M/S MILAN CONSTRUCTION WORKS AND ANOTHER v. PRADIP KUMAR VERMA, SUPERINTENDENT ENGINEER, ELECTRICITY DISTRIBUTION

CAPL/7116/2026 · 2026-10-07

Piyush Agrawal

body2026

Judgment text

Extracted from the PDF above. The PDF is authoritative.

HIGH COURT OF JUDICATURE AT ALLAHABAD CONTEMPT APPLICATION (CIVIL) No. - 7116 of 2026 Court No. - 7 HON'BLE PIYUSH AGRAWAL, J. Heard learned counsel for the applicant(s). Vide order dated 24.07.2026 passed in Writ C No. 27157/2026 filed by the applicant(s), the writ Court directed as under: "Considering the facts and circumstances of the case and without adverting into the merits of the case, the writ petition is disposed off permitting the petitioners to file a fresh representation along with certified copy of this order raising all their grievances before the newly impleaded respondent no.6-Superintendent Engineer, Electricity Distribution Division, Ballia within a period of one month from today. In case, any such representation is filed by the petitioners, the respondent no.6 shall consider and decide the same in accordance with law within a period of one month thereafter from the date he receives the representation of the petitioners." Learned counsel for the applicant(s) submits that a certified copy of the aforesaid order was submitted for compliance before the opposite party(s) on 08.08.2026, but the opposite party(s) has willfully not complied with the order and, thus, has committed civil contempt liable for punishment under Section 12 of the Contempt of Courts Act, 1971. Prima facie, a case of contempt has been made out for punishing the opposite party(s) for willful disobedience of the writ Court order. Versus Counsel for Applicant(s) : Anand Kumar Pandey Counsel for Opposite Party(s) : M/S Milan Construction Works And Another .....Applicant(s) Pradip Kumar Verma, Superintendent Engineer, Electricity Distribution .....Opposite Party(s) However, considering the facts and circumstances of the case, one more opportunity is accorded to the opposite party(s) to comply with the aforesaid order of the writ Court in its letter and spirit within three months from the date of production of a copy of this order. The applicant(s) shall supply a duly stamped registered envelope addressed to the opposite party(s) and another self-addressed stamped envelope to the office within one week from today. The office shall send a copy of this order along with the self-addressed envelope of the applicant(s) with a copy of contempt application to the opposite party(s) within one week thereafter and keep a record thereof. The opposite party(s) shall comply with the directions of the writ Court and intimate the applicant(s) of the order through the self-addressed envelop within a week thereafter. With the aforesaid observations, this application is disposed of at this stage with liberty to the applicant(s) to move a fresh application, if the order is not complied with by the opposite party(s) within the stipulated time as aforementioned. October 8, 2026 Amit Mishra CAPL No. 7116 of 2026 2 (Piyush Agrawal,J.) Digitally signed by :- AMIT KUMAR MISHRA High Court of Judicature at Allahabad