N G INFRA BUILDTECH PVT LTD v. GANNON DUNKERLEY AND CO LTD
O.M.P.(MISC.)(COMM.)/286/2026 · 2026-04-01
Avneesh Jhingan
body2026
DailyLaw.ai
[ 2026 DAILYLAW 1030 (DEL) · dailylaw.ai ]
DailyLaw.ai
[ 2026 DAILYLAW 1030 (DEL) · dailylaw.ai ]
Judgment text
Extracted from the PDF above. The PDF is authoritative.
$~44 * IN THE HIGH COURT OF DELHI AT NEW DELHI + O.M.P.(MISC.)(COMM.) 286/2026 & I.A. 8650/2026
N G INFRA BUILDTECH PVT LTD
.....Petitioner Through: Mr. Jeevesh Nagrath, Sr. Adv. with Mr. Ayush Beotra, Adv.
versus
GANNON DUNKERLEY AND CO LTD
.....Respondent
Through: Mr. Vaibhav Tyagi, Adv.
CORAM:
HON'BLE MR. JUSTICE AVNEESH JHINGAN
O R D E R %
01.04.2026
1. This petition is filed under Section 29A of the Arbitration and Conciliation Act, 1996 seeking extension of period for concluding the arbitration proceedings.
2.
Learned counsel for the respondent has no serious objection to the prayer made.
3. In view of the above, the time period for conclusion of the proceedings is extended by nine months as prayed for.
4. This petition is disposed of in the aforesaid terms.
AVNEESH JHINGAN, J APRIL 1, 2026 Ch
This is a digitally signed order. The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above. The Order is downloaded from the DHC Server on 06/04/2026 at 10:58:46