HC-KAR NC: 2026:KHC:30350 WP No. 18051 of 2026
IN THE HIGH COURT OF KARNATAKA AT BENGALURU DATED THIS THE 19TH DAY OF JUNE 2026 BEFORE THE HON'BLE MR. JUSTICE B M SHYAM PRASAD WRIT PETITION NO. 18051 OF 2026 (LB-BMP)
BETWEEN:
1.
P N SHARATH S/O K.N. PRAHALADA, AGED ABOUT 42 YEARS
2.
P.N. SANTOSH S/O K.N. PRAHALADA, AGED ABOUT 35 YEARS
BOTH ARE RESIDING AT NO.62/1, 4TH MAIN ROAD, CHAMARAJPET, BANGALORE-560018
…PETITIONERS (BY SRI. SRINIVAS V., ADVOCATE) AND:
1.
THE COMMISSIONER CENTRAL BANGALORE CITY CORPORATION 10TH FLOOR, MULTIPURPOSE P.U. BUILDING, MAHATMA GANDHI ROAD, BENGALURU -560 001
Digitally signed by VANAMALA N Location: HIGH COURT OF KARNATAKA
- 2 -
HC-KAR NC: 2026:KHC:30350 WP No. 18051 of 2026
2.
THE ASSISTANT EXECUTIVE ENGINEER CENTRAL BANGALORE CITY CORPORATION 2ND MAIN ROAD, NANJAMBA AGRAHARA, T.R. MILL ROAD CHAMARAJPET, BANGALORE -560 018
3.
THE ASSISTANT DIRECTOR TOWN PLANNING BRUHATH BENGALURU MAHANAGARPALIKE WEST ZONE BASHYAM PARK, SHESHADRIPURAM BENGALURU-560 020
4.
THE ASSISTANT ENGINEER TOWN PLANNING (WEST) OFFICE OF THE ASSISTANT DIRECTOR TOWN PLANNING BRUHATH BENGALURU MAHANAGAR PALIKE WEST ZONE BASHYAM PARK, SHESHADRIPURAM BENGALURU-560 020
…RESPONDENTS (BY SRI. PAWAN KUMAR, ADVOCATE)
THIS WP IS FILED UNDER ARTICLES 226 AND 227 OF THE CONSTITUTION OF INDIA PRAYING TO QUASH THE CONFIRMATION DATED 11-01-2023 BEARING NO NAM. SA. NI. NA. YO. (PA)- 1/CO/38A/22-23 PASSED UNDER 248(3), OF THE BBMP ACT BY THE RESPONDENT NO 3 AND 4 VIDE ANNEXURE F TO THE WRIT PETITION.
THIS PETITION, COMING ON FOR ORDERS, THIS DAY, ORDER WAS MADE THEREIN AS UNDER:
- 3 -
HC-KAR NC: 2026:KHC:30350 WP No. 18051 of 2026
CORAM: HON'BLE MR. JUSTICE B M SHYAM PRASAD
ORAL ORDER
The petitioners have called in question Confirmation Order dated 11.01.2023 [Annexure - F] under Section 248(3) of the Bruhat Bengaluru Mahanagara Palike Act, 2020 [for short, 'the BBMP Act'] and the notice issued on 08.06.2026 for demolition in terms of the Confirmation Order [Annexure - G]. Mr. V. Srinivas, the learned counsel for the petitioners, and Mr. Pawan Kumar, a learned Standing counsel who accepts notice for the respondents, are heard for final disposal of the petition with the petitioners' principal grievance being that the proceedings under Section 248 of the BBMP Act are concluded even without they being served with a copy of either the Provisional Order or the Confirmation Order.
- 4 -
HC-KAR NC: 2026:KHC:30350 WP No. 18051 of 2026
2. Mr. V. Srinivas, arguing in support of the petitioners' request for an interim order, submits that the respondents cannot demolish a completed structure without extending opportunities as contemplated under Section 248 of the BBMP Act, and because the Confirmation Order and the preceding Provisional Order are without notice, the lack of opportunity is indisputable. The learned counsel next argues that the proceedings are concluded even without inspection of the property.
3. Inarguably, the petitioners have an alternative remedy under Section 250 of the Greater Bengaluru Governance Act, 2024. The petitioners can avail this remedy subject to showing cause for condonation of delay. If the petitioners do avail such remedy, the Appellate Authority will have to call for records and examine whether there must be any interference on the grounds urged by the petitioners.
- 5 -
HC-KAR NC: 2026:KHC:30350 WP No. 18051 of 2026
4. When such remedy is available to the petitioners, this Court is not inclined to interfere, and this Court is of the opinion that the petition must be
disposed of reserving liberty to the petitioners to avail alternative remedy calling upon the Appellate Authority, if the petitioners avail such remedy, to consider the question of delay as well in the circumstances relied upon by the petitioners. At this stage, Mr. V. Srinivas submits that there is imminent threat of demolition, and this Court must ensure that demolition is put off until the Appellate Authority considers the petitioners' request for condonation of delay.
5. Mr. Pawan Kumar is heard on this aspect as well. This Court is disposing of this petition relegating the petitioners to alternative remedy and if this remedy is to be meaningful, there cannot be any precipitation. The precipitation shall not be until the Appellate Authority considers both the application for
- 6 -
HC-KAR NC: 2026:KHC:30350 WP No. 18051 of 2026
condonation of delay and interim stay by a reasoned
order provided the petitioners avail such alternative remedy within six [6] weeks from today. The petition stands disposed of accordingly. It is needless to observe that all questions are left open to be considered by the Appellate Authority.
Sd/- (B M SHYAM PRASAD) JUDGE
RB