SHRI.K.DHANA SEKAR v. THE SUPERINTENDING ENGINEER AND AND
WPA/48/2026 · 2026-02-10
Arijit Banerjee
body2026
DailyLaw.ai
[ 2026 DAILYLAW 3501 (CAL) · dailylaw.ai ]
DailyLaw.ai
[ 2026 DAILYLAW 3501 (CAL) · dailylaw.ai ]
Judgment text
Extracted from the PDF above. The PDF is authoritative.
1
IN THE HIGH COURT AT CALCUTTA [ CIRCUIT BENCH AT PORT BLAIR ] ***
WPA/48/2026
Shri K. Dhana Sekar
Vs.
The Superintending Engineer and …
Mr. U. Partha Sarathi
... for the petitioner
Mr.S.C. Mishra
… for the respondents [through virtual mode] February 10, 2026 [SR] Item No.49 Learned advocate for the Electricity Department says that the petitioner’s application for electric connection was rejected on December 10, 2025, since there was deficiency in the application. Necessary documents were not submitted with the application.
Learned advocate for the petitioner says that the petitioner shall make a fresh application enclosing thereto necessary documents.
If such application is made within a fortnight from date, the Electricity Department shall process the same, in accordance with law. If the petitioner’s application is found to be in order, then, within thirty days from date of the petitioner complying with all formalities including payment
of requisite charges, the department shall provide electricity connection to the petitioner.
WPA/48/2026 is disposed of.
Parties to act on the server copy of this order downloaded from the official website of this Court.
( Arijit Banerjee, J. )