Extracted from the PDF above. The PDF is authoritative.
1
2026:CGHC:10942-DB
NAFR HIGH COURT OF CHHATTISGARH AT BILASPUR WA No. 196 of 2026 1 - South Eastern Coalfields Ltd. Through Its Chairman Cum Managing Director, Head Office, (Vasant Vihar Wrongly Mentioned In The Impugned Order) Seepat Road, Bilaspur, Chhattisgarh. 2 - Chief General Manager South Eastern Coalfields Ltd., Gavera Area, District - Korba, Chhattisgarh. 3 - General Manager South Eastern Coalfields Ltd., Gavera Area, District - Korba, Chhattisgarh. 4 - Senior Manager (Mining) South Eastern Coalfields Ltd., Gavera Area, District - Korba, Chhattisgarh.
... Appellants versus 1 - Vijay Kumar S/o Rati Yadav Aged About 27 Years R/o Gram- Naraibodh, Tahsil- Katghora, District- Korba, Chhattisgarh. 2 - Collector Korba, District - Korba, Chhattisgarh. 3 - Additional Tehsildar Katghora District - Korba, Chhattisgarh.
... Respondents (Cause-title taken from Case Information System) For Appellants : Mr. Sudhir Kumar Bajpai, Advocate For Respondents No.2 & 3 : Mr. Prasun Kumar Bhaduri, Deputy Advocate General Hon'ble Shri
Ramesh Sinha,
Chief Justice
Hon'ble
Shri
Ravindra Kumar Agrawal
, Judge
Judgment
on Board
Per
Ramesh Sinha
, Chief Justice
03.03.2026
1. Heard Mr. Sudhir Kumar Bajpai, learned counsel for the appellants on I.A. No.01, which is an application for condonation of delay of 159 days in preferring the present writ appeal. ANURADHA TIWARI Digitally signed by ANURADHA TIWARI Date: 2026.03.03 16:48:30 +0530
2
2.
Learned counsel for the appellants submits that the present writ appeal has been preferred against the order dated 07.07.2025 passed by the learned Single Judge in W.P.(S) No. 6250/2018; however, there has occurred a delay of 159 days in filing the same. He submits that the prescribed period of limitation for filing the writ appeal is 45 days and the delay is neither deliberate nor intentional but has occurred on account of procedural and administrative formalities inherent in a Public Sector Undertaking. It is contended that immediately after pronouncement of the impugned order, the appellants applied for a certified copy, which upon preparation was delivered to the counsel and thereafter forwarded to the concerned Area Office of South Eastern Coalfields Limited (SECL) for consideration.
3.
Learned counsel further submits that upon receipt and examination of the impugned order, the Area Office initiated the process for preferring an appeal and the matter was forwarded to the Headquarters of SECL at Bilaspur for approval. Since the appellants are a Government Company and decisions of this nature require scrutiny at multiple levels along with administrative sanction, some time was consumed in obtaining necessary permissions. After due approval was granted by the competent authority, the case file was handed over to counsel for drafting and filing of the appeal along with the present application for condonation of delay. It is thus submitted that the delay of 159 days has occurred due to bona fide and procedural reasons beyond the immediate control of the appellants. Being a Public Sector Undertaking, the decision-making process necessarily involves official
3 channels and compliance with departmental formalities. Therefore, in the interest of substantial justice, it is prayed that this Court may be pleased to condone the delay and decide the appeal on merits rather than dismissing it on technical grounds of limitation.
4.
Learned counsel appearing for the State/respondents No.2 and 3 opposes the application for condonation of delay and submits that the delay of 159 days in filing the present writ appeal is inordinate and has not been properly explained. It is contended that merely stating that the appellants are a Public Sector Undertaking and that the matter underwent departmental processing does not constitute sufficient cause within the meaning of the Limitation Act. No specific dates or particulars have been furnished to demonstrate due diligence at each stage, and the explanation offered is vague and general in nature. Learned counsel further submits that the law of limitation equally applies to Government departments and public undertakings, and administrative inefficiency cannot be a ground for condonation as a matter of course. Accordingly, it is prayed that the application for condonation of delay be rejected and, consequently, the writ appeal be dismissed as barred by limitation. 5. The Hon’ble Supreme Court in the matter of Postmaster General and others v. Living Media India Limited and another, (2012) 3 SCC 563, has dealt with the limitation issue and held as under:-
“27. It is not in dispute that the person(s) concerned were well aware or conversant with the issues involved including the prescribed period of limitation for taking up the matter by way of filing a special leave petition in this
4 Court. They cannot claim that they have a separate period of limitation when the Department was possessed with competent persons familiar with court proceedings. In the absence of plausible and acceptable explanation, we are posing a question why the delay is to be condoned mechanically merely because the Government or a wing of the Government is a party before us. 28. Though we are conscious of the fact that in a matter of condonation of delay when there was no gross negligence or deliberate inaction or lack of bonafide, a liberal concession has to be adopted to advance substantial justice, we are of the view that in the facts and circumstances, the Department cannot take advantage of various earlier decisions. The claim on account of impersonal machinery and inherited bureaucratic methodology of making several notes cannot be accepted in view of the modern technologies being used and available. The law of limitation undoubtedly binds everybody including the Government. 29.
In our view, it is the right time to inform all the government bodies, their agencies and instrumentalities that unless they have reasonable and acceptable explanation for the delay and there was bonafide effort, there is no need to accept the usual explanation that the file was kept pending for several months/years due to considerable degree of procedural red- tape in the process. The government departments are under a special obligation to ensure that they perform their duties with diligence and commitment. Condonation of delay is an exception and should not be used as an anticipated benefit for government departments. The law shelters everyone under the same light and should not be swirled for the benefit of a few. 30. Considering the fact that there was no proper explanation offered by the Department
5 for the delay except mentioning of various dates, according to us, the Department has miserably failed to give any acceptable and cogent reasons sufficient to condone such a huge delay. Accordingly, the appeals are liable to be dismissed on the ground of delay.”
6. Recently, the Hon’ble Supreme Court in the matter of State of Madhya Pradesh v. Ramkumar Choudhary, 2024 INSC 932, while considering the delay, issued some directions and observed as follows:-
“5. The legal position is that where a case has been presented in the Court beyond limitation, the petitioner has to explain the Court as to what was the "sufficient cause" which means an adequate and enough reason which prevented him to approach the Court within limitation. In Majji Sannemma v. Reddy Sridevi, 2021 SCC Online SC 1260, it was held by this Court that even though limitation may harshly affect the rights of a party, it has to be applied with all its rigour when prescribed by statute. A reference was also made to the decision of this Court in Ajay Dabra v. Pyare Ram, 2023 SCC Online 92 wherein, it was held as follows:
"13.
This Court in the case of Basawaraj v. Special Land Acquisition Officer [(2013) 14 SCC 81] while rejecting an application for condonation of delay for lack of sufficient cause has concluded in Paragraph 15 as follows:
“15. The law on the issue can be summarised to the effect that where a case has been presented in the court beyond limitation, the applicant has to explain the court as to what was the “sufficient cause” which means an adequate and enough reason which prevented him to approach the court within limitation. In case a party is found to be negligent, or for want of bona fide on his part in the facts and
6 circumstances of the case, or found to have not acted diligently or remained inactive, there cannot be a justified ground to condone the delay. No court could be justified in condoning such an inordinate delay by imposing any condition whatsoever. The application is to be decided only within the parameters laid down by this Court in regard to the condonation of delay. In case there was no sufficient cause to prevent a litigant to approach the court on time condoning the delay without any justification,
putting
any
condition whatsoever, amounts to passing an order in violation of the statutory provisions and it tantamounts to showing utter disregard to the legislature.”
14. Therefore, we are of the considered opinion that the High Court did not commit any mistake in dismissing the delay condonation application of the present appellant." Thus, it is crystal clear that the discretion to condone the delay has to be exercised judiciously based on facts and circumstances of each case and that, the expression 'sufficient cause' cannot be liberally interpreted, if negligence, inaction or lack of bona fides is attributed to the party. 5.1.
In Union of India v. Jahangir Byramji Jeejeebhoy (D) through his legal heir, 2024 INSC 262, wherein, one of us (J.B.Pardiwala, J) was a member, after referring to various decisions on the issue, it was in unequivocal terms observed by this Court that delay should not be excused as a matter of generosity and rendering substantial justice is not to cause prejudice to the opposite party. The relevant passage of the same is profitably extracted below:
“24. In the aforesaid circumstances, we made
7 it very clear that we are not going to look into the merits of the matter as long as we are not convinced that sufficient cause has been made out for condonation of such a long and inordinate delay. 25. It hardly matters whether a litigant is a private party or a State or Union of India when it comes to condoning the gross delay of more than 12 years. If the litigant chooses to approach the court long after the lapse of the time prescribed under the relevant provisions of the law, then he cannot turn around and say that no prejudice would be caused to either side by the delay being condoned. This litigation between the parties started sometime in 1981. We are in 2024. Almost 43 years have elapsed. However, till date the respondent has not been able to reap the fruits of his decree. It would be a mockery of justice if we condone the delay of 12 years and 158 days and once again ask the respondent to undergo the rigmarole of the legal proceedings. 26. The length of the delay is a relevant matter which the court must take into
consideration while considering whether the delay should be condoned or not. From the tenor of the approach of the appellants, it appears that they want to fix their own period of limitation for instituting the proceedings for which law has prescribed a period of limitation. Once it is held that a party has lost his right to have the matter considered on merits because of his own inaction for a long, it cannot be presumed to be non-deliberate delay and in such circumstances of the case, he cannot be heard to plead that the substantial justice deserves to be preferred as against the technical considerations. While considering the plea for condonation of delay, the court must not start with the merits of the main matter. The court owes a duty to first
8 ascertain the bona fides of the explanation offered by the party seeking condonation. It is only if the sufficient cause assigned by the litigant and the opposition of the other side is equally balanced that the court may bring into aid the merits of the matter for the purpose of condoning the delay.
27. We are of the view that the question of limitation is not merely a technical
consideration. The rules of limitation are based on the principles of sound public policy and principles of equity. We should not keep the ‘Sword of Damocles’ hanging over the head of the respondent for indefinite period of time to be determined at the whims and fancies of the appellants. xxx xxx xxx
34. In view of the aforesaid, we have reached to the conclusion that the High Court committed no error much less any error of law in passing the impugned order. Even otherwise, the High Court was exercising its supervisory jurisdiction under Article 227 of the Constitution of India.
35. In a plethora of decisions of this Court, it has been said that delay should not be excused as a matter of generosity. Rendering substantial justice is not to cause prejudice to the opposite party. The appellants have failed to prove that they were reasonably diligent in prosecuting the matter and this vital test for condoning the delay is not satisfied in this case.
36. For all the foregoing reasons, this appeal fails and is hereby dismissed. There shall be no order as to costs.” Applying the above legal proposition to the
facts of the present case, we are of the opinion that the High Court correctly refused to condone the delay and dismissed the appeal
9 by observing that such inordinate delay was not explained satisfactorily, no sufficient cause was shown for the same, and no plausible reason was put forth by the State. Therefore, we are inclined to reject this petition at the threshold. 6. At the same time, we cannot simply brush aside the delay occurred in preferring the second appeal, due to callous and lackadaisical attitude on the part of the officials functioning in the State machinery. Though the Government adopts systematic approach in handling the legal issues and preferring the petitions/applications/appeals well within the time, due to the fault on the part of the officials in merely communicating the information on time, huge revenue loss will be caused to the Government exchequer. The present case is one such case, wherein, enormous delay of 1788 days occasioned in preferring the second appeal due to the lapses on the part of the officials functioning under the State, though valuable Government lands were involved. Therefore, we direct the State to streamline the machinery touching the legal issues, offering legal opinion, filing of cases before the Tribunal / Courts, etc., fix the responsibility on the officer(s) concerned, and penalize the officer(s), who is/are responsible for delay, deviation, lapses, etc., if any, to the value of the loss caused to the Government. Such direction will have to be followed by all the States scrupulously. 7. There is one another aspect of the matter which we must not ignore or overlook. Over a period of time, we have noticed that whenever there is a plea for condonation of delay be it at the instance of a private litigant or State the delay is sought to be explained right from the time, the limitation starts and if there is a delay of say 2 years or 3 years or 4 years till the end of the same. For example if the period of limitation is 90 days then the party seeking
10 condonation has to explain why it was unable to institute the proceedings within that period of limitation. What events occurred after the 91st day till the last is of no consequence.
The court is required to consider what came in the way of the party that it was unable to file it between the 1st day and the 90th day. It is true that a party is entitled to wait until the last day of limitation for filing an appeal. But when it allows the limitation to expire and pleads sufficient cause for not filing the appeal earlier, the sufficient cause must establish that because of some event or circumstance arising before the limitation expired it was not possible to file the appeal within time. No event or circumstance arising after the expiry of limitation can constitute such sufficient cause. There may be events or circumstances subsequent to the expiry of limitation which may further delay the filing of the appeal. But that the limitation has been allowed to expire without the appeal being filed must be traced to a cause arising within the period of limitation. (See: Ajit Singh Thakur Singh and Another v. State of Gujarat, AIR 1981 SC 733).”
7. Taking into account the facts and circumstances of the present case, in the light of aforementioned judgments of the Hon’ble Supreme Court in the matters of Postmaster General (supra) and Ramkumar Choudhary (supra), it is evident that Government Departments/Public Sector Undertakings are under a special obligation to discharge their duties with due diligence and commitment. Condonation of delay is an exception, not the rule, and cannot be claimed as a matter of right or anticipated privilege by Government Entities/Public Sector Undertakings. The law casts its protection equally upon all litigants and cannot be distorted to confer undue advantage upon a select few. 11
8. Upon considering the matter in its entirety and in light of the chronology placed on record, we find that the impugned order was passed on 07.07.2025, whereas the present writ appeal has been filed after a delay of 159 days beyond the prescribed period of limitation of 45 days under Section 2(1) of the Chhattisgarh High Court (Appeal to Division Bench) Act, 2006.
Though the appellants have attempted to explain the delay by referring to procurement of certified copy, movement of the file from the Area Office to the Headquarters of SECL at Bilaspur, and grant of administrative approval, the explanation offered is general and routine in nature. The chronology essentially discloses internal correspondence and official formalities, but no specific material has been brought on record to show diligent and time-bound steps taken within the statutory period. The reasons assigned do not constitute sufficient cause within the meaning of law for condoning such delay. 9. It is well settled that the law of limitation binds Government bodies and Public Sector Undertakings equally, and administrative or bureaucratic procedures cannot be accepted as a ground for condonation as a matter of course. The appellants have failed to demonstrate any exceptional, unavoidable or compelling circumstance which prevented them from filing the appeal within the prescribed limitation. The explanation, being vague and unsupported by cogent particulars, does not justify exercise of discretionary jurisdiction in favour of the appellants. 12
10. This Court is further of the considered view that the pleadings made in the application for condonation of delay are wholly unsatisfactory and lack bona fides. The grounds urged are stereotyped and appear to have been taken in a routine manner. A Public Sector Undertaking, equipped with a full-fledged administrative and legal machinery, is expected to act with promptitude and responsibility. Instead, the conduct reflected from the record indicates a casual approach and prolonged inaction, as if the appellants had gone into deep slumber after passing of the impugned order. Such indifference cannot be rewarded by condoning substantial delay. 11. In view of the aforesaid discussion, we are not inclined to condone the delay of 159 days in filing the writ appeal. Consequently, the application for condonation of delay is rejected. As a result, the writ appeal stands dismissed on the ground of delay and laches, without entering into the merits of the case.
Sd/- Sd/- (Ravindra Kumar Agrawal) (Ramesh Sinha) Judge Chief Justice Anu