p. 1 IN THE HIGH COURT OF ORISSA AT CUTTACK
W.P.(C) No.22433 of 2026 CNR No. ODHC010532792026
Siba Prasad Padhi …. Petitioner Mr. A.Parija, Sr.Advocate
-versus-
Odisha Industrial Infrastructure Development Corporation, Bhubaneswar & Ors. …. Opposite Parties
CORAM:
SHRI JUSTICE B. P. ROUTRAY
ORDER 11.09.2026
Order No.
02.
1. The matter is taken up through hybrid mode.
2. Heard Mr. Parija, learned Senior Counsel for the Petitioner.
3. It is submitted that the admitted dues of the Petitioner pursuant to completion of construction of M.Tech Hostel Building for Veer Surendra Sai University of Technology (VSSUT) at Burla, is pending for more than seven years. In this regard the representation of the Petitioner is pending before the authority.
4. Accordingly, the writ petition is disposed of at the stage of admission with a direction to the Chief General Manager (Civil), IDCO, Bhubaneswar (Opposite Party No.2) to consider the grievance of the Petitioner as per his representation at Annexure-9 and take decision, in accordance with law, within a period of two months from the date of Digitally Signed Signed by: SANGRAM DAS Reason: Authentication Location: High Court of Orissa, Cuttack Date: 11-Sep-2026 14:46:18 Signature Not Verified p. 2 receipt of certified copy of this order along with a copy of the writ petition.
5. An urgent certified copy of this order shall be issued on proper application.
(B.P. Routray)
Judge
S.Das