2026:JHHC:18176-DB 1
IN THE HIGH COURT OF JHARKHAND AT RANCHI
W.P. (C) No. 3162 of 2021
Vaishnavi Hospital, having its registered office at Bypass Road, near Baadshahi Paeen, P.O. & P.S.-Jakariyapur, District-Patna (Bihar), through its partner, Prince Kumar Tiwari, S/o Late Dhruv Deo Tiwari, R/o Krishna Niketan School Road, near Baadshahi Paeen, Rohni Nagar, P.O. & P.S.-Jakariyapur, District-Patna (Bihar)
….. Petitioner
Versus
1. The State of Jharkhand, through the Chief Secretary, Ranchi
2. The Principal Secretary, Department of Health, Medical Education and Family Welfare, Government of Jharkhand, Ranchi
3. The Superintendent of Labour, Dumka
4. The Dean/Principal, Phulo-Jhano Medical College, Dumka
5. The Superintendent, Phulo-Jhano Medical College Hospital, Dumka
6. Birsa Security & Service Settlement, through its authorized signatory, Mr. Nagesh Kumar Singh, Birsa Chowk, Ray Colony, Station Road, Hatia, P.O.-Hatia, P.S.-Jagannathpur, District-Ranchi
….. Respondents
-----
CORAM
HON’BLE THE CHIEF JUSTICE
HON’BLE MR. JUSTICE RAJESH SHANKAR
----- For the Petitioner: None For the State:
Mr. Vibhor Mayank, A.C. to A.G.
-----
08/22.06.2026
1. None for the petitioner.
2. Mr. Vibhor Mayank, learned A.C. to A.G., appears for the State.
3. This writ petition challenges Memo No. 777 dated 15.04.2021 cancelling MoU dated 31.03.2021 with the petitioner for supply of human resources on outsourcing basis.
4. Mr. Vibhor Mayank submits that the contractual period was only for one year with a renewal clause.
5. There was no interim relief granted in this matter and pursuant to the cancellation order dated 15.04.2021, the same work was awarded to the respondent No. 6. By now, the term of the contract must have expired. In any event, at this advanced stage, it would be difficult to put the clock back and award the work to the petitioner assuming that it makes out any case for award of the
2026:JHHC:18176-DB 2
same. That is possibly the reason why the petitioner is not having much interest in pursuing this writ petition.
6. Accordingly, we dispose of the present writ petition, but with liberty to the petitioner to explore the possibility of filing a civil suit seeking damages etc. However, we clarify that we have not examined the merits of the matter and therefore all contentions of the parties are left open.
7. The present writ petition is accordingly disposed of with liberty in the above terms without any order for costs.
(M. S. SONAK, C.J.)
(RAJESH SHANKAR, J.) 22.06.2026 Satish/Vikas/