Research › Search › Judgment

Bombay High Court · body

2026 DAILYLAW 17641 (BOM)

M/S SHRI SAISHWAR INFRA v. THE MAHARASHTRA STATE ELECTRICITY DISTRIBUTION CO. LTD.

IA/7462/2026 · 2026-10-09

Public Interest Litigationbody2026

Judgment text

Extracted from the PDF above. The PDF is authoritative.

66-IA-7462-2026.docx IN THE HIGH COURT OF JUDICATURE AT BOMBAY CIVIL APPELLATE JURISDICTION INTERIM APPLICATION NO. 7462 OF 2026 IN FIRST APPEAL NO. 2354 OF 2008 M/s. Shri Saishwar Infra … Appellants/Applicants Vs. The Maharashtra State … Respondents Electricity Distribution Co. Ltd. WITH CIVIL APPLICATION NO. 4099 OF 2009 INTERIM APPLICATION NO. 7463 OF 2026 IN FIRST APPEAL NO. 2354 OF 2008 Mr. S. S. Redkar a/w. Mr. Yogesh Rawool for the Applicant. Ms. A.R.S. Baxi - for the Appellant (Original Defendant). CORAM : GAURI GODSE, J. DATE : 9th OCTOBER 2026 ORDER : Interim Application No. 7462 of 2016 and Interim Application No. 7463 of 2026. 1. Both these interim applications are filed to add the subsequent purchaser as respondent no. 2 in the first appeal. By consent both the applications are allowed in terms of prayer clause (b). 1/2 rrpillai RAJESHWARI RAMESH PILLAI Digitally signed by RAJESHWARI RAMESH PILLAI Date: 2026.10.12 14:25:23 +0530 66-IA-7462-2026.docx 2. Learned counsel for the appellant shall carry out amendment in the first appeal. 3. Learned counsel for the added respondents waives notice of the first appeal. 4. The interim applications are disposed of in the aforesaid terms. [GAURI GODSE, J.] 2/2