Research › Search › Judgment

High Court of Delhi · body

2026 DAILYLAW 15573 (DEL)

POWER GRID CORPORATION OF INDIA LIMITED v. SPML INFRA LIMITED

O.M.P.(MISC.)(COMM.)/628/2026 · 2026-08-12

Avneesh Jhingan

body2026

Judgment text

Extracted from the PDF above. The PDF is authoritative.

$~66 * IN THE HIGH COURT OF DELHI AT NEW DELHI # CNR No. DLHC010369142026 + O.M.P.(MISC.)(COMM.) 628/2026, I.A. 21681/2026 & I.A. 21682/2026 POWER GRID CORPORATION OF INDIA LIMITED .....Petitioner Through: Mr. S B Upadhyay, Sr. Adv. with Mr. Pranay Kishore Mishra & Mr. B K Pardeep, Advs. versus SPML INFRA LIMITED .....Respondent Through: Mr. Sourav Dutta, Adv. CORAM: HON'BLE MR. JUSTICE AVNEESH JHINGAN O R D E R % 12.08.2026 1. This petition is filed under Section 29A of the Arbitration and Conciliation Act, 1996 seeking extension of period for concluding the arbitration proceedings. 2. Learned counsel for the respondent has no serious objection to the prayer made. 3. In view of the above, the time period for conclusion of the proceedings is extended by nine months w.e.f. 04.08.2026 as prayed for. 4. This petition is disposed of in the aforesaid terms. All pending applications are also disposed of. AVNEESH JHINGAN, J AUGUST 12, 2026 Ch This is a digitally signed order. The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above. The Order is downloaded from the DHC Server on 14/08/2026 at 12:54:04