. 4,58,480/-) with an interest @ 24% per annum for the delayed amount to the petitioner in respect of execution of above-mentioned work forthwith and pass…”
2. Case of the petitioner firm, in brief, is that pursuant to the administrative sanction accorded by respondent No.2 under CMDF Grant vide proceedings dated 27.03.2023, respondent No.5-Panchayat resolved to entrust the work of
“Augmentation of PWS Scheme in Amudalapalli Village of Ungutur Mandal’, to
4
the petitioner’s firm on a nomination basis vide Resolution No.09 dated
26.04.2023. Accordingly, respondent No.4 entered into an agreement with the petitioner on 17.07.2023 and subsequently executed a supplemental agreement on 25.09.2023. The petitioner’s firm completed the work within the stipulated time. Thereafter, the respondent authorities measured the work, recorded the measurements in the Measurement Book, and passed the 1st & Final Bill on 08.01.2025 for a net amount of Rs.4,14,704/- (gross amount of Rs.4,58,480/-). However, despite the completion of the work and passing of the bill, the respondent authorities have failed to take steps to release the said amount till date. Aggrieved thereby, the present Writ Petition has been filed by the petitioner herein. 3. Heard learned counsel for the petitioner and the learned Assistant Government Pleader for Panchayat Raj and Rural Development appearing for the respondents. Perused the material available on record. 4. Learned Assistant Government Pleader for Panchayat Raj and Rural Development, on written instructions received from the Executive Engineer, RWS&S Division, Machilipatnam, submits that there is no dispute either with regard to the work executed by the petitioner or the amount payable to the petitioner.
According to him, due to technical issue, the CMDF bills are not being uploaded in the CFMS/NIDHI Portal. He further submits that the payment will be released after the technical issue is resolved and seeks six
5
months’ time for payment of the said amount. The written instructions are placed on record. 5. Since the amount payable is admitted and undisputed, the writ petition is maintainable. In M/s Utkal Highways Engineers and Contractors Vs. Chief General Manager & Ors1, it was held at Para No.8 as under:
“Be that as it may, the High Court has not dealt with the merits of the writ petition. Moreover, it is not an inviolable rule that no money claim can be adjudicated upon in exercise of writ jurisdiction. Non- payment of admitted dues, inter alia, may be considered an arbitrary action on the part of respondents and for claiming the same, a writ petition may lie. Further, throwing a writ petition on ground of availability of alternative remedy after 10 years, particularly, when parties have exchanged their affidavits, is not the correct course unless there are disputed questions of fact which by their very nature cannot be adjudicated upon without recording formal evidence.”
6. Having regard to the fact that there is no dispute with regard to the work executed by the petitioner and in view of the submissions made by the learned Assistant Government Pleader for Panchayat Raj and Rural Development,, the respondent authorities are directed to pay the Net amount of Rs.4,14,704/- (Rupees Four Lakhs Fourteen Thousand Seven Hundred and Four only) payable to the petitioner, within a period of six (6) weeks from the date of receipt of a copy of this order. 1 2025 SCC OnLine SC 1400
6
7. Accordingly, the Writ Petition is disposed of. There shall be no order as to costs. As a sequel thereto, the miscellaneous applications, if any, pending in the Writ Petition shall stand closed.
_____________________________ JUSTICE K.SREENIVASA REDDY Date: 20.07.2026 anr
7
HON’BLE SRI JUSTICE K.SREENIVASA REDDY
Writ Petition No.9940 of 2026 Date: 20.07.2026
anr