Date of reserved for orders : --- Date of pronouncement :01.07.2026 Date of uploading :16.07.2026 APHC010516552025
IN THE HIGH COURT OF ANDHRA PRADESH AT AMARAVATI (Special Original Jurisdiction) [3331] WEDNESDAY, THE 1st DAY OF JULY 2026 PRESENT THE HONOURABLE SRI JUSTICE SUBBA REDDY SATTI WRIT PETITION NO: 27705/2025 Between:
1. K. RAMALINGARAJU INFRA PROJECT,, REP BY K.RAMALINGARAJU S/O K.JAGANNADHARAJU,
MANAGING PARTNER, 1-0, NEAR RTO OFFICE, OPP SITAM ENGINEERING COLLEGE K L PURAM, VIZIANAGARAM. 2. BOLLAM SESHAGIRI RAO, S/O ABADDAM, AGED 46 YEARS, OCC CIVIL CONTRACTOR,R/O FLAT NO 202, PRIDES VIRGO CLASISICS AVENUE , NEAR SYDICATE BANK. RING ROAD, VIZIANAGARAM. ...PETITIONER(S) AND
1. THE STATE OF ANDHRA PRADESH, REP. BY ITS PRINCIPLE SECRETARY,
IRRIGATION DEPARTMENT, SECRETARIAT BUILDINGS VELAGAPUDI, AMARAVATHI, GUNTUR DIST.,
2. THE STATE OF ANDHRA PRADESH, REP. BY ITS PRINCIPLE SECRETARY,
FINANCE AND PLANNING DEPARTMENT, SECRETARIAT BUILDINGS VELAGAPUDI, AMARAVATHI, GUNTUR DIST,
3. THE ENGINEER IN CHIEF, IRRIGATION DEPARTMENT, AMARAVATHI, GUNTUR DIST.,
4. THE DISTRICT COLLECTOR, WEST GODAVARI DIST AT BHIMAVARAM. 5. THE SUPERINTENDENT ENGINEER, IRRIGATION DEPARTMENT, ELURU. Page 2 of 5
6. THE EXECUTIVE ENGINEER, DRAINAGE DIVISION, BHMAVARAM, WEST GODAVARI DIST. ...RESPONDENT(S): Petition under Article 226 of the Constitution of India praying that in the circumstances stated in the affidavit filed therewith, the High Court may be pleased to issue order or orders, direction or directions, Writ or Writs particularly one in the nature Writ of Mandamus or any appropriate writ declare the action of the respondents in not paying the bills for execution of works by the Petitioner works under 1. Agreement No. 18/2024-25, dt.09-07- 2024 2. Agreement No. 19/2024-25, dt.09-07-2024 3.
Agreement No. 20/2024-25, dt.09- 07-2024Total four works amount of Rs.37,62,033/- to the petitioner with 6 percent interest till the date of final payment from the date of completion of respective works, as illegal, arbitrary violation of principles of natural justice and violative of Article 14, 19 (i) g, 21 of the Constitution of India, consequently direct the respondents to release the bills for the above completed works immediately with 6 percent interest and to pass IA NO: 1 OF 2025 Petition under Section 151 CPC praying that in the circumstances stated in the affidavit filed in support of the petition, the High Court may be pleased prayed that this Hon'ble Court may be pleased to direct the respondents to release the amount of Rs.37,62,033/-towards payment of above final bills for the contract works under taken by the petitioner long back, pending disposal of main writ petition and to pass Counsel for the Petitioner(S):
1. K L N SWAMY Counsel for the Respondent(S):
1. GP FOR IRRI AND CAD
2. GP FOR FINANCE PLANNING The Court made the following order: Heard, Sri K.L.N.Swamy, learned counsel for the petitioner and Sri Satish, learned Assistant Government Pleader for Irrigation and Command Area Development for the respondents. 2. The above writ petition was filed to declare the action of the respondents in not releasing an amount of Rs.37,62,033/- payable to the petitioner in relation to the works executed i.e., i) Agreement No.18/2024-25 p. 3 dated 09.07.2024, ii) Agreement No.19/2024-25 dated 09.07.2024 and iii) Agreement No.20/2024-25 dated 09.07.2024, as illegal and arbitrary. 3. Learned counsel for the petitioner would submit that the petitioner has executed the works; however, the respondent authorities have failed to release the amount payable. Learned counsel would further submit that the amount claimed by the petitioner includes the EMD amount. 4. Today, when the matter is taken up, the learned Assistant Government Pleader, Irrigation and Command Area Development, submitted instructions of the Executive Engineer, Drainage Division, Bhimavaram – 6th respondent vide Letter No.EE/DD/BVRM/AB/A.4/CC’s/96 dated 21.01.2026. 5. Learned Assistant Government Pleader would submit that the petitioner is entitled to an amount of Rs.5,10,226/- in respect of the first work, Rs.9,29,087/- in respect of the second work, and Rs.15,94,004/- in respect of the third work, totaling Rs.30,33,317/-. The amount referred to supra is exclusive of the EMD amount.
The EMD amount will be released to the petitioner after the final bill. 6. In reply, learned counsel for the petitioner would submit that in respect of the EMD amount, liberty may be granted to the petitioner to approach the Court if the respondent authorities fail to release the amount after the payment of the principal amount. In respect of the interest, learned counsel would submit that liberty may be granted to the petitioner to approach the competent Civil Court. 7. Thus, as seen from the instructions, there is no dispute regarding the execution of the aforementioned works and the petitioner’s entitlement for Rs.30,33,317/-. Since the amount payable is admitted and undisputed, the writ petition is maintainable. In M/s Utkal Highways Engineers and Contractors v. Chief General Manager & Ors1, it was held at Para No.8 as under: p. 4
1 2025 SCC online SC 1400
“Be that as it may, the High court has not dealt with the merits of the writ petition. Moreover, it is not an inviolable rule that no money claim can be adjudicated upon in exercise of writ jurisdiction. Non-payment of admitted dues, inter alia, may be considered an arbitrary action on the part of respondents and for claiming the same, a writ petition may lie. Further, throwing a writ petition on ground of availability of alternative remedy after 10 years, particularly, when parties have exchanged their affidavits, is not the correct course unless there are disputed questions of fact which by their very nature cannot be adjudicated upon without recording formal evidence.”
8. Given the instructions furnished by the Executive Engineer, Drainage Division, Bhimavaram – 6th respondent, the Writ Petition is disposed of directing the respondents to release the amount of Rs.30,33,317/- (Rupees Thirty Lakhs Thirty Three Thousand Three Hundred and Seventeen only) payable to the petitioner regarding execution of aforementioned works, within Four (04) months from the date of receipt of the copy of this order. 9.
Liberty is granted to the petitioner in case of non-refund of the EMD amount to approach the Court again after payment of the principal amount. Liberty is also granted to the petitioner, subject to the entitlement under the terms of the agreement, to claim interest by approaching the competent Civil Court. No order as to costs. As a sequel, pending miscellaneous petitions, if any, shall stand closed. ___________________________ JUSTICE SUBBA REDDY SATTI Date: 01.07.2026 SNI Whether the order is:
Speaking Yes/No / Reasoned Yes/No Reportable Yes/No / Non-Reportable Yes/No p. 5 226 THE HONOURABLE SRI JUSTICE SUBBA REDDY SATTI
WRIT PETITION NO: 27705 of 2025
Date: 01.07.2026 SNI