CONT P No. 693 of 2026 __________ Page1 of 4 IN THE HIGH COURT OF JUDICATURE AT MADRAS DATED: 24-04-2026 CORAM THE HON'BLE MR JUSTICE M.DHANDAPANI CONT P No. 693 of 2026 M/s.ShambhuVengu Yarn Mills P. Ltd.
WEG No.039214340843, No.4/997/3 to 6, Anangur Road, Mettukadai, KallankattuValasu(Po), Kumarapalayam-638 183, rep. by its Authorised Signatory, K.Rajalingam. ..Petitioner(s) Vs
1. Radhakrishnan IAS, The Tamilnadu Power Distribution Corporation Ltd (TNPDCL), 144, Anna Salai, Chennai-600 002 Rep.by its Managing Director. 2. Vinothan, Tamil Nadu Green Energy Corporation Ltd (TNGECL), 144, Anna Salai, Chennai-600 002 Rep. by its Managing Director. 3. S.Mangalanthan, The Chief Engineer/NCES, (TNPDCL) 2nd Floor, 144, Anna Salai, Chennai-600 002. 4. R.Geetha, The Superintending Engineer, The Tamil Nadu Power Distribution Corporation Ltd (TNPDCL), Udumalpet Electricity Distribution Circle, Udumalpet. https://www.mhc.tn.gov.in/judis
CONT P No. 693 of 2026 __________ Page2 of 4
5. G.Dharani, The Superintending Engineer, The Tamil Nadu Power Distribution Corporation Ltd (TNPDCL), Mettur Electricity Distribution Circle, Mettur Dam. ..Contemnor(s) Prayer: Contempt Petition filed under Section 11 of the Contempt of Courts Act, 1971, to punish the respondents for their act of committing Contempt of Court by disobeying the order of this Court dated 22.04.2025 made in WP No.13729 of 2025. For Petitioner(s): Mr.R.S.Pandiyaraj For Contemnor(s): Mr.D.R.Arun Kumar ORDER This Contempt Petition has been filed seeking to punish the respondents for wilful disobedience of the order dated 22.04.2025 passed by this Court in WP No.13729 of 2025. 2. Today, when the matter was taken up for hearing, learned counsel appearing on behalf of the respondents submitted that, the order under contempt has been complied with. https://www.mhc.tn.gov.in/judis
CONT P No. 693 of 2026 __________ Page3 of 4
3. Recording the above submission made by the learned counsel appearing on behalf of the respondents, this Contempt Petition stands closed. 24-04-2026 Index: Yes/No Speaking/Non-speaking order Neutral Citation: Yes/No VEDA To 1.The Tamilnadu Power Distribution Corporation Ltd (TNPDCL), 144, Anna Salai, Chennai-600 002 Rep.by its Managing Director. 2.Tamil Nadu Green Energy Corporation Ltd (TNGECL), 144, Anna Salai, Chennai-600 002 Rep. by its Managing Director. 3.The Chief Engineer/NCES, (TNPDCL) 2nd Floor, 144, Anna Salai, Chennai-600 002. 4.The Superintending Engineer, The Tamil Nadu Power Distribution Corporation Ltd (TNPDCL), Udumalpet Electricity Distribution Circle, Udumalpet. 5.The Superintending Engineer, The Tamil Nadu Power Distribution Corporation Ltd (TNPDCL), Mettur Electricity Distribution Circle, Mettur Dam.
https://www.mhc.tn.gov.in/judis
CONT P No. 693 of 2026 __________ Page4 of 4 M.DHANDAPANI, J. VEDA CONT P No. 693 of 2026 24-04-2026 https://www.mhc.tn.gov.in/judis