[2026:RJ-JP:6188] HIGH COURT OF JUDICATURE FOR RAJASTHAN BENCH AT JAIPUR S.B. Civil Writ Petition No. 20373/2025
1. Pramod Kaviya S/o Shri Sabal Dan Kavya, Aged About 40 Years, R/o A-111, Tara Nagar-A, Karni Path, Jhotwara, Jaipur And Also At Gram-Gumanpura, Near Maha Maya Mandir.
2. Ashok Kaviya S/o Shri Sabal Dan Kaviya, Aged About 39 Years, R/o A-111, Tara Nagar-A, Karni Path, Jhotwara, Jaipur And Also At Gram-Gumanpura, Near Maha Maya Mandir. ----Petitioners Versus
1. District Collector, District - Sikar.
2. Tehsildar, Village Dantaramgarh, Distt. Sikar.
3. Power Grid Bhadla, Sikar Transmission Line Ltd. Through Its Managing Director, B-9, Qutab Institutional Area, Katwaria Sarai, New Delhi- 110016 Also At Saudamini, Plot No.2, Sector-29, Gurugram Haryana- 122001 ----Respondents For Petitioner(s) : Mr. Rishabh Khandelwal For Respondent(s) : Mr. Jai Prakash Gupta Ms. Preeti Soni for Mr. V.D. Gathala, AGC HON'BLE MR. JUSTICE GANESH RAM MEENA
Order 10/02/2026
1. The learned counsel for the petitioners submits that the respondents are laying the transmission line over the Khatedari land of the petitioners, without notice and compensation to them for the alleged damage.
2. The learned counsel for the respondents submits that the petitioners are entitled for compensation in accordance with
[2026:RJ-JP:6188] (2 of 2) [CW-20373/2025] law and for that, the respondents are required to make measurement of the land, but the petitioners are not allowing to the respondents authorities to measure the land so as to compute the compensation.
3.
Learned counsel for the petitioners submits that the petitioners are ready to cooperate with the respondents authorities, as regards the measurement of the land.
4. Heard.
5. Considered the submissions made by the learned counsels appearing for the respective parties.
6. The respondents authorities shall proceed for measurement of the land and shall compute the compensation and same be paid to the petitioners, as early as possible.
7. The respondents authorities before going for measurement of the land, shall also issue notice to the petitioners for measurement.
8. Accordingly, this writ petition is disposed of.
9. The stay application and pending application, if any, also stand disposed.
(GANESH RAM MEENA),J ARTI SHARMA /21