Research › Search › Judgment

High Court of Andhra Pradesh · body

2026 DAILYLAW 33967 (AP)

RKN PROJECTS PRIVATE LTD v. The State of Andhra Pradesh

WP/28030/2024 · 2026-06-30

Subba Reddy Satti

body2026

Judgment text

Extracted from the PDF above. The PDF is authoritative.

Date of reserved for orders : --- Date of pronouncement :01.07.2026 Date of uploading :15.07.2026 APHC010536312024 IN THE HIGH COURT OF ANDHRA PRADESH AT AMARAVATI (Special Original Jurisdiction) [3331] WEDNESDAY, THE 1st DAY OF JULY 2026 PRESENT THE HONOURABLE SRI JUSTICE SUBBA REDDY SATTI WRIT PETITION NO: 28030/2024 Between: 1. RKN PROJECTS PRIVATE LTD, REP BY ITS MANAGING DIRECTOR, N RAMESH KUMAR, S/O N BALAIAH, AGED ABOUT 58 YEARS, OC CONTRACTOR, R/O D NO 26-2-29, 2ND LANE, RITHWIK, ENCLAVE, A.K.NAGAR, NELLORE, SPSR NELLORE DISTRICT ...PETITIONER AND 1. THE STATE OF ANDHRA PRADESH, REP. BY ITS PRINCIPAL SECRETARY, IRRIGATION DEPARTMENT, SECRETARIAT BUILDINGS, VELAGAPUDI, AMARAVATI, GUNTUR DISTRICT, ANDHRA PRADESH. 2. THE STATE OF ANDHRA PRADESH, REP. BY ITS PRINCIPAL SECRETARY, FINANACE DEPARTMENT, SECRETARIAT BUILDINGS, VELAGAPUDI, AMARAVATI, GUNTUR DISTRICT, ANDHRA PRADESH. 3. THE SUPERINTENDING ENGINEER, SSLC AND SB CIRCLE, NELLORE, S.P.S.R. NELLORE DISTRICT. 4. THE EXECUTIVE ENGINEER, SSLC AND SB DIVISION NO-1, NELLORE, S.P.S.R NELLORE DISTRICT. ...RESPONDENT(S): Petition under Article 226 of the Constitution of India praying that in the circumstances stated in the affidavit filed therewith, the High Court may be pleased to issue a Writ, order or direction more particularly one in the nature p. 2 of Writ of Mandamus declaring the action of the Respondents in not paying the interest amount of Rs.49,53,425/- to the Petitioner @ 6percent per annum for the execution of the work under Construction of side drain at K.R.R Centre at GundavoluArundatiwada Village, Rapur (M), SPSR Nellore District, with Agreement No. 38SE/2018-2019 Dated 07.09.2018 and Suppl. Agreement No. 5SE/2019-2020 Dated 01.08.2019 to the petitioner is arbitrary, illegal and consequently direct the respondents to pay the interest amount for i.e., 1) 1151 days, 2) 763 days 3) 605 days and 4) 252 days delay @ 6 percent per annum as per the orders of Honble High Court in W.A.No. 724 of 2021 and batch Dated 12.10.2023 to the petitioner for the execution of the above said works on the admitted bill amount from the date when the bills were submitted by the petitioner for payment to till the date of final payment and pass such IA NO: 1 OF 2024 Petition under Section 151 CPC praying that in the circumstances stated in the affidavit filed in support of the petition, the High Court may be pleased IA NO: 1 OF 2025 Petition under Section 151 CPC praying that in the circumstances stated in the affidavit filed in support of the petition, the High Court may be pleased to grant leave to the Respondent No.4 to file Counter Affidavit in WP.No.28030 of 2024 and to pass Counsel for the Petitioner: 1. S SIVA KUMARI Counsel for the Respondent(S): 1. GP FOR IRRI AND CAD 2. GP FOR FINANCE PLANNING The Court made the following order: Heard Sri S.Bhaskar, learned counsel representing Smt. S.Siva Kumari, learned counsel for the petitioner and Sri Satish, learned Assistant Government Pleader for Irrigation and Command Area Development for the respondents 1 to 4. p. 3 2. The above writ petition was filed to declare the action of the respondents in not paying interest amount of Rs.49,53,425/- @ 6% per annum in relation to the works executed by the petitioner at KRR Centre, Gundavolu Arundatiwada Village, Rapur Mandal, SPSR Nellore District, vide Agreement No.38SD/2018-2019 dated 07.09.2018 and the Supplementary Agreement No.5SE/2019-2020 dated 01.08.2019, as illegal and arbitrary. 3. The basis of the petitioner’s claim, as seen from the affidavit, is the order of the Division Bench in W.A.No.724 of 2021 and batch dated 12.10.2023. 4. A counter-affidavit was filed on behalf of the 4th respondent. In para-6 of the counter-affidavit, it was noted that the payment was made to the petitioner. In para-7 of the counter-affidavit, it was pleaded about the condition No.6.0 of the Agreement and Clause 69 of the Andhra Pradesh Standard Specifications and further contended that the contractor is not entitled to claim interest upon any guarantee fund or payments in arrears or balances. In para-8 of the counter-affidavit, it was pleaded about the order dated 11.02.2025 in W.A.No.60 of 2025. 5. No rejoinder was filed by the petitioner. 6. The point for consideration is: Whether the petitioner is entitled to claim interest in the light of clause 69 of the Andhra Pradesh Standard Specifications by invoking the extraordinary jurisdiction under Article 226 of the Constitution of India? 7. Before delving into the facts, it is necessary to refer to Clause 69 of the Andhra Pradesh Detailed Standard Specifications, which reads as under: “69. Interest on money due to the contractor:- (a) No omission by the Executive Engineer or the Sub-Divisional Officer to pay the amount due upon certificates shall vitiate or make void the contract, nor shall the contractor be entitled to interest upon any p. 4 guarantee fund or payments in arrear, nor upon any balance which may, on the final settlement of his accounts, be found to be due to him. (b) Whenever the withheld amount reaches Rs. 1,000 or a multiple thereof, the contractor may, at his option, deposit with Executive Engineer Rs. 1,000 or a multiple thereof, in any of the forms of interest bearing securities recognized for the purpose by the Andhra Pradesh Public Works Accounts Code and subject to the provisions therein contained, in which case in the equivalent withheld amount shall be paid to him forthwith. The contractor will be permitted to exercise the option in this clause, subject only to the condition that the rate of progress contained in the Articles of Agreement is properly maintained.” 8. In A.P.S.R.T.C. vs. P. Ramanareddi,1 the learned single judge of the composite High Court interpreted the scope of Clause 69 and observed as under: “23. Thus it is clear that this Clause 69 is intended to really prevent any claim for interest during the running period when final bill is not settled and also in respect of earnest money deposit or the sum equal to 2½ % of the total value of the work done till the expiry of the period of six months. This six months‟ period is called „observation period‟, so that the Department can see whether the work was done satisfactorily or not. Clause 69 cannot be construed as a total prohibition, but it operates a limited period of six months from the date of the completion of the work and hence I negative this contention that Clause 69 is a bar to claim interest. 24. It is fairly well settled that the claim for interest can either be under the agreement, or under the usage of trade having force of law, or under the provisions of substantive law or under the provisions of the Interest Act, 1839 or when the Court exercises equitable jurisdiction as envisaged in the proviso to Sec. 1 of the said Act. (Vide: Vithal dass v. Rup Chand (AIR 1967 SC 188). So far as the requirement of Interest Act is concerned, the Supreme Court in Thawardas v. Union of India (AIR 1955 SC 468) laid down five conditions: 1. The interest is not payable under any other law. 2. there must be a debt or a sum certain. 3. it must be payable at a certain time or otherwise. 1 1988 SCC OnLine AP 343 : (1989) 1 ALT 195 p. 5 4. these debts or sums must be payable by virtue of some written instrument. 5. there must have been a demand in writing stating that interest will be demanded from the date of the demand.” 9. In W.A.No.60 of 2025, the Division Bench, after considering the order in W.A.No.724 of 2024 on which the petitioner placed reliance, observed as follows: “8. It needs to be pointed out that it is no longer res integra as has been held by a three-Judge Bench of the Apex Court in Union of India vs. Bright Power Projects (India) (P) Ltd.1 that when parties to a contract agree that interest would not be awarded on the amount payable to the contractor under the contract, the contractor in those circumstances cannot claim interest either before a civil Court or before an arbitral tribunal. The Apex Court held: “10. …so far as payment of interest on the amount payable to the contractor under the contract was concerned, there was a specific term that no interest was to be paid thereon. 11. When parties to the contract had agreed to the fact that interest would not be awarded on the amount payable to the contractor under the contract, in our opinion, they were bound by their understanding. Having once agreed that the contractor would not claim any interest on the amount to be paid under the contract, he could not have claimed interest either before a civil court or before an Arbitral Tribunal.” 9. In fact, Section 3(3) of the Interest Act, 1978, specifically carves out an exception and recognizes the right of the parties to contract out of the payment of interest on any duty or damages by virtue of an express agreement. Section 3 (3) (a) (ii) of the Act reads thus: “3 (3) (a) (i) … (ii) any debt or damages upon which payment of interest is barred, by virtue of an express agreement;” 10. In the light of the aforementioned facts and the law as discussed hereinabove, in our opinion, the judgment and order impugned to the extent it orders payment of interest @ 6% per annum, in our view, is unsustainable. The judgment and order to that extent is set aside. However, we make it clear that this would not prejudice the right of p. 6 any of the parties to agitate their respective claims and counter- claims before an appropriate forum, in accordance with law.” 10. That being the legal regime, the petitioner’s claim regarding the interest, unless the petitioner lets in evidence, it may not be possible to determine the issue. The petitioner has to establish the completion of work within the time stipulated; non-payment of the amount as per the terms and conditions; and entitlement to claim interest despite cl. 69 APSS in the contract need to be examined by a competent authority based upon the evidence. It is a well- settled law that, in a Writ Petition, a disputed question of fact should ordinarily not be entertained. The Hon’ble Apex Court in Himmat Singh vs. State of Haryana,2 held that: "18. ...In the grounds of a writ petition only a question of law can be raised and not a statement of fact. No statement has been made in the body of the writ petition. The statement made in the said grounds was also not verified in accordance with the writ rules. Despite the same, as we have noticed hereinbefore, the fifth respondent in his affidavit denied or disputed the contents thereof. Whether the statement of the appellant or the fifth respondent was correct or not could not ordinarily be decided in a writ proceeding. It is well known that in a writ petition ordinarily such a disputed question of fact should not be entertained..." 11. Also in Punjab National Bank vs. Atmanand Singh,3 recently the Hon’ble Apex Court, restricting the scope of interference under Article 226 of the Constitution, held that: "22. We restate the above position that when the petition raises questions of fact of complex nature, such as in the present case, which may for their determination require oral and documentary evidence to be produced and proved by the party concerned and also because the relief sought is merely for ordering a refund of money, the High Court should be loath in entertaining such writ petition and instead must relegate the parties to remedy of a civil suit. Had it been a case where material facts referred to in the writ petition are admitted facts or indisputable facts, the High Court may p. 7 2 (2006) 9 SCC 256 3 (2020) 6 SCC 256 be justified in examining the claim of the writ petitioner on its own merits in accordance with law." 12. Thus, the discussion supra, apart from the judgment of the Division Bench, since Clause 69 of the Andhra Pradesh Standard Specifications is made part of the contract, the petitioner is not entitled to claim interest. The petitioner’s entitlement, if any, vis-à-vis the interest, it requires evidence to be let in. Without proper evidence on record, in the considered opinion of this court, granting interest in the facts of the case is impermissible. 13. Given the facts and circumstances of the case, the writ petition is disposed of, directing the petitioner to approach the appropriate forum regarding interest. There shall be no order as to costs. As a sequel, pending miscellaneous petitions, if any, shall stand closed. ___________________________ JUSTICE SUBBA REDDY SATTI Date: 01.07.2026 SNI Whether the order is: Speaking Yes/No / Reasoned Yes/No Reportable Yes/No / Non-Reportable Yes/No p. 8 224 THE HONOURABLE SRI JUSTICE SUBBA REDDY SATTI WRIT PETITION NO: 28030 OF 2024 Date: 01.07.2026 SNI