Sbw 22-asia-1905-2026.doc IN THE HIGH COURT OF JUDICATURE AT BOMBAY CIVIL APPELLATE JURISDICTION INTERIM APPLICATION NO.1905 OF 2026 IN COMMERCIAL ARBITRATION APPEAL (ST) NO.1923 OF 2026 Model Infra Corporation Ltd. … Appellant V/s. Uday V. Meha (Trading as Amisha Metal & Alloy Industries) … Respondent
Mr. Madhur Baya a/w Ms. Vaishnavi Agrawal for the Appellant. Mr. Paresh Thakur a/w Mr. Yash Tated for the Respondents.
CORAM : A. S. GADKARI AND KAMAL KHATA, JJ. DATE : 6th October, 2026. P.C.:- 1) This is an Application for condonation of delay of 20 days in preferring Commercial Arbitration Appeal (ST) No.1923 of 2026, against the impugned Order dated 8th September, 2025. 2) Learned Advocate appearing for the Respondent vehemently opposed the Application and submitted that, the delay has been wrongly calculated and as a matter of fact, the delay is of 76 days. 1/2 SANDHYA BHAGU WADHWA Digitally signed by SANDHYA BHAGU WADHWA Date: 2026.10.14 15:05:40 +0530
Sbw 22-asia-1905-2026.doc 3) However, perusal of Application indicates that, sufficient cause is made out for condonation of the said delay. 4) In view thereof, the delay is condoned and the Application is allowed in terms of prayer clause (a).
(KAMAL KHATA, J.) (A.S. GADKARI, J.) 2/2