Extracted from the PDF above. The PDF is authoritative.
$~6 * IN THE HIGH COURT OF DELHI AT NEW DELHI + ARB.P. 538/2026
M/S H.R. CONSTRUCTION CO.
.....Petitioner
Through: Ms. Pooja Dua & Mr. S.W. Haider, Advs.
versus
UNION OF INDIA
.....Respondent
Through: Mr. T.P. Singh, Adv.
CORAM:
HON'BLE MR. JUSTICE AVNEESH JHINGAN
O R D E R %
20.07.2026
1. This petition is filed under Section 11 of the Arbitration and Conciliation Act, 1996 (for short „the Act‟) for appointment of an arbitrator.
2. The facts in brief are that the respondent awarded to the petitioner the work of construction of subways, platforms and allied works at Bijwasan on the Delhi-Rewari section of Northern Railway for a contract value of Rs.40,95,75,975.69/- vide Contract Agreement dated 11.09.2018. Clause 64 of the General Conditions of Contract (for short 'GCC‟) provides for disputes resolution through arbitration. Dispute arose between the parties regarding payment of claims. The petitioner invoked arbitration by issuing a notice dated 10.12.2025 under Section 21 of the Act. No arbitral tribunal was constituted hence, the present petition.
3.
Learned counsel for the respondent submits that no reply is required to be filed however, contends that the petition was filed six months after the receipt of the full and final payment wherein an undertaking was not to raise This is a digitally signed order. The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above. The Order is downloaded from the DHC Server on 23/07/2026 at 11:35:57
any further claim. 4. Before proceeding further it would be relevant to quote clause 64 of the GCC:
“64(1) Demand For Arbitration 64.(1)(i) In the event of any dispute or difference between the parties hereto as to the construction or operation of this contract, or the respective rights and liabilities of the parties on any matter in question, dispute or difference on any account or as to the withholding by the Railway of any certificate to which the contractor may claim to be entitled to, or if the Railway fails to make a decision within 120 days, then and in any such case, but except in any of the ''excepted matters" referred to in Clause 63 of these Conditions, the contractor, after 120 days but within 180 days of his presenting his final claim on disputed matters shall demand in writing that the dispute or difference be referred to arbitration. 64.(1)(ii) The demand for arbitration shall specify the matters which are in question, or subject of the dispute or difference as also the amount of claim item-wise. Only such dispute(s)or difference(s) in respect of which the demand has been made, together with counter claims or set off, given by the Railway, shall be referred to arbitration and other matters shall not be included in the reference. 64.(1)(iii) (a) The Arbitration proceedings shall be assumed to have commenced from the day, a written and valid demand for arbitration is received by the Railway. (b) The claimant shall submit his claim stating the facts supporting the claims alongwith all the relevant documents and the relief or remedy sought against each claim within a period of 30 days from the date of appointment of the Arbitral Tribunal. (c) The Railway shall submit its defence statement and counter claim(s), if any, within a period of 60 days of This is a digitally signed order.
The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above. The Order is downloaded from the DHC Server on 23/07/2026 at 11:35:57
receipt of copy of claims from Tribunal thereafter, unless otherwise extension has been granted by Tribunal. (d) Place of Arbitration : The place of arbitration would be within the geographical limits of the Division of the Railway where the cause of action arose or the Headquarters of the concerned Railway or any other place with the written consent of both the parties. 64.(1)(iv) No new claim shall be added during proceedings by either party. However, a party may amend or supplement the original claim or defence thereof during the course of arbitration proceedings subject to acceptance by Tribunal having due regard to the delay in making it. 64.(1)(v) .lf the contractor(s) does/do not prefer his/their specific and final claims in writing, within a period of90 days of receiving the intimation from the Railways that the final bill is ready for payment, he/they will be deemed to have waived his/their claim(s) and the Railway shall be discharged and released of all liabilities under the contract in respect of these claims. 64(2) Obligation During Pendency Of Arbitration : Work under the contract shall, unless otherwise directed by the Engineer, continue during the arbitration proceedings, and no payment due or payable by the Railway shall be withheld on account of such proceedings, provided, however, it shall be open for Arbitral Tribunal to consider and decide whether or not such work should continue during arbitration proceedings. 64(3) Appointment of Arbitrator: 64.(3)(a)(i) In cases where the total value of all claims in question added together does not exceed Rs. 25,00,000 (Rupees twenty five lakh only), the Arbitral Tribunal shall consist of a Sole Arbitrator who shall be a Gazetted Officer of Railway not below JA Grade, nominated by the General Manager.
The sole arbitrator shall be appointed within 60 days from the day when a written and valid demand for arbitration is received by GM. This is a digitally signed order. The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above. The Order is downloaded from the DHC Server on 23/07/2026 at 11:35:57
64.(3)(a)(ii) In cases not covered by the Clause 64(3)(a)(i), the Arbitral Tribunal shall consist of a Panel of three Gazetted Railway Officers not below JA Grade or 2 Railway Gazetted Officers not below JA Grade and a retired Railway Officer, retired not below the rank of SAG Officer, as the arbitrators. For this purpose, the Railway will send a panel of more than 3 names of Gazetted Railway Officers of one or more departments of the Railway which may also include the name(s) of retired Railway Officer(s) empanelled to work as Railway Arbitrator to the contractor within 60 days from the day when a written and valid demand for arbitration is received by the GM Contractor will be asked to suggest to General Manager at least 2 names out of the panel for appointment as contractor's nominee within 30 days from the date of dispatch of the request by Railway. The General Manager shall appoint at least one out of them as the contractor's nominee and will, also simultaneously appoint the balance number of arbitrators either from the panel or from outside the panel, duly indicating the 'presiding arbitrator' from amongst the 3 arbitrators so appointed. GM shall complete this exercise of appointing the Arbitral Tribunal within 30 days from the receipt of the names of contractor's nominees. While nominating the arbitrators, it will be necessary to ensure that one of them is from the Accounts Department. An officer of Selection Grade of the Accounts Department shall be considered of equal status to the officers in SA grade of other departments of the Railway for the purpose of appointment of arbitrator.
64.(3)(a)(iii) If one or more of the arbitrators appointed as above refuses to act as arbitrator, withdraws from his office as arbitrator, or vacates his/their office/offices or is/are unable or unwilling to perform his functions as arbitrator for any reason whatsoever or dies or in the opinion of the General Manager fails to act without undue delay, the General Manager shall appoint new arbitrator/arbitrators to act in his/their place in the same manner in which the earlier arbitrator/arbitrators had been appointed. Such reconstituted This is a digitally signed order. The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above. The Order is downloaded from the DHC Server on 23/07/2026 at 11:35:57
Tribunal may, at its discretion, proceed with the reference from the stage at which it was left by the previous arbitrator (s). 64.(3) (a)(iv) The Arbitral Tribunal shall have power to call for such evidence by way of affidavits or otherwise as the Arbitral Tribunal shall think proper, and it shall be the duty of the parties hereto to do or cause to be done all such things as may be necessary to enable the Arbitral Tribunal to make the award without any delay. The Arbitral Tribunal should record day to-day proceedings. The proceedings shall normally be conducted on the basis of documents and written statements. 64.(3) (a)(v) While appointing arbitrator(s) under SubClause (i), (ii) & (iii) above, due care shall be taken that he/they is/are not the one/those who had an opportunity to deal with the matters to which the contract relates or who in the course of his/their duties as Railway servant(s) expressed views on all or any of the matters under dispute or differences.
The proceedings of the Arbitral Tribunal or the award made by such Tribunal will, however, not be invalid merely for the reason that one or more arbitrator had, in the course of his service, opportunity to deal with the matters to which the contract relates or who in the course of his/their duties expressed views on all or any of the matters under dispute. 64.(3)(b)(i) The arbitral award shall state item wise, the sum and reasons upon which it is based. The analysis and reasons shall be detailed enough so that the award could be inferred therefrom. 64.(3)(b)(ii) A party may apply for corrections of any computational errors, any typographical or clerical errors or any other error of similar nature occurring in the award of a Tribunal and interpretation of a specific point of award to Tribunal within 60 days of receipt of the award. This is a digitally signed order. The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above. The Order is downloaded from the DHC Server on 23/07/2026 at 11:35:57
64.(3)(b)(iii) A party may apply to Tribunal within 60 days of receipt of award to make an additional award as to claims presented in the arbitral proceedings but omitted from the arbitral award. 64. (4) In case of the Tribunal, comprising of three Members, any ruling on award shall be made by a majority of Members of Tribunal. In the absence of such a majority, the views of the Presiding Arbitrator shall prevail. 64. (5) Where the arbitral award is for the payment of money, no interest shall be payable on whole or any part of the money for any period till the date on which the award is made. 64.(6) The cost of arbitration shall be borne by the respective parties.
The cost shall inter-alia include fee of the arbitrator(s), as per the rates fixed by Railway Board from time to time and the fee shall be borne equally by both the parties. Further, the fee payable to the arbitrator(s) would be governed by the instructions issued on the subject by Railway Board from time to time irrespective of the fact whether the arbitrator(s) is/are appointed by the Railway Administration or by the court of law unless specifically
directed by Hon 'ble court otherwise on the matter. 64.(7) Subject to the provisions of the aforesaid Arbitration and Conciliation Act 1996 and the rules thereunder and any statutory modifications thereof shall apply to the arbitration proceedings under this Clause.”
5. The clause 64 is unambiguous, the parties agreed for dispute resolution through arbitration. The petitioner has complied with the prerequisite of issuing notice under Section 21 of the Act. 6. The contention of the learned counsel for the respondent that there was an undertaking by the petitioner not to raise any further claim after receipt of the full and final payment and that the dispute was raised six This is a digitally signed order. The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above. The Order is downloaded from the DHC Server on 23/07/2026 at 11:35:57
months after acceptance of the final payment need not be gone into at the referral stage. Suffice to say that the claim is prima facie not time-barred, the fallout of the undertaking given by the petitioner not to raise any further claim is an issue that requires adducing of evidence and shall be decided by the arbitrator at an appropriate stage. 7. Since the GCC has an arbitration clause and a prima facie dispute exists between the parties, the petition is allowed by appointing Mr. J.K. Maheshwari, Supreme Court Judge (Retd.) (Mobile No. 9425112888) as the sole arbitrator for adjudication of the disputes which have arisen between the parties. 8. Arbitral proceedings will be held under the aegis of Delhi International Arbitration Centre (DIAC). Fee of the Arbitrator shall be fixed as per fee schedule. 9. Before entering upon reference, the learned Arbitrator will comply with Section 12 of the Act. 10. It is made clear that since this Court has not expressed any opinion on the merits of the rival claims of the parties and it will be open for the parties to file their respective claims/counter claims before the learned Arbitrator which will be considered in accordance with law. 11. A copy of this order be forwarded to the learned Arbitrator for information. AVNEESH JHINGAN, J JULY 20, 2026/‘JK’ This is a digitally signed order. The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above.
The Order is downloaded from the DHC Server on 23/07/2026 at 11:35:57