PRL PROJECTS AND INFRASTRUCTURE LIMITED v. AIRPORTS AUTHORITY OF INDIA
O.M.P.(MISC.)(COMM.)/509/2026 · 2026-07-17
Avneesh Jhingan
body2026
DailyLaw.ai
[ 2026 DAILYLAW 12225 (DEL) · dailylaw.ai ]
DailyLaw.ai
[ 2026 DAILYLAW 12225 (DEL) · dailylaw.ai ]
Judgment text
Extracted from the PDF above. The PDF is authoritative.
$~58 * IN THE HIGH COURT OF DELHI AT NEW DELHI + O.M.P.(MISC.)(COMM.) 509/2026
PRL PROJECTS AND INFRASTRUCTURE LIMITED
.....Petitioner Through: Ms. Anusuya Salwan, Ms. Nikita Salwan & Mr. Rachit Wadhwa, Advs.
versus
AIRPORTS AUTHORITY OF INDIA
.....Respondent
Through: Mr. Vaibhav Kalra, Adv.
CORAM:
HON'BLE MR. JUSTICE AVNEESH JHINGAN
O R D E R %
17.07.2026
1. This petition is filed under Section 29A of the Arbitration & Conciliation Act, 1996 seeking extension of period for concluding the arbitration proceedings.
2.
Learned counsel for the respondent has no serious objection to the prayer made.
3. In view of the above, the time period for conclusion of the proceedings is extended by nine months w.e.f. 21.05.2026 as prayed for.
4. This petition is disposed of in the aforesaid terms.
AVNEESH JHINGAN, J JULY 17, 2026 Ch
This is a digitally signed order. The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above. The Order is downloaded from the DHC Server on 20/07/2026 at 11:36:57