Research › Search › Judgment

Bombay High Court · body

2026 DAILYLAW 1777 (BOM)

M/S AMISHA BUILDCON PVT LTD v. JIDNYASA CO OPERATIVE HOUSING SOCIETY

ARP/139/2026 · 2026-08-21

body2026

Judgment text

Extracted from the PDF above. The PDF is authoritative.

918-ARP-139-26.DOC IN THE HIGH COURT OF JUDICATURE AT BOMBAY CIVIL APPELLATE JURISDICTION ARBITRATION PETITION NO. 139 OF 2026 M/s Amisha Buildcon Pvt Ltd ...Petitioner Versus Jidnyasa Co Operative Housing Society ...Respondent ---------- Mr. Sumeet Savda a/w Ms Priyal Gandhi i/b SHS Chambers for Petitioner. Mr. Robin Thomas i/b Mr. Mihir Joshi for Respondent. ---------- CORAM: S. M. MODAK, J. DATED: 21st AUGUST, 2026 P.C. 1. Heard learned Advocate for the Petitioner. 2. This is an application for an extension of a period for publication of the award. It is submitted that the Respondent has consented. 3. My attention is invited to the mail sent by the learned Arbitrator at page 33. Learned Arbitrator has requested an extension of six week till the end of July 2026. That period is already over. Orally it is submitted that the period be extended till December 2026, as the matters are closed for pronouncement of the award. Meera Jadhav MEERA MAHESH JADHAV Digitally signed by MEERA MAHESH JADHAV Date: 2026.08.24 13:54:12 +0530 918-ARP-139-26.DOC 4. Hence, the period for declaration of the award is extended till 31st December 2026. Let the learned Arbitrator to make an endeavour to declare the award till that time 5. Petition accordingly stands disposed of. (S. M. MODAK, J.) Meera Jadhav