2026:JHHC:489
1
IN THE HIGH COURT OF JHARKHAND AT RANCHI Contempt Case (Civil) No. 587 of 2024
M/s. Adarsh Construction, having its office at Pratap Nagar, Naisarai, Ramgarh Cantonment, Ramgarh, through its partner Ajit Narayan Singh
... … Petitioner Versus
1. The State of Jharkhand
2. Mr. Manish Ranjan, Managing Director, Jharkhand State Building Construction Corporation Limited, Ranchi
3. Mr. Sanjay Kujur, Manager-cum-Executive Engineer, Jharkhand State Building Construction Corporation Limited, Ranchi
4. Mr. Ajay Kumar Singh, Principal Secretary, Department of Health, Medical Education and Family Welfare, Government of Jharkhand, Ranchi
5. Mr. Arava Rajkamal, Secretary, Building Construction Department, Project Bhawan, Dhurwa, Ranchi
... … Opposite Parties
CORAM: HON'BLE MR. JUSTICE RAJESH SHANKAR -----
For the Petitioner
: Mr. Abhijeet Kumar Singh, Advocate
For the Opp. Party Nos.1, 4 & 5 : Mr. Abhilash Kumar, AC to GP-II
For the Opp. Party Nos. 2 & 3 : Ms. Khalida Haya Rashmi, Advocate
-----
08/09.01.2026 The present contempt petition has been filed for initiating a contempt proceeding against the contemnors/opposite parties alleging wilful violation of the order dated 16.11.2022 passed in W.P.(C) No. 3701 of 2022.
2.
Learned counsel for the petitioner submits that the
order dated 16.11.2022 passed in W.P.(C) No. 3701 of 2022 has now been complied by the opposite parties.
3. Considering the said submission, there is no need to further proceed in the contempt petition. The contempt proceeding as against the opposite parties is hereby dropped.
4. The contempt petition is accordingly disposed of.
(Rajesh Shankar, J.) January 09, 2026 Manish Uploaded on 09.01.2026