CNR: KAHC010278102025 NC: 2026:KHC:37932-DB CCC No. 479 of 2025
IN THE HIGH COURT OF KARNATAKA AT BENGALURU
DATED THIS THE 23RD DAY OF JULY, 2026
PRESENT
THE HON'BLE MR. VIBHU BAKHRU, CHIEF JUSTICE
AND
THE HON'BLE MRS. JUSTICE K.S. HEMALEKHA
CIVIL CONTEMPT PETITION NO. 479 OF 2025
BETWEEN:
1.
NAGARJUNA GREEN RIDGE APARTMENT OWNERS' ASSOCIATION REPRESENTED BY AUTHORISED SIGNATORY MR. SHANTANU PANDEY S/O SHRI B.P. PANDEY AGED ABOUT 48 YEARS RESIDING AT F-603 NAGARJUNA GREENRIDGE APARMENTS HSR LAYOUT SECTOR-2 BENGALURU - 560 102
CONSTITUTED VIDE DEED OF DECLARATION REGISTERED UNDER KARNATAKA APARTMENT OWNERSHIP ACT, 1972 REGISTERED BEFORE BOMMANAHALLI SENIOR SUB REGISTRAR BEARING DOCUMENT NO. BNG(U)-BMH-7062-2007-08
HAVING ADDRESS 15/2, 19TH MAIN, 27TH CROSS SECTOR 2, HSR LAYOUT BENGALURU 560 102 …COMPLAINANT (BY SRI KARTIKEYA KHANNA, ADVOCATE)
Digitally signed by AMBIKA H B Location: High Court of Karnataka
- 2 -
HC-KAR
CNR: KAHC010278102025 NC: 2026:KHC:37932-DB CCC No. 479 of 2025
AND:
1.
AMJED KHAN S/O P. NAZER KHAN AGED ABOUT MAJOR SITE NO.6, RAGHAVENDRA NILAYA 19TH MAIN, SECTOR 2 HSR LAYOUT BENGALURU - 560 102
ALSO AT NO.3, 2ND CROSS 24TH MAIN HAMILTON BAILEY HOSPITAL BENGALURU - 560 102
2.
MR. TUSHAR GIRINATH THE CHIEF COMMISSIONER BRUHAT BENGALURU MAHANAGARA PALIKE (BBMP) N.R. SQUARE, BANGALORE - 560 002
3.
MRS. RAMYA S ZONAL COMMISSIONER BOMMANAHALLI ZONE, BBMP BRUHAT BENGALURU MAHANAGARA PALIKE (BBMP) HSR LAYOUT, BDA COMPLEX BANGALORE - 560 102
4.
MR. NAGESH S/O MR. MARAPPA ADDITIONAL DIRECTOR OF TOWN PLANNING (ADTP) BOMMANAHALLI SUB-DIVISION, BBMP BRUHAT BENGALURU MAHANAGARA PALIKE (BBMP) HSR LAYOUT BDA COMPLEX BANGALORE - 560 102 …ACCUSED (SRI V. SRINIVAS, ADVOCATE FOR ACCUSED No.1 & SRI K.S. MALLIKARJUNA REDDY, ADVOCATE FOR ACCUSED Nos.2 TO 4)
THIS CCC IS FILED UNDER ARTICLE 215 OF THE CONSTITUTION OF INDIA READ WITH SECTIONS 11 AND 12 OF
- 3 -
HC-KAR
CNR: KAHC010278102025 NC: 2026:KHC:37932-DB CCC No. 479 of 2025
THE CONTEMPT OF COURTS ACT, 1971, PRAYING TO PUNISH THE ACCUSED FOR CIVIL CONTEMPT OF COURT FOR VIOLATION OF THE ORDER OF THIS HON'BLE COURT DATED 16.12.2024 PASSED IN W.P. NO.27433/2024 AT ANNEXURE-A & ETC.
THIS PETITION, COMING ON FOR HEARING, THIS DAY,
ORDER WAS MADE THEREIN AS UNDER:
CORAM: HON'BLE MR. VIBHU BAKHRU, CHIEF JUSTICE and HON'BLE MRS. JUSTICE K.S. HEMALEKHA
ORAL ORDER
(PER: HON'BLE MR. VIBHU BAKHRU, CHIEF JUSTICE)
1. Accused No.1 is found guilty of willful disobedience of the
order dated 16.12.2024 passed in Writ Petition No.27433/2024 (LB-BMP), the operative part of which reads as under: a. The petition stands disposed of with liberty to the fourth respondent to call in question the Provisional and Confirmation Orders dated 07.10.2024 and 25.10.2024 respectively in the appeal under Section 253 of the BBMP Act. b. The fourth respondent will be at liberty to file such appeal within a period of six [6] weeks from today and the Appellate Authority, if the fourth respondent files such appeal, is called upon to decide the appeal on merits at the earliest and in any event before
30.05.2025. c. The submission that the fourth respondent will not continue with the construction until the disposal of the appeal, is taken on record as an undertaking for due compliance and the authorities are also directed not take coercive measures against the construction. - 4 -
HC-KAR
CNR: KAHC010278102025 NC: 2026:KHC:37932-DB CCC No. 479 of 2025
d. It is needless to observe that if the petitioner can make out a right for impleadment in the appeal, if filed, will be at such liberty. 2. It is apparent from the above that the Court had restrained the concerned authorities from not taking any coercive measures in view of the undertaking given by the accused that he will not continue further construction. 3. Accused No.1 has since violated the said undertaking and continued the construction activities. It is also noted that he had continued the same even during the course of the present proceedings. 4. Accused No.1 pleaded guilty to the charges framed on
03.07.2026. 5. Although accused No.1 has tendered his apology, the affidavit furnished also seeks to explain why he deliberately violated the order. According to him, the same was, inter alia for the reason that the bank had insisted that the loan amounts would be released to him strictly in accordance with the stage of construction. Therefore, if the work was stopped, the loan facility
- 5 -
HC-KAR
CNR: KAHC010278102025 NC: 2026:KHC:37932-DB CCC No. 479 of 2025
may have been recalled. This also indicates that the accused has taken a calculated decision to disobey the orders of the court. We are also unable to accept that the accused is genuinely remorseful or repentant. 6. Considering the given circumstances, we sentence accused No.1 to a simple imprisonment for a period of 48 hours. 7.
The Registrar General shall issue necessary warrants. 8. The complaint is disposed of. 9. The pending interlocutory applications also stand disposed of. Sd/- (VIBHU BAKHRU) CHIEF JUSTICE
Sd/- (K.S. HEMALEKHA) JUDGE