Extracted from the PDF above. The PDF is authoritative.
1
CGHC010293892026
2026:CGHC:36427
NAFR HIGH COURT OF CHHATTISGARH AT BILASPUR WP227 No. 1042 of 2026 1 - Kuhru S/o Ramnath Khadiya Aged About 57 Years Caste-Khadiya, R/o Village- Mudagaon, Presently Tahsil Tamnar, District- Raigarh, (C.G.) 2 - Dhaneshwar S/o Madhuram Aged About 55 Years Caste-Khadiya, R/o Village- Mudagaon, Presently Tahsil Tamnar, District- Raigarh, (C.G.) 3 - Bhimsen S/o Pilaram Aged About 54 Years Caste-Khadiya, R/o Village- Mudagaon, Presently Tahsil Tamnar, District- Raigarh, (C.G.) ... Petitioner(s) versus 1 - State Of Chhattisgarh Through The Secretary Department Of Revenue And Disaster, Mantralaya, Mahanadi Bhawan, Nawa Raipur, (C.G.) 2 - The Commissioner Upper Commissioner, Bilaspur Divsion, Bilaspur, (C.G.) 3 - The Collector Raigarh, District- Raigarh, (C.G.) 4 - The Sub-Divisional Officer (Revenue) Lailunga, Tahsil -Lailunga, District- Raigarh (C.G.) 5 - Rameshwar S/o Late Madan Singh Aged About 47 Years Caste-Aghariya, Occupation- Agriculture, R/o Village- Taragarh, Tahsil- Lailunga, District- Raigarh (C.G.) 6 - Bhuwneshwar S/o Late Madan Singh Aged About 45 Years Caste- Aghariya, Occupation- Agriculture, R/o Village-Taragarh, Tahsil-Lailunga , District- Raigarh (C.G.) 7 - Padum S/o Late Madan Singh Aged About 44 Years Caste-Aghariya, Occupation- Agriculture, R/o Village-Taragarh, Tahsil-Lailunga , District- Raigarh (C.G.) 8 - Khema S/o Late Madan Singh Aged About 43 Years Caste-Aghariya, SUMIT KUMAR Digitally signed by SUMIT KUMAR Date: 2026.08.19 16:31:14 +0530
2 Occupation- Agriculture, R/o Village-Taragarh, Tahsil-Lailunga , District- Raigarh (C.G.) 9 - Chandrashekhar S/o Late Madan Singh Aged About 41 Years Caste- Aghariya, Occupation- Agriculture, R/o Village-Taragarh, Tahsil-Lailunga , District- Raigarh (C.G.) 10 - Rukhmani S/o Late Madan Singh Aged About 39 Years Caste-Aghariya, Occupation- Agriculture, R/o Village-Taragarh, Tahsil-Lailunga , District- Raigarh (C.G.) 11 - Smt. Indumati @ Tekmati Wd/o Gangaram Aged About 67 Years Caste- Aghariya, Occupation- Agriculture, R/o Village-Taragarh, Tahsil-Lailunga , District- Raigarh (C.G.) 12 - Ghasiya @ Ashok S/o Late Gangaram Aged About 47 Years Caste- Aghariya, Occupation- Agriculture, R/o Village-Taragarh, Tahsil-Lailunga , District- Raigarh (C.G.) 13 - Tejram S/o Late Bhagirathi Aged About 72 Years Caste-Aghariya, Occupation- Agriculture, R/o Village-Taragarh, Tahsil-Lailunga , District- Raigarh (C.G.) 14 - Bhojram S/o Late Bhagirathi Aged About 67 Years Caste-Aghariya, Occupation- Agriculture, R/o Village-Taragarh, Tahsil-Lailunga , District- Raigarh (C.G.) ... Respondent(s) For Petitioner(s) : Mr. Roop Ram Naik, Advocate For Respondent(s) : Ms. Vaishali Mahilong, Dy.G.A. (Hon’ble Shri Justice Ravindra Kumar Agrawal, J.)
Order on Board 14/08/2026
1. The default pointed out by the Registry is waived.
2. Heard.
3. Present is a writ petition under Article 227 of the Constitution of India filed by the petitioner against the impugned order dated 04.04.2024
3 passed by Chhattisgarh Board of Revenue, Bilaspur in Revenue Case No. RN/13/R/A-23/45/2024, whereby the revision filed by the petitioner before Board of Revenue has been dismissed.
4.
Learned counsel for the petitioner would submit that against the order dated 11.07.2018 passed by Commissioner, Bilaspur Division, Bilaspur, the petitioner had earlier approached before this Court in WPC No. 937/2019, which was dismissed vide order dated 01.04.2019 with a direction to the petitioner to approach before the Board of Revenue in appropriate proceedings. The petitioner could approach the Board of Revenue on 05.02.2024 after obtaining the certified copy of the order dated 01.04.2019 passed in WPC No. 937/2019 and filed the revision on 16.02.2024. The same has been dismissed on the ground of delay and laches vide order dated 04.04.2024. He would further submit that the issue of possession over the subject land on the basis of an agreement and the applicability of provision under Section 170B of Chhattisgarh Land Revenue Code, 1959 is involved in the case before the Board of Revenue, which requires adjudication on merits. Therefore, even if there is some delay on the part of the petitioner, the same may be condoned and the Board of Revenue may be directed to decide the revision on its own merits. 5. I have heard learned counsel for the petitioner and perused the documents annexed with the petition. 6. The undisputed facts in the present writ petition is that the order dated 11.07.2018 passed by Commissioner, Bilaspur Division was earlier challenged by the petitioner before this Court in WPC No. 937/2019, which was dismissed vide order dated 01.04.2019 reserving liberty to
4 the petitioner to approach before the Board of Revenue in appropriate proceeding. However, after passing of the order dated 01.04.2019, the petitioner kept silent till 2024 and has not availed his remedy as has been reserved in his favour by the order dated 01.04.2019. The petitioner had approached Board of Revenue only on 16.02.2024 after obtaining the certified copy of the order dated 01.04.2019 passed by this Court in WPC No. 937/2019 for which there is no explanation for delay in filing the revision since 2019 up to 2024. The Board of Revenue has observed in its order that the petitioner was not diligent in prosecuting his case and there is no plausible explanation for delay in filing the revision. Even, the order dated 04.04.2024 passed by the Board of Revenue is challenged in the present petition after about more than 02 years, for which also there is no explanation. 7.
The Hon’ble Supreme Court in the matter of Postmaster General and others v. Living Media India Limited and another, (2012) 3 SCC 563, has dealt with the limitation issue and held as under:-
“27. It is not in dispute that the person(s) concerned were well aware or conversant with the issues involved including the prescribed period of limitation for taking up the matter by way of filing a special leave petition in this Court. They cannot claim that they have a separate period of limitation when the Department was possessed with competent persons familiar with court proceedings. In the absence of plausible and acceptable explanation, we are posing a question why the delay is to be condoned mechanically merely because the Government or a wing of the Government is a party before us. 28. Though we are conscious of the fact that in a matter of condonation of delay when there was no gross negligence or deliberate inaction or lack of bonafide, a liberal concession has to be adopted to advance substantial justice, we are of the view that in the facts and circumstances, the Department cannot take advantage of various earlier decisions. The claim on
5 account of impersonal machinery and inherited bureaucratic methodology of making several notes cannot be accepted in view of the modern technologies being used and available. The law of limitation undoubtedly binds everybody including the Government. 29. In our view, it is the right time to inform all the government bodies, their agencies and instrumentalities that unless they have reasonable and acceptable explanation for the delay and there was bonafide effort, there is no need to accept the usual explanation that the file was kept pending for several months/years due to considerable degree of procedural red-tape in the process. The government departments are under a special obligation to ensure that they perform their duties with diligence and commitment. Condonation of delay is an exception and should not be used as an anticipated benefit for government departments.
The law shelters everyone under the same light and should not be swirled for the benefit of a few. 30. Considering the fact that there was no proper explanation offered by the Department for the delay except mentioning of various dates, according to us, the Department has miserably failed to give any acceptable and cogent reasons sufficient to condone such a huge delay. Accordingly, the appeals are liable to be dismissed on the ground of delay.”
8. Recently, a Division Bench of the Hon’ble Supreme Court in the matter of State of Madhya Pradesh v. Ramkumar Choudhary, 2024 INSC 932, while considering the delay, issued some directions and observed as follows:-
“5. The legal position is that where a case has been presented in the Court beyond limitation, the petitioner has to explain the Court as to what was the "sufficient cause" which means an adequate and enough reason which prevented him to approach the Court within limitation. In Majji Sannemma v. Reddy Sridevi, 2021 SCC Online SC 1260, it was held by this Court that even though limitation may harshly affect the rights of a party, it has to be applied with all its rigour when prescribed by statute. A reference was also made to the decision of this Court in Ajay Dabra v. Pyare Ram, 2023 SCC Online 92 wherein, it was held as follows:
"13. This Court in the case of Basawaraj v. Special Land Acquisition Officer [(2013) 14 SCC 81] while
6 rejecting an application for condonation of delay for lack of sufficient cause has concluded in Paragraph 15 as follows:
“15. The law on the issue can be summarised to the effect that where a case has been presented in the court beyond limitation, the applicant has to explain the court as to what was the “sufficient cause” which means an adequate and enough reason which prevented him to approach the court within limitation.
In case a party is found to be negligent, or for want of bona fide on his part in the facts and circumstances of the case, or found to have not acted diligently or remained inactive, there cannot be a justified ground to condone the delay. No court could be justified in condoning such an inordinate delay by imposing any condition whatsoever. The application is to be decided only within the parameters laid down by this Court in regard to the condonation of delay. In case there was no sufficient cause to prevent a litigant to approach the court on time condoning the delay without any justification,
putting
any
condition whatsoever, amounts to passing an order in violation of the statutory provisions and it tantamounts to showing utter disregard to the legislature.”
14. Therefore, we are of the considered opinion that the High Court did not commit any mistake in dismissing the delay condonation application of the present appellant." Thus, it is crystal clear that the discretion to condone the delay has to be exercised judiciously based on facts and circumstances of each case and that, the expression 'sufficient cause' cannot be liberally interpreted, if negligence, inaction or lack of bona fides is attributed to the party. 5.1. In Union of India v. Jahangir Byramji Jeejeebhoy (D) through his legal heir, 2024 INSC 262, wherein, one of us (J.B.Pardiwala, J) was a member, after referring to various decisions on the issue, it was in unequivocal terms observed by this Court that delay should not be excused as a matter of generosity and rendering substantial justice is not to cause prejudice to the opposite party. The relevant passage of the same is profitably extracted below:
7
“24. In the aforesaid circumstances, we made it very clear that we are not going to look into the merits of the matter as long as we are not convinced that sufficient cause has been made out for condonation of such a long and inordinate delay. 25.
It hardly matters whether a litigant is a private party or a State or Union of India when it comes to condoning the gross delay of more than 12 years. If the litigant chooses to approach the court long after the lapse of the time prescribed under the relevant provisions of the law, then he cannot turn around and say that no prejudice would be caused to either side by the delay being condoned. This litigation between the parties started sometime in
1981. We are in 2024. Almost 43 years have elapsed. However, till date the respondent has not been able to reap the fruits of his decree. It would be a mockery of justice if we condone the delay of 12 years and 158 days and once again ask the respondent to undergo the rigmarole of the legal proceedings. 26. The length of the delay is a relevant matter which the court must take into consideration while considering whether the delay should be condoned or not. From the tenor of the approach of the appellants, it appears that they want to fix their own period of limitation for instituting the proceedings for which law has prescribed a period of limitation. Once it is held that a party has lost his right to have the matter considered on merits because of his own inaction for a long, it cannot be presumed to be non-deliberate delay and in such circumstances of the case, he cannot be heard to plead that the substantial justice deserves to be preferred as against the technical considerations. While considering the plea for condonation of delay, the court must not start with the merits of the main matter. The court owes a duty to first ascertain the bona fides of the explanation offered by the party seeking condonation. It is only if the sufficient cause assigned by the litigant and the opposition of the other side is equally balanced that the court may bring into aid the merits of the matter for the purpose of condoning the delay. 27.
We are of the view that the question of limitation is not merely a technical consideration. The rules of limitation are based on the principles of sound public policy and principles of equity. We should not keep the ‘Sword of Damocles’ hanging over the head of the respondent for indefinite
8 period of time to be determined at the whims and fancies of the appellants. xxx xxx xxx
34. In view of the aforesaid, we have reached to the conclusion that the High Court committed no error much less any error of law in passing the impugned order. Even otherwise, the High Court was exercising its supervisory jurisdiction under Article 227 of the Constitution of India. 35. In a plethora of decisions of this Court, it has been said that delay should not be excused as a matter of generosity. Rendering substantial justice is not to cause prejudice to the opposite party. The appellants have failed to prove that they were reasonably diligent in prosecuting the matter and this vital test for condoning the delay is not satisfied in this case. 36. For all the foregoing reasons, this appeal fails and is hereby dismissed. There shall be no order as to costs.” Applying the above legal proposition to the facts of the present case, we are of the opinion that the High Court correctly refused to condone the delay and dismissed the appeal by observing that such inordinate delay was not explained satisfactorily, no sufficient cause was shown for the same, and no plausible reason was put forth by the State. Therefore, we are inclined to reject this petition at the threshold. 6. At the same time, we cannot simply brush aside the delay occurred in preferring the second appeal, due to callous and lackadaisical attitude on the part of the officials functioning in the State machinery.
Though the Government adopts systematic approach in handling the legal issues and preferring the petitions/ applications/ appeals well within the time, due to the fault on the part of the officials in merely communicating the information on time, huge revenue loss will be caused to the Government exchequer. The present case is one such case, wherein, enormous delay of 1788 days occasioned in preferring the second appeal due to the lapses on the part of the officials functioning under the State, though valuable Government lands were involved. Therefore, we direct the State to streamline the machinery touching the legal issues, offering legal opinion, filing of cases before the Tribunal / Courts, etc., fix the responsibility on the officer(s) concerned, and penalize the officer(s), who is/are
9 responsible for delay, deviation, lapses, etc., if any, to the value of the loss caused to the Government. Such direction will have to be followed by all the States scrupulously. 7. There is one another aspect of the matter which we must not ignore or overlook. Over a period of time, we have noticed that whenever there is a plea for condonation of delay be it at the instance of a private litigant or State the delay is sought to be explained right from the time, the limitation starts and if there is a delay of say 2 years or 3 years or 4 years till the end of the same. For example if the period of limitation is 90 days then the party seeking condonation has to explain why it was unable to institute the proceedings within that period of limitation. What events occurred after the 91st day till the last is of no consequence. The court is required to consider what came in the way of the party that it was unable to file it between the 1st day and the 90th day. It is true that a party is entitled to wait until the last day of limitation for filing an appeal.
But when it allows the limitation to expire and pleads sufficient cause for not filing the appeal earlier, the sufficient cause must establish that because of some event or circumstance arising before the limitation expired it was not possible to file the appeal within time. No event or circumstance arising after the expiry of limitation can constitute such sufficient cause. There may be events or circumstances subsequent to the expiry of limitation which may further delay the filing of the appeal. But that the limitation has been allowed to expire without the appeal being filed must be traced to a cause arising within the period of limitation. (See: Ajit Singh Thakur Singh and Another v. State of Gujarat, AIR 1981 SC 733).”
9. Having considered the submissions made by learned counsel for the petitioner, facts and circumstances of the case as emerges from the documents annexed with the present writ petition and also in the light of aforementioned judgments of the Hon’ble Supreme Court in the matters of Postmaster General (supra) and Ramkumar Choudhary (supra), I do not find any jurisdictional error or perversity in the impugned order dated 04.04.2024 passed by the Chhattisgarh Board of Revenue, Bilaspur. It is also to be noticed here that the impugned order passed by the Board of Revenue is on 04.04.2024, however, the
10 petitioner has filed the present writ petition after about two years, that is on 25.07.2026, which is also suffered from delay and laches. 10. Accordingly, the writ petition fails and is dismissed. Sd/- (Ravindra Kumar Agrawal) JUDGE Sumit