$~36 * IN THE HIGH COURT OF DELHI AT NEW DELHI # CNR No. DLHC010457542026 + O.M.P.(MISC.)(COMM.) 758/2026 & I.A. 26433/2026
HERO SOLAR ENERGY PVT LTD
.....Petitioner Through: Mr. Yash Srivastava, Ms. Satakshi Sood, Mr. Ayushman Das and Ms. Naimishi Verma, Advocates.
versus
M/S INDRAPRASTHA POWER GENERATION COMPANY LTD .....Respondent Through: Mr. Chandra Prakash and Ms. Aindri Saha, Advocates.
CORAM:
HON'BLE MR. JUSTICE TUSHAR RAO GEDELA
O R D E R %
24.09.2026
O.M.P.(MISC.)(COMM.) 758/2026
1. This is a petition under Section 29A (5) of the Arbitration & Conciliation Act, 1996 seeking extension of mandate of the Arbitral Tribunal by another nine months with effect from 17.09.2026 when the mandate of the Arbitral Tribunal had expired.
2. Issue notice.
3. Notice is accepted by Mr. Chandra Prakash, learned counsel appearing on behalf of the respondent, who has no objection in case the petition is allowed.
4. Accordingly, in view of the aforesaid statement, the petition is allowed and the mandate of the Arbitral Tribunal is extended for a further period of nine months with effect from 17.09.2026. This is a digitally signed order. The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above. The Order is downloaded from the DHC Server on 29/09/2026 at 12:08:38
5. In view of the above, the present petition is disposed of alongwith pending application.
TUSHAR RAO GEDELA, J SEPTEMBER 24, 2026 kct