SWAPAN KUAMR CHAKRABORTY v. WEST BENGAL ELECTRICITY DISTRIBUTION COMPANY LIMITED AND ORS.
WPA/8797/2026 · 2026-05-14
Ravi Krishan Kapur
body2026
DailyLaw.ai
[ 2026 DAILYLAW 19648 (CAL) · dailylaw.ai ]
DailyLaw.ai
[ 2026 DAILYLAW 19648 (CAL) · dailylaw.ai ]
Judgment text
Extracted from the PDF above. The PDF is authoritative.
5 14.05.2026 Ct. No.07 J.Das IN THE HIGH COURT AT CALCUTTA CONSTITUTIONAL WRIT JURISDICTION APPELLATE SIDE
WPA 8797 of 2026
Swapan Kuamr Chakraborty Vs. West Bengal Electricity Distribution Company Limited and Ors.
Mr. Don Sen
Mr. Haradhan Mondol
…For the petitioner
Mr. Debjit Mukherjee
…For the WBSEDCL
Ms. Somoshree Saha
Ms. Chandana Maitra
…For the respondent nos.4 to 6
1. The grievance of the petitioner is directed against inaction of the WBSEDCL in providing a separate electricity connection to the premises of the petitioner.
2. Pursuant to an order dated 30 April 2026, it is submitted on behalf of the WBSEDCL that there are civil disputes by and between the petitioner and the private respondents which ought to be adjudicated by the concerned District Magistrate having jurisdiction.
3. There is also a question of installation of an electricity pole on land which admittedly does not belong to the petitioner.
2
4. In view of the above, WPA 8797 of 2026 stands disposed of by directing the concerned District Magistrate having jurisdiction to decide the grievance of the petitioner as to whether it is feasible or practical to install a separate connection at the subject premises.
5. It is needless to mention that in carrying out the above exercise, the District Magistrate is directed to give notice to the petitioner, private respondents as well as the WBSEDCL. The above exercise is to be completed within eight weeks from the date of passing of this order.
(Ravi Krishan Kapur, J.)