APHC010343522024
IN THE HIGH COURT OF ANDHRA PRADESH AT AMARAVATI (Special Original Jurisdiction) [3504] WEDNESDAY,THE TWENTY NINETH DAY OF APRIL TWO THOUSAND AND TWENTY SIX PRESENT THE HONOURABLE SRI JUSTICE MAHESWARA RAO KUNCHEAM WRIT PETITION NO: 17669/2024 Between:
1. KUKKALA RAMAKRISHNA, S/O KRISHNA MURTHY, AGED 43 YEARS, OCC CONTRACTOR, D.NO. 5-3, KONTHERU VILLAGE, ELAMANCHILI MANDAL, WEST GODAVARI DISTRICT. ...PETITIONER AND
1. THE STATE OF AP, REP. BY ITS PRINCIPAL SECRETARY HOUSING DEPARTMENT SECRETARIAT, VELAGAPUDI, AMARAVATI, THULLUR MANDAL, GUNTUR DISTRICT. 2. STATE OF ANDHRA PRADESH, REP. BY ITS PRINCIPAL SECRETARY FINANCE DEPARTMENT, SECRETARIAT, VELAGAPUDI, AMARAVATI, THULLUR MANDAL, GUNTUR DISTRICT. 3. A P STATE HOUSING CORPORATION LTD, 2 ND FLOOR, SP RIVER VIEW BUILDING, TADEPALLI, AMARAVATI, REP. BY ITS MANAGING DIRECTOR. 4. THE DISTRICT COLLECTOR, WEST GODAVARI DISTRICT, BHIMAVARAM. 5. THE SUPERINTENDING ENGINEER, (DELEGATED WITH POWERS OF CE) APSHCL HEAD OFFICE, VIJAYAWADA. 6. THE PROJECT DIRECTOR, A.P. STATE HOUSING CORPORATION LTD, WEST GODAVARI DISTRICT, BHIMAVARAM. 7. THE DISTRICT HEADHOUSING, WEST GODAVARI DISTRICT, BHIMAVARAM. 8. THE EXECUTIVE ENGINEER, A.P. STATE HOUSING CORPORATION LTD, WEST GODAVARI DISTRICT, BHIMAVARAM. 2
9. THE DIVISION HEAD HOUSING, A.P. STATE HOUSING CORPORATION LTD, NARASAPURAM DIVISION, NARASAPURAM, WEST GODAVARI DISTRICT. ...RESPONDENT(S): Petition under Article 226 of the Constitution of India praying that in the circumstances stated in the affidavit filed therewith, the High Court may be pleased topleased to issue a Writ, Order, or Direction more particularly one in the nature of WRIT OF MANDAMUS or any other appropriate writ or direction declaring the action of the respondents in not releasing the payments for the works of Formation of Approach Roads, Culverts, Shifting of Electrical lines and Filling of Low-lying Lands in YSR Jagananna layout colonies of Konteru Village, Elamanchili Mandal, West Godavari District i.e., i) Providing Approach Road in YSR Jagananna Housing Colony Layout ID 054421LA112359 namely Konteru Layout No.3 in Kontheru Village of Elamanchili Mandal (Bit-1) for an amount of Rs. 4,32,212/-, ii) Providing Approach Road in YSR Jagananna Housing Colony Layout ID No. 054421 LA112359 namely Konteru Layout No.3 in Kontheru Village of Elamanchili Mandal (Bit-2) for an amount of Rs. 3,24,910/- and hi) Providing Culvert in YSR Jagananna Housing Colony Layout ID 054421 LA112359 namely Konteru Layout-3 at Konteru Village, Elamanchili Mandal for an amount of Rs. 4,51,725/- totaling an amount of Rs.
12,08,847/- as illegal, arbitrary and violative of Art 14 and 21 of Constitution of India and consequently direct the respondent authorities to release Rs. 12,08,847/- forthwith for the above said works executed by the petitioner and pass Counsel for the Petitioner:
1. RAMBABU KOPPINEEDI Counsel for the Respondent(S):
1. E V JAGANNADHA RAO (SC FOR AP STATE HOUSEING COOP LTD)
2. MALLIKHARJUNA MOORTHY K (SC FOR A.P HOUSING CORPORATION LIMITED)
3. GP FOR HOUSING
4. GP FOR FINANCE PLANNING The Court made the following:
3
HONOURABLE SRI JUSTICE MAHESWARA RAO KUNCHEAM
WRIT PETITION NO.17669/2024
ORDER:
This Writ Petition under Article 226 of the Constitution of India is filed seeking the following main relief:
“declaring the action of the respondents in not releasing the payments for the works of Formation of Approach Roads, Culverts, Shifting of Electrical lines and Filling of Low-lying Lands in YSR Jagananna layout colonies of Konteru Village, Elamanchili Mandal, West Godavari District i.e., i) Providing Approach Road in YSR Jagananna Housing Colony Layout ID 054421LA112359 namely Konteru Layout No.3 in Kontheru Village of Elamanchili Mandal (Bit-1) for an amount of Rs. 4,32,212/-, ii) Providing Approach Road in YSR Jagananna Housing Colony Layout ID No. 054421 LA112359 namely Konteru Layout No.3 in Kontheru Village of Elamanchili Mandal (Bit-2) for an amount of Rs. 3,24,910/- and hi) Providing Culvert in YSR Jagananna Housing Colony Layout ID 054421 LA112359 namely Konteru Layout-3 at Konteru Village, Elamanchili Mandal for an amount of Rs. 4,51,725/- totaling an amount of Rs. 12,08,847/- as illegal, arbitrary and violative of Art 14 and 21 of Constitution of India and consequently direct the respondent authorities to release Rs. 12,08,847/- forthwith for the above said works executed by the petitioner and pass”
2. The sum and substance of the writ petition is that the petitioner challenged the inaction of the respondents in not releasing the amounts even after completion of the entire works entrusted to him.
3. Heard learned counsel for the petitioner, learned Assistant Government Pleader for Finance & Planning and Sri K. Mallikarjuna Moorthy, learned Standing Counsel for the respondent Corporation.
4.
Learned counsel for the petitioner, while reiterating the averments made in the writ affidavit, submits that in view of the non-release of the
4
admitted amounts, the petitioner is facing multifarious problems, physically and fiscally. Hence, he submits that the release of the amounts is just and essential. 5. On the other hand, learned Standing Counsel for the respondent Corporation, places a copy of the written instructions dated 27.04.2026 issued by the concerned authority of the Corporation and submits that the bills amount of Rs.12,08,847/-(Rupees Twelve Lakhs Eight Thousand Eight Hundred and Forty Seven Only) is going to be uploaded within three weeks in the NIDHI Module as per the Government procedure. He submits that three months' time may be granted for paying the admitted amounts to the petitioner. 6. Since it is not in dispute that the petitioner completed the works and has yet to receive payment, as evident from the written instructions dated 27.04.2026 of the concerned respondent Corporation authority, this Court finds the respondents‟ failure to pay is unjustified. However, taking into consideration of the ground realities to settle the admitted amounts, the respondents are granted rational time to settle the dues. 7. The respondent Corporation, being the instrumentality of the „State‟ within the meaning of Article 12 of the Constitution of India, is bound to release the amount for the undisputed works done by the petitioner, without any further delay. A mere financial incapacity or
5
paucity of funds cannot be a valid defence for non-fulfilment of such statutory obligations, more particularly, when the works executed by the petitioner are admitted by the respondent Corporation. 8. So far as the interest portion is concerned, the Hon‟ble Division Bench in the case of Managing Director &Ors. Vs. Sree Balaji Constructions &Ors. (Writ Appeal No.60 of 2025) held that the award of interest on delayed payments was unsustainable in the absence of specific terms and conditions of the relevant agreement between the parties, but in the instant case, the learned counsel for the petitioner has not touched on the said point. However, the Hon‟ble Division Bench in similar circumstances made it clear that the parties are at liberty to pursue their claims in respect of the interest portion before an appropriate forum in accordance with Law. 9.
In the light of the above legal position, coupled with the fact that the liability for the undisputed works was admitted by the respondents, the writ petition is disposed of with a direction to the respondents to release the amount of Rs.12,08,847/-(Rupees Twelve Lakhs Eight Thousand Eight Hundred and Forty Seven Only) payable to the petitioner, within a period of three (3) months, from the date of receipt of copy of this order. It is needless to say that the petitioner is at liberty to approach the appropriate forum with regard to interest, if so advised. 6
There shall be no order as to costs. Miscellaneous petitions pending, if any, shall stand closed. ______________________________ MAHESWARA RAO KUNCHEAM, J Date: 29.04.2026 GVK
7
74 THE HON’BLE SRI JUSTICE MAHESWARA RAO KUNCHEAM
WRIT PETITION No.17669 of 2024
Date: 29.04.2026
GVK
8